Majority
Headnote
Contracts—Construction—Compensation.On the 1st of July, 1897, the plaintiff entered into a contract with the mayor, aldermen, and commonalty of the city óf New York, by which he agreed “to furnish plans and working drawings, with specifications therefor, prepare the same for public letting, and supervise the construction and inspect the materials for the construction of the viaduct connecting Melrose and Webster avenues,” in consideration of the city paying to him “the sum of 5 per cent, of the total cost of the construction of said viaduct.” On the 30th of December following, the city entered into a contract with the firm of Stevens & O’Rourke, by which said firm agreed to construct the viaduct; but, as this contract is not set forth in the record, we are unable to examine its terms. It appears, however, that the plaintiff furnished the plans and specifications for the work, prepared the same for letting, supervised the construction, and inspected the materials for the viaduct, as required by his contract; that the work required to be performed by Stevens & O’Rourke was completed on the 13th of August, 1901, and accepted by the city, and the contractors paid the sum of $166,298.09; that on the 18th of October, 1901, the plaintiff rendered a bill to the city for the balance due him under his contract, which was paid, and the bill receipted in full; that subsequently Stevens & O’Rourke recovered a judgment against the city, after a trial before a referee, who found that the city had broken its contract with that firm, in that it had failed to permit the firm to commence the work and prosecute the same as provided in its contract, and that such delay had caused the firm damage by reason of the advance in price of granite and iron, to the amount of $53,82-1.06, for which sum, with interest, judgment was directed; that thereafter the judgment was paid, and the plaintiff in this action then presented a claim to the city for 5 per cent, of the amount thereof, alleging that this was a part of the cost of the construction of the viaduct, within the meaning of his contract; that the claim was rejected, and this action brought. At the conclusion of the trial, by consent of parties, the jury was discharged and the case disposed of by the trial judge, who found in favor of the plaintiff for the full amount claimed, and defendant has appealed.
I am of the opinion the judgment should be reversed. The plaintiff’s contract was for 5 per cent, of the total cost of the construction of the viaduct. What did the parties have in mind when they agreed upon this method of fixing the compensation? Obviously the cost of construction as contemplated by the plans, specifications, and drawings made by plaintiff, and that this cost of construction was the amount paid the contractors on completion of the work seems to have been the view of the plaintiff himself. He was paid from time to time as the work progressed, and his receipt for the final balance, given October 18th, staged that it was "in full payment of the above account.” The bill then presented and the receipt for payment thereof clearly indicate the plaintiff’s understanding as to the meaning of the contract. Stevens & O’Rourke had been paid the full contract price, and the plaintiff had received 5 per cent, of the total cost of construction. It is diffi
The judgment appealed from, therefore, must be reversed, and a new trial ordered, with costs to appellant to abide event.
INGRAHAM and LAMBERT, JJ., concur.
HOUGHTON, J. I dissc ri. The contract of plaintiff with the defendant was that he was to have 5 per cent, on the total cost of the viaduct. The defendant treated the judgment obtained against it by the contractor as an addition to the cost of the structure. Defendant was authorized by law to issue bonds for the building of the viaduct. It paid the judgment by a sale of such bonds. If the judgment had been for mere damages, it would have had no authority to do this, but must have paid it from the general funds of the city. By its own interpretation of the transaction and of the contract, therefore, the amount represented by the judgment was an addition to the cost of the work.
I think the defendant is bound by this, and that the plaintiff is entitled to his percentage on the thus conceded total cost, and that the judgment should be affirmed.
PATTERSON, P. J„ concurs.
Cases cited
- Gearty v. Mayor of New York 171 N. Y. 61 at 63 p. 731