Majority
Headnote
1. Municipal Cobpobations — Conteacts fob Stbeet Impbovement — Consteuction—Delay of Pbbfobmance.The action was brought to recover $1,990, balance due under a contract for grading, curbing, etc., Longwood avenue, from Tiffany street to the Southern Boulevard. It is conceded that the amount earned under the contract was $27,714.47, of which there was paid to the plaintiff $26,874.48, leaving a balance of $1,990, for which the plaintiff sues. The city in its answer alleges that it was entitled to deduct from the amount earned under the contract $1,840, being liquidated damages for 184 days overtime, at $10 a day. It will be seen from these figures that the plaintiff in any event is entitled to $150, which was the amount retained over and above the amount which the city insists it had the right to deduct, so that for that amount the plaintiff is in any event entitled to recover. The learned trial judge at the close of the case directed a verdict in favor of the plaintiff for the full amount, and the question presented for our consideration upon this appeal is whether that direction was right as to the $1,840 which was deducted by the city for overtime.
In directing a verdict for the plaintiff the learned trial judge stated that the certificate of the borough president was erroneous in principle and that it was “wrong, untrue, and made under a misconstruction of the terms of the contract”; and he stated that he gave much weight to the fact that there was an omission in the certificate with reference to Sundays and holidays, and that upon the whole case the plaintiff was entitled to recover the amount claimed. It will be noticed, therefore, that the controversy upon the trial turned upon the question as to whether the certificate of the borough president, upon whom was imposed the duty of certifying as to the time expended in doing the work, was erroneous and the result of a misconstruction of the provisions of the contract. In order to determine whether the conclusion reached at the Trial Term was right, it is necessary that we should refer to some of the provisions of the contract.
It was therein agreed by the plaintiff that he should finish the work within 250 working days after notice given to commence.the work, and that in the computation of said days “the time * * * during which the work required by this contract has been delayed in consequence of the condition of the weather, or by any act or omission on the part of the parties of the first part (all of which shall be determined by the said commissioner, who will certify to the same in writing), and also Sundays and holidays on which no work was done, and days on which the prosecution of the whole work is suspended by order of said commissioner, shall be excluded.” It was also provided that:
“Mason work of all kinds * * * Including laying of vitrified stoneware and all work in setting curbstones and laying flagging and bridge stones shall cease from the 1st of December to the 1st of April in each year.”
Also any incumbrances or obstructions which may be upon the line of the work when it is begun or may thereafter be placed there shall, if directed by the engineer, be removed by the contractor at his own expense.
With respect to the latter, namely, the obstructions which the contractor was obliged to remove at his own expense, it was made to appear' that there was a building standing on the line of the proposed improve
From the certificate of the borough president given as required by the contract, it appears that there were—:
250 days allowed to complete the work.
202 days allowed for unsuitable weather.
447% days allowed for unavoidable delays.
days allowed for inspection not chargeable to contractor.
184 days chargeable to contractor.
1,083% days inspector’s time on the work.
1,083% days.
But the actual number of calendar days taken for the completion according to the respondent was 1,717 days. He claims that there should be deducted for Sundays and holidays and the winter months 678 days, which number deducted from 1,717 leaves 1,039 days. This result approximates sufficiently close to the whole number of days charged in the certificate under “inspection days” as 1083^2 to make it evident that Sundays, holidays, and winter months were deducted, the discrepancy being explainable either upon the ground of error or upon the ground that there was certain work done during the winter months, to the contrary of which the plaintiff was not able to testify.
The delays occasioned by fault of the city were estimated by the engineers, and the time account by that estimate and report stood as follows :
By encroachment of building .................................... 50 days
“ delay of N. Y. N. H. & H. R. R. Co..........................20 days
“ “ in moving poles ...................................... 10 days
“ “ from laying of water pipes..........*..................20 days
100 days
Time of inspector on work ...................................... 1,072%
Time allowed on contract..............................250 days
Unsuitable weather ..................................196% days
Allowance for delays ................................100 days
- 546%
526
Notwithstanding this estimate, the city concluded that as damage only to the extent of what had been paid an inspector during this time at the rate of $3.50 per day could be deducted, viz., $1,844.50, that the contract- or should be charged only with that amount, and therefore the overtime was reduced to 184 days, and to reach a balance the allowance for "unavoidable delay” was raised to 447J4 days. The figures are slightly changed in the final certificate, due no doubt to some minor error in computation. This was a construction of the contract most favorable to the contractor, being an allowance of 343 days in excess of the chief engineer’s estimate.
The contract, moreover, provided that:
“To prevent all disputes and litigation, it is further agreed between the parties to this contract that the Ohief Engineer of Construction shall in all cases determine the amount or the quantity of the several kinds of work which are to be paid for under this contract, and he shall determine all questions in relation to said work and the construction thereof, and he shall in all cases decide every question which may arise relative to the execution of this contract on the part of the aforesaid contractor.”
But assuming, without deciding, that the certificate being shown to be so indefinite and uncertain that it could be disregarded, and looking behind it, we think there was a question as to the amount of overtime for which the contractor should be charged. Taking the view most favorable to the respondent of time elapsed and credits for delays, the time sheet would be:
Whole number of days ...................................... 1,717
Time allowed .......................................... 250
Claimed for delays ............................... 535
Sundays and holidays ................................. 286
Winter months ....................................... 392
Unsuitable weather .................................... 202
1,665 1,665
Overtime .............................................. 52 days.
It will thus be seen upon this record that there was presented a disputed question of fact as to the overtime, which should have been submitted to the jury, and for the error, therefore, in directing a verdict, the judgment should be reversed and a new trial ordered, with costs to the appellant to abide the event. All concur.