Municipal Coepobations—Public Improvements—Sewers—Contract.The city of New York, for the purpose ©f sewering its Twenty-Third and Twenty-Fourth Wards, or a portion thereof, provided for the construction of a system of sewers, to consist of a main branch and several lateral sewers emptying into it, all of which were delineated on a map or plan. After the map had been filed the city advertised for bids for the construction of the main sewer, extending in the West Farms Road from Edgewater Road to Boston Road, and in Boston Road from West Farms Road to East 182d street, and in East 178th street from Boston Road to Southern Boulevard, and in Southern Boulevard from East 175th street to Pelham avenue; and in the advertisement attention was called to the map or plan, specification, and location of the work, and notice given that “bidders must satisfy themselves by personal examination of the location of the proposed work” before bidding, and that the prices bid for the construction would include the work necessary for the “proper protection of the work from water,” as well as “the cost of furnishing and operating all pumps
The plaintiff fully performed his contract and was paid therefor up- ■ wards of $300,000. Subsequently he commenced this action to recover damages, amounting to between $29,000 and $30,000, alleged to have been sustained by him by reason of the act of the city in permitting water to flow upon his work from the lateral sewers, which were constructed prior to the completion of his contract. The answer put in issue the material allegations of the complaint upon which the right to recover was predicated. At the trial it appeared that, subsequent to the execution of the plaintiff’s contract, the city entered into other contracts for the construction of six lateral sewers; that they were constructed prior to the completion of plaintiff’s work; and that water did in fact flow therefrom upon plaintiff’s work, or percolate through the adjacent soil, causing him damage. The trial court, however, at the conclusion of plaintiff’s case, concluded this did not entitle him to recover under the terms of his contract, and dismissed the complaint, directing the exceptions taken thereto to be heard in the first instance at the Appellate Division.
I am of the opinion the complaint was properly dismissed. The plaintiff’s work was but a part of the work adopted by the city for the construction of a system of sewers, and that other contracts were to be let was clearly contemplated, and provision made therefor in case such other contracts should be completed prior to the work which plaintiff contracted to do and perform. The sewer which plaintiff was to con
It seems to me clear the acts of which plaintiff now complains, and which he alleges caused him damage, were not due to any act of omission or commission on the part of the city, but were the direct consequence of the performance of his work and for which he had specifically stipulated. In addition to the foregoing, it would seem, if the plaintiff had performed his contract within the stipulated time, his work would have been completed before the construction of the lateral sewers, in which event no damage would have been sustained by him.
I am of the opinion, therefore, that the exceptions are not well taken, for which reason the same should be overruled, and the motion for a new trial denied, with costs. All concur.