Majority
OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be affirmed, with costs.
Plaintiff commenced this proceeding against defendants Huber Construction, Inc. and Littleton/Huber Joint Venture seeking, as relevant to this appeal, a portion of the management fees collected by Huber as part of the payment for projects completed by the parties in connection with the joint venture. Defendants moved for summary judgment dismissing the complaint. Resolution of the motion rested on the validity and interpretation of various documents alleged to govern the parties’ relationship. Supreme Court partially granted defendants’ motion to the extent that it dismissed all causes of action except the one seeking recovery of a portion of the manage
Regardless of which party created the joint venture’s purported operating agreement, defendants met their initial burden of establishing that such document was not executed by Huber. Plaintiff failed to raise a triable issue of fact in response. The joint venture, therefore, could not be governed by the terms of that unenforceable document (see Gilbert Frank Corp. v Federal Ins. Co., 70 NY2d 966 , 967 [1988]).
With the operating agreement invalidated, the governing contract was the parties’ memorandum of understanding, which was indisputably signed by both parties. If a contract is complete, clear and unambiguous, it must be enforced according to its plain meaning (see Beardslee v Inflection Energy, LLC, 25 NY3d 150 , 157 [2015]; Schron v Troutman Sanders LLP, 20 NY3d 430 , 432 [2013]). The memorandum of understanding plainly provides for a 9% management fee to Huber, which Huber was not required to share with plaintiff. Thus, under the terms of that agreement, defendants were entitled to summary judgment dismissing plaintiff’s cause of action seeking a portion of the management fees. Plaintiff’s remaining arguments are lacking in merit.
Chief Judge DiFiore and Judges Pigott, Rivera, Abdus-Salaam, Stein and Garcia concur; Judge Fahey taking no part.
Order affirmed, with costs, in a memorandum.
Cases cited
- Littleton Construction Ltd. v. Huber Construction, Inc. 125 AD3d 1404 p. 1083
- Gilbert Frank Corp. v. Federal Insurance 70 NY2d 966 at 967 p. 1083
- Beardslee v. Inflection Energy, LLC 25 NY3d 150 at 157 p. 1083
- Schron v. Troutman Sanders LLP 20 NY3d 430 at 432 p. 1083