Majority
Headnote
Abbitbation and Award—Agreements to Arbitrate—Ousting Jurisdiction ' on Coubts.John W. Ferguson had a contract for the cpnstruction of a building for the Hamilton Trust Company, of Paterson, N. J. Plans for the same were made by one H. G. Stephens, architect. The firm of D. S. Hess & Co., these defendants, were subcontractors under Ferguson. The plaintiff, doing business as the Empire Brass & Metal Works, entered into a contract with the defendants on July 31, 1902, for the performance of certain work and the furnishing of certain materials in the construction of the metal work of iron, polished and electro-plated, for the said Hamilton Trust Company’s building. By the terms of the original contract this work was to have been completed on the 25th day of October, 19Ó2. This provision was waived by mutual consent November 11,1902, and the contract was modified by making a change in the materials to be used at an additional cost to the defendants of $3,000, which brought the contract up to $10,750. This modified contract fixed no date for the completion of the work. The original contract, after stipulating that the subcontractor (the plaintiff) should “well and sufficiently perform and finish in a thorough and workmanlike manner * * * all metal work of iron,” etc., “under the direction and to the satisfaction of the general contractors [these defendants] and H. G. Stephens, architect, * * * agreeably to the drawings and specifications made by the said architect,” provided in the third clause that:
“Should any alteration be required in the work shown or described in the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall tie made by the general contractors, and the sum hereinafter agreed to be paid for the work according to the original specifications shall be increased or diminished as the case may be.”
It was further provided that:
“In case such valuation' is not agreed to, the subcontractor shall proceed with the alteration upon the written order of the general contractors, and the valuation of the work added or omitted shall be referred to three (3) arbitrators, * * * the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one-half of the expense of such reference.”
It is clear that under the provisions of this clause the plaintiff could do no extra work for which he could make a charge, except upon the written directions of the defendants. In case the defendants gave such
“It is perfectly agreeable to us to leave all questions as to the interpretation of the plans and specifications to Mr. .John W. Ferguson for his decision. This refers only to matters which have not been decided up to that date. It is also agreed that Mr. Ferguson’s decision shall be final. If this is your understanding of the matter, kindly send us your acceptance of same, and we will procéed with all drawings or instructions which are given u's in writing affecting the work on the Hamilton Trust Company in Paterson, N. J.', without raising any question, no matter whether it is according to contract or not.”
On the 27th day of February, two days later, the defendants wrote to the plaintiff:
“We are agreeable to leaving undecided questions in relation to the above work, to the decision of Mr. John W. Ferguson, but do not desire that work be proceeded with upon this building which might be construed as additional work without a written notice to that effect from you.”
On the 28th day of February the plaintiff acquiesced in the suggestion that the extra work for which a claim was to be made should be stated in writing to the defendants, at the same time enumerating the items for which he would ask Mr. Ferguson to award “an extra,” which embraced “the iron work which goes above the frames which we made for the revolving doors,” “register facings,” and “the trouble and expense we have been put to, owing to the fault of some one in setting those revolving windows, without authority from us.” It was declared in this communication that “this covers all the points which have not been settled between ourselves”; the defendants being requested, if there was any of this work to be-stopped, to notify the plaintiff at once.
The practical result accomplished here is, not a waiver of the provisions of the third clause of the contract, but a modification of the contract, to make it a workable agreement. The parties could not agree as to what constituted the alterations provided for in that clause, and to obviate this difficulty the)’' agreed between themselves that Mr. Ferguson should determine the construction to be .placed upon the provisions. He was to determine whether the work was called for under the contract, or whether it was extra; and while this, under the exact lan
The principal item for extras for which the plaintiff recovered before the referee, and upon this appeal seeks to sustain, was set forth in the eighth cause of action of the complaint. After alleging the formalities of performance, the complaint continues:
“That upon the completion of the contract, as hereinbefore set forth, plaintiff submitted the question as to the valuation of such additional work to John W. Ferguson. That the said John W. Ferguson refused to pass upon said item, without passing upon all items in dispute directly between the plaintiff and the said John W. Ferguson. That the plaintiff notified the defendants of the action of the said Ferguson, and that he would not be bound thereby. That thereafter the plaintiff offered to refer to three arbitrators, as provided in said contract, the question of the kind, character, and valuation of such additional work. That thereupon defendants refused to refer to three' arbitrators, as provided in said contract, the questions of the kind, character, and valuation of such additional work.”
