Majority
Headnote
Municipal Corporations—Use op Streets—Authority to Grant.The question for our determination, presented by the record at bar, is purely one of power. The plaintiff Rapid Transit Subway Construction Company has contracted with the rapid transit commission to build a certain part of the system of subways now under construction, and the plaintiff Cranford & McNamee, as a subcontractor of its coplaintiff, has used, with the consent and pursuant to the permit of the rapid transit commission, parts of. certain streets in Brooklyn which cross the street under which the construction is now progressing; such use, it is fairly to be assumed from the affidavits, being reasonably necessary for the prompt and proper progress of the work. The occupation of such cross-streets is without the permit of the borough president of the borough of Brooklyn, or of its commissioner of public works. These latter officials have threatened to re
The rapid transit act (Laws 1891, p. 3, c. 4) bestows the most general grant of power upon the rapid transit commission when it provides (section 1) that it “shall have and exercise the specific authority and powers hereinafter conferred, and also such other and necessary powers as may be requisite to the efficient performance of the duties imposed upon the said board by this act.” Under this act (section 4) the board was required to determine whether or not “it is for the interest of the public and of the city in which it is appointed that a rapid .transit railway or railways for the conveyance and transportation off persons and property should be established therein,” and so “to determine and establish the route or routes thereof and the general plan of construction.” "Section 5 required the board to transmit the plans and conclusions it adopted to the common council of the city. If approved by the common council.and by any other local authority in which the exclusive supervision of any street, road, highway, or avenue which was to be used under the provisions of the law should be vested, and if a majority of property owners consented thereto, or failing that, a commission appointed by the Appellate Division of the Supreme Court should report in favor of the construction of the railroad and that report should be confirmed,-then by section 6 the board was required to prepare detailed plans and specifications for the construction of such railway in accordance with the general plan of construction. “Stations and station approaches,” section 6 provided, “may be under or over streets of the route or cross streets, and the board of aldermen, or other legislative body, of any such city shall have power to regulate by general •or special ordinance or resolution, the' erection, alteration and maintenance upon or in connection with any building used wholly or in part for station purposes, or approaches, or any and all structures or parts of structures extending over the whole or any part of any sidewalk or sidewalks adjacent thereto.” The board was further empowered from time to time to alter such detailed plans and specifications, “but always so that the same shall accord with the general plan of construction; but whenever a contract shall have been made for the construction of any railway herein provided for, no such alteration shall be made by the board without the consent of the contractor and his sureties, except as liberty shall have been reserved in such contract by said board for such alteration.” Lor the purpose of facilitating construction “and to diminish the period of occupancy of any street for the transportation of material” it was provided in section 33 that any contractor acting under a contract pursuant to this act might, with the approval of the rapid transit board, “lay upon or over the surface of any street, temporary tramways, to be used only for the removal of excavated materials or the transportation of material for use in' the construction.”
It is true that by sections 383 and 391 of the charter of the city oí New York (Laws 1897, pp., 139, 140, c. 378) the borough president has cognizance and control of the issue of permits to builders and others to use and open streets, and to those who seek to interfere with the pavement or disturb- the surface of streets for the usual purposes for which these acts are done; and it is likewise true that there is no specific language in the rapid transit act which in terms gives to the rapid transit commission the .power to issue permits for the occupation of cross-streets by those actually engaged in the construction of the subway for necessary purposes.. We think, however, that the whole tenor of.the act is to endow the commission with all powers necessary to effectuate the speedy, proper, and adequate construction of the subway. The'commission is created and is recognized as a distinct municipal agency, whose acts, authorized by specific enactment or by necessary implication, are as binding upon the municipality as authorized acts of the ordinary city officials. As we have observed,' the Legislature of 1894, in amending the act by the addition of section 34 and following, has imposed upon the- commission larger obligations, and incidentally larger powers. By section 34 it was provided that, in case the people should have determined by vote that a rapid transit railway should be constructed for and at. the expense of the city, it should be the duty of the board either to proceed with the construction of such railway or railways and to provide for the operation of the same, or to change and modify routes, or to adopt additional ones, etc.; that as soon as the requisite consents shall have been obtained for any rapid transit railroad, and the detail plans and specifications prepared as provided in section 6, “the said board, for and in behalf of said city, shall enter into a contract with any person, firm or corporation, which in the opinion of said board, shall be best qualified to fulfill and carry out said contract, for the construction of such road or roads upon the routes and in accordance with the plans and specifications so adopted, for such sum or sums of money, to be raised and-paid out of the treasury of said city, as hereinafter provided, and on such terms and conditions, not inconsistent with the aforesaid
“For the purpose of constructing or operating any road for the construction and operation of which a contract shall have been made by the board of rapid transit railroad commissioners, including necessary stations and station approaches, or for the purpose of operating or securing the operation of the same. * * ■■■ ”
The board, for and in behalf of the city, may acquire by conveyance or b)r condemnation “any real estate and any rights, terms and interest therein, any and all rights, privileges, franchises and easements, whether of owners or abutters, or others to interfere with the construction or operation of such road or to recover damages therefor, which, in the opinion of the board, it shall be necessary to acquire -or .extinguish for the purpose of constructing and operating such road free of interference or right of interference.” By section 38 the board is empowered to agree with the contractor in any such contract “upon changes in arid modifications of said contract, or of the plans and specifications upon which said road or roads is or are to be constructed,” but with the limitation that the routes and general plan provided for in section 5 shall not be changed or modified without the consent and authorization provided for in that section, nor shall the minimum rental to be paid to the city for the use of the road be reduced beyond that provided for in the statute.
It is apparent, from an examination of the sections to which we have referred and of other provisions contained in the act, that it was thq intent of the Legislature to confer upon the commission all of the necessary powers properly to construct the subway, and this, without the concurrent action of the ordinary municipal authorities, except where such action was specifically required by the act. The power to grant a valid permit to a contractor or subcontractor to occupy an adjacent part of cross-streets where such occupation is necessary in the prosecution of the work is, we think, an -incidental power which the commission possesses under the act; and the mere fact that this specific power is not among those enumerated by the Legislature does not alter the case, for, if the act had attempted in detail to enumerate all of the specific powers the commission might have, it would necessarily have partaken of the “prolixity of a legal code.”
It is urged on behalf of the appellants that subdivision 5 of section 2é of the act reserves to the ordinary municipal authorities the right to grant permits for the occupation of streets, such as the plaintiffs are indulging in. That subdivision provides:
“No such corporation shall have the right to acquire the use or occupancy of public parks or squares in such county, or the use and occupancy of any of the streets or avenues, except such as may have been designated for the route or routes of such railway, and except such temporary privileges as the proper authorities may grant to such corporations to facilitate such construction.”
The order continuing the injunction during the pendency of the action should, therefore, be affirmed.
Order affirmed, with $10 costs and disbursements. All concur.