Majority
Headnote
Principal and Surety—Discharge of Surety—Change of Contract.The plaintiff in supplying itself with water made a contract for the construction of a pipe line 19,300 feet long. A section of it 2,200 feet long was to be laid in a deep tunnel instead of a deep trench, by a modification of the contract in which the surety joined. The contractors abandoned the work after doing part of it, and this action is against their surety on its bond for performance. The complaint was dismissed on the close of the plaintiff’s evidence on the ground that the pleaded defence that the plaintiff and the contractor changed the contract by an agreement made between them without the consent of the surety was made out. The claim is that the tunnel through the said section of 2,200 feet was changed in the detail of doing the work from a curved line to a straight line. The contract and specifications show that the pipe line was of 20-inch pipe and was to be laid in a right of way of the general width of 66 feet acquired by the city, the plaintiff. The map used to acquire the right of way showed the centre line thereof, but not the side lines. They were determinable by measurements from the centre line, the width of the right of way being given. This same map was used in the specifications and contract to show where the pipe line was to be laid. The centre line was all that it showed, as already stated, but the specifications, which with the map were made part of the contract, stated that the general width of the right of way for the pipe line was 66 feet. The contract does not say in words that the pipe line is to follow the said centre line, but the defendant, the surety, claims that that is the contract, nevertheless, by reason of the said map being part thereof.
This may be granted and still the dismissal would be error. The evidence, including the map, shows that the right of way over the said section of 2,200 feet curved or waved to right and then to left
When the strict letter of the contract is examined, it will also be seen that it is not that the trench and tunnel shall strictly adhere to the centre line, for it provides that the work shall be done under detail plans to be furnished by the engineer as it progresses, and that “the trenches shall be straight and curved as directed,” i. e., by him; and the substitution of the tunnel for the trench on the section in question left this still in force.
There is another reason why the dismissal was erroneous, even assuming that the original contract required the trench to follow the centre line. As has already been mentioned, the original contract requiring the pipe to be laid in a trench was by agreement of the parties and the surety changed by substituting a tunnel along the section in question. The change was a concession to the contractor and surety, it being for their benefit. The trench for most of the distance was to be from 30 to 35 feet- deep, all through rock excepting the top 13 feet, and the object of the change was to make the work less expensive. The agreement of change does not say the tunnel shall follow the centre line; it simply substitutes a tunnel for a trench, except that the tunnel is to be 9 feet lower than the trench. It would be easy enough to follow the centre line on the surface in digging the trench, but to follow that constantly curving line in building such a small tunnel through rock 39 to 44 feet below the surface would be a very different matter. The evidence is that it would be impracticable. Now the change from trench to tunnel carried with it all things necessary to make such change practicable. The parties did not mean an impracticable change. The contrary must be presumed. If it were possible at all to approximately excavate the tunnel through rock on the constant curve of the centre line, instead of on a straight line, or straight lines, the great nicety and difficulty of it would add greatly to the expense, whereas the object of the change was to lessen the expense. There was no reason to do so, and it would have been folly and detrimental to the contractor and the surety to do so.
When this case was here before ( 97 App. Div. 344 , 90 N. Y. Supp. 16 ), the record made it appear to us that there was a substantial departure from the contract in doing the work, to the injury of and which therefore released the surety, i. e., a “change of the route from that around the hill to the straightened line through it,” as our opinion says; and we properly concluded that such change “released the surety in the absence of its assent.” We now know from the present record that there was no such agreement or change, but that the contract was substantially performed.
The judgment should be reversed.
Judgment reversed, and new trial granted; costs to abide event. All concur, except HOOKER and RICH, JJ., who dissent.
Cases cited
- Glacius v. Black 50 N. Y. 145 p. 376
- Rowe v. Gerry 112 App. Div. 358 p. 376
- Smith v. Molleson 148 N. Y. 241 p. 376
- Ulster County Savings Institution v. Young 161 N. Y. 23 at 55 p. 376
- City of Middletown v. Ætna Indemnity Co. of Hartford 97 App. Div. 344 p. 377