The pleader then alleges reasonable valuation, and asks for judgment for the amount. The answer puts these matters in issue. We examine the record in vain' for any evidence to show that John W. Ferguson refused to pass upon the matters submitted to him by the plaintiff, except upon condition that he should pass.upon other matters pending between himself and the plaintiff. It is true that the plaintiff in his letter refuses to go on with the arbitration, and alleges that the arbitrator refused to consider matters, except in connection with others in which he was interested; but this is not evidence of that fact. It clearly appears from the record that the only matters before Mr. Ferguson were .such as the plaintiff voluntarily placed before him. There is no evidence which warrants the conclusion that Mr. Ferguson sought or undertook to pass upon any item or question which plaintiff did not voluntarily place before him. The evidence clearly discloses that the plaintiff knew neither more nor less of Mr. Ferguson at the
“While we do not see any obligation on our part to enter into any arbitration other than we have already agreed to, we are disposed to have the controversy between us settled as speedily and with as little inconvenience as possible to all concerned.”
Then followed a proposition to “arbitrate all questions between us, provided that the plaintiff would agree that the decision shall be final and binding and that judgment may be entered upon the decision.” Thereupon the plaintiff wrote to the defendants that:
“We do not see any reason for us now to deviate from the terms of the contract between us of July 31, 1902. That contract was good enough for us then, and is good enough for us now. On the basis of the terms of that contract we proceeded with our work, and on that basis we stand to-day. Clause 3 of that contract is specific, and in pursuance of that clause we request you now, for the last time, to-day, to name' us your representative for the arbitration provided for by that clause of the contract.”.
On the 3d day of December the plaintiff seems to have repented of this, and offers to arbitrate as suggested by the defendants; but nothing was ever done about it, and the plaintiff testified that he thought he had indicated that he would not act under this last letter. If we assume that the plaintiff had a right to repudiate this arbitration before Mr. Ferguson, and that the result of this repudiation would be to restore the original contract, it must be apparent that the offer of arbitration made by the plaintiff was not that provided for in clause 3 of such contract. That clause provided merely for arbitrators to determine the reasonable value of the work added or omitted, and not the determination of whether or not there was added or omitted work. That was to be evidenced by the written authority of the defendants. The plaintiff’s theory seems to be that he could have a modification of the contract, waiving the written authorization by the defendants, and at the same time have the benefit of the provisions for arbitrators to determine the valuation of the work which he claimed was extra. But this clearly never was within the contemplation of the
The suggestion that the defendants lost any rights by failing to protest when the plaintiff notified them that he refused to be bound by the arbitration of Mr. Ferguson is begging the question. They had agreed to submit to this arbitration. They had modified their contract in this respect. They had done no wrong. Their liability depended upon the plaintiff securing the awárd of the arbitrator; and, if he chose to repudiate the contract, it was no part of their duty to protest against it. But, as a matter of fact, they did offer to submit the whole question to three arbitrators, conditioned only that judgment might be entered upon the decision; and this the plaintiff refused, preferring to stand, as he said, upon the terms of the original contract. It now appears that with those terms he did not comply. There is no reason to suppose that-the defendants would not, if they had known of any misconduct on the part of Mr. Ferguson, have agreed to the substitution of some other person, if such suggestion had been made to them by the plaintiff; and as the duty and obligation of satisfying conditions precedent was upon the plaintiff, and he made no effort to comply with the letter or spirit of his modified contract, but asserted his right to go back to the original contract, he has only himself to
