Majority
Headnote
Action—Stay—Pendency of Another Action.Action is pending in this court to recover for work, labor, and services and for materials alleged to have been furnished by plaintiff as building contractors under contracts in writing and for breach of contract by defendants. The court has granted leave to serve a supplemental complaint setting up the discharge in bankruptcy in January, 1907, of one of the defendants upon condition that he'pay costs to date. About the same time as the commencement of this action, and in the year 1908, the plaintiff filed a notice of mechanic’s lien against the defendants and affecting the premises on which the work forming the basis of this action was done, and thereafter an action was commenced by the plaintiff herein against these defendants in the Supreme Court, New York county, to foreclose the mechanic’s lien. That action is now pending in the Supreme Court. The defendants bonded the lien, the sureties on the bond duly qualified, and the plaintiff in that action is preparing motion papers for leave to bring in the sureties as parties defendant and to prosecute that action. Motion is now made for a stay of the trial of the action pending in this court until after the trial of the action in the Supreme Court.
The statute which creates a lien upon real property for the benefit of contractors and materialmen is remedial, but the remedy is not exclusive and does not bar the lienor from pursuing any other or further remedy which he may have independent of the statute. He may pursue these remedies simultaneously, but he can have but one satisfaction of his claim.' The right of a plaintiff under ordinary circumstances to pursue his remedy for the- debt by common-law action" and at the same time to enforce his lien by foreclosure is well established. Power v. Onward Construction Co., 39 Misc. Rep. 708 , 80 N. Y. Supp. 950 ; Snyder’s Annotated Lien Laws (4th Ed.) p. 20, and cases cited. It has been held that, unless the decision in one action will determine all the rights set up in another and the judgment in the one disposes of the controversy in both, the court in the one action will not stay proceedings in the other. Nussberger v. Wasserman, 40 Mise. Rep. 120, 81 N. Y. Supp. 295 . It is clear that in the action now pending in the Supreme Court all the rights of these parties may be" determined, and the judgment there would dispose of the controversy in both actions. Under such circumstances, if sufficient cause appear, a stay of the action in this court may be granted. As the lien was acquired in 1903, the dischárge in bankruptcy in 1907 would not ordinarily be available as a defense in the action to foreclose the lien. Crane Co. v. Pneumatic Signal Co., 94 App. Div. 53 , 87 N. Y. Supp. 917 .
The foundation of every lien is a contract indebtedness, express or implied. Should the defendant Lustbader be permitted to proceed to trial upon the issue joined by the supplemental answer setting up his discharge in bankruptcy, such discharge would be a complete bar to the‘recovery of any judgment against him in this action. It is contended that such determination would be prejudicial to plaintiff’s rights in the foreclosure action in the Supreme Court, and plaintiff makes this motion for a stay. I have found no case in which the precise question
Settle order on notice.
Cases cited
- Holyoke v. Adams 59 N. Y. 233 p. 943