In this situation it is by the plaintiff suggested, on the authority of Seward v. City of Rochester, 109 N. Y. 164 , 16 N. E. 348 , that the determination of Mr. Ferguson as arbitrator was not a necessary condition precedent ,to the right of the plaintiff to recover. The proposition is that the agreement to arbitrate was such as to oust the courts of jurisdiction, and that it was void as against public policy. There can be no doubt of the rule that where parties undertake, by independent covenant or agreement, to provide for an adjustment and settlement of all disputes and differences by arbitration, to the exclusion of the courts, such agreement is void and does not stand in the way of recovery. The case cited is authority for that proposition. In the case at bar, however, there is no general agreement for the adjustment of controversies. There is a mere provision that the arbitrator shall determine whether work .is added or omitted under the contract, and the value of such work. When these questions have been determined, the courts have full authority to adjust the rights of the parties, and under such circumstances the jurisdiction of this state will be searched in vain, we believe, for a case holding-that such an agreement is void.' In the Seward Case, supra, the plaintiff entered into a written agreement with the water commissioners of the city of Rochester granting to them the right to lay iron pipes for the conveyance of water across his land, with the right to enter upon same for the purpose of making repairs. The city covenanted to pay him "a fair and just compensation for any damage” that might accrue “by the breaking, bursting, or leakage of said water pipes, or any of them, or from any other cause.” It was then agreed, as far as these possible and prospective damages were concerned, that, if the parties could not agree upon the amount of damages, these should “be appraised and fixed by two disinterested persons, one to be selected by each party, and, in case they could not agree, by an umpire to be selected by them, and the award of two of the three thus selected,” it was declared, “should be final and conclusive.” The discussion of the learned court points out clearly the objections to this clause—that it is a general provision, not confined to the rights created by the contract, but covering all possible injuries flowing fr.om the construction and maintenance of the pipes of every kind and class, and quotes with approval the discussion of the court in Delaware & Hudson Canal Co. v. Penn. Coal Co., 50 N. Y. 250 , as follows:
“In one class it is said the parties undertake by an independent covenant or agreement to provide for an adjustment and settlement of all disputes and
differences by arbitration, to the exclusion of the courts; and in the other they merely, by the same agreement which creates the liability and gives the "right, qualify the right, by providing that before a right of action shall accrue certain facts shall be determined or amounts or values ascertained, and this is made a condition precedent, either in terms or by necessary implication. * » e The agreement here belongs to the first class. It submits all controversies which may arise in the future out of the grant made to arbitration, totally irrespective ol\the question whether the rights sought to be vindicated shall prove to be the creation of the contract or have an independent existence under the law as administered by the courts,” etc.
The case at bar as clearly falls within the second class as the Seward Case, supra, fell within the first class. Here the only questions agreed to be submitted arise directly under the contract. The first is whether there is work added or omitted, as appears from the drawings and specifications; and the second is the reasonable valuation of such work added or omitted. The determination of these questions is clearly a condition precedent to any right of recovery on the part of the plaintiff under the modified contract, and the conditions named in the third clause are of a like nature, if the plaintiff elects to stand upon his original contract. In the case of Sweet v. Morrison, 116 N. Y. 19 , 22 N. E. 276 , 15 Am. St. Rep. 376 , the agreement was far more general and inclusive in its character, and the court not only approved the contract, but held that the award of the engineer, who was the arbitrator, could not be corrected upon the trial, although error might be shown. See O’Brien v. Mayor of New York, 139 N. Y. 543 , 35 N. E. 323 ; Byron v. Low, 109 N. Y. 291 , 16 N. E. 45 ; Hamilton v. Liverpool Ins. Co. 136 U. S. 242 , 10 Sup. Ct. 945 , 34 L. Ed. 419 .
In the case last above cited the court reiterates the rule that:
“Where parties, in their contract, fix upon a certain mode by wbicli the amount to be paid shall be ascertained, as in the present case, the party that seeks an enforcement of the agreement must show that he has done everything on his part which could be done to carry it into effect. He cannot compel the payment of the amount claimed unless he shall procure the kind of evidence required by the contract or show that by time or accident he is unable to do so.” Spink v. Co-operative Ins. Co., 25 App. Div. 484 . 49 N. Y. Supp. 730 .
The provision under consideration in National Contracting Co. v. Hudson River W. P. Co., 170 N. Y. 439 , 63 N. E. 450 , was certainly far more open to objection that it tended to oust the courts of jurisdiction than the contract here under consideration, yet the court on demurrer refused to sustain the contention that it was void; and, we believe the uniform authority of this country is in harmony with the views expressed.
If we are correct in these conclusions, it follows that the eighth cause of action must fail. The plaintiff fails to show an award on the part of the arbitrator agreed upon, or any justification in law for a failure to produce such evidence, and the written notice of claim by the plaintiff does not meet the requirements of the third clause of the original agreement that the work should be undertaken only upon the written authorization of the defendants. The Court of Appeals in Langley v. Rouss, 185 N. Y. 201 , 77 N.
Concurrence
A “provision that the builder is not to execute any extra work, or make any modifications or alterations in the work mentioned in the specifications and plans, unless ordered in writing by the engineer in charge, or claim payment for the same unless such written order be produced, is valid, and should be enforced.”
In the case at bar there were to be no extras, unless by agreement between the parties or upon the written authorization of the defendants, subject to an arbitration as to the value of the work; and this court is not at liberty to permit a recovery where the conditions mutually agreed upon have not been complied with.
We are equally clear that there is no valid foundation for the cause of action No. 7. There was no time limit in the modified contract. No notice was given at any time by the plaintiff that he would hold the defendants responsible for damages resulting from, delay because of their failure to perform. This was prerequisite .to a right of recovery for damages resulting from such a cause as is here claimed. In fact, the record does not disclose that the defendants were in default under the contract at any time, and that they are liable for delays such as are shown by the record.
The findings of the referee in respect to causes of action Nos. 1, 2, 3, 4, 5, and 6 may be said to be supported (though meager in instances) in the .testimony, and the judgment to that extent should not be disturbed.
The judgment should therefore be modified, by deducting $3,569.04 therefrom as of the date of entry, and, as so modified, affirmed, without costs.
INGRAHAM and EAUGHEIN, JJ., concur.
I concur in the reduction of-the judgment recovered in this action by the sum of $576, which the referee has allowed for damage suffered by the plaintiff on account of extra superintendence of work, which it is asserted was required in consequence of delay in the work caused by acts of the defendants. I am of the opinion that the evidence did not justify the referee in allowing that amount as an item of recovery by the plaintiff.
I am compelled, however, to dissent from the further reduction of the judgment by the sum of $¡3,993.04, which amount was allowed by the referee for extra work as claimed by the plaintiff. While it is true that, by the terms of the contract between the parties, written orders were required to authorize the performance of extra work, yet the evidence shows, satisfactorily to my mind, that such requirement was waived. That the work was performed, and that the defendants received and accepted it, is indisputable. During its progress the defendants agreed to submit the construction of the contract to arbitration. Pending that arbitration, it was disclosed that Mr. Eerguson, one óf the arbitrators, was personally interested in the determination of the question; for this work was evidently such as would either come within a contract to be performed by him or within the plaintiff’s contract, and thédatter with good reason objected to going on with the proceeding before one who was virtually an adverse party to him. It was not incumbent upon the
The judgment should be ^modified by deducting therefrom the amount of $576, and, as thus modified, affirmed, without costs in this court.
HOUGHTON, J., concurs.
Cases cited
- Seward v. City of Rochester 109 N. Y. 164 p. 656
- President of Delaware & Hudson Canal Co. v. Pennsylvania Coal Co. 50 N. Y. 250 p. 656
- Sweet v. Morrison 116 N. Y. 19 at 22 p. 657
- O'Brien v. Mayor of New York 139 N. Y. 543 p. 657
- Byron v. Low 109 N. Y. 291 p. 657
- Hamilton v. Liverpool, London & Globe Insurance 136 U. S. 242 p. 657
- National Contracting Co. v. Hudson River Water Power Co. 170 N. Y. 439 p. 657
- Langley v. Rouss 185 N. Y. 201 p. 657