1. Costs—Extra Allowance.In, the decision heretofore ■ rendered in this action it was held that the contract in question was canceled by the state, without sufficient cause, on the 20th of January, 1906. The cancellation of the contract being unlawful, the state is precluded from recovering damages against the contractors, and they would be entitled to recover whatever amount had been actually earned upon the contract at the time of its unlawful cancellation by the state. • If the amount which had been actually earned equaled the contract price, then the full amount could be recovered; and, if moneys had been actually earned under the contract at the time of the cancellation, the issuing of a certificate by the state architect certifying the amount due would not be necessary as a condition precedent to payment of such moneys earned,' for, if the contractors had earned a certain amount of money, and then the contract was unlawfully canceled by the state, they are surely entitled to recover from the state the amount actually earned upon the contract at the time of its cancellation. If the state is seemingly compelled to pay more than the unpaid balance of the contract price, it is for the reason that the state continued payment to the contractors after liens were filed without protecting itself against liens, of which it had due notice.
In that view of the case, it seems to me that the amount earned at the time of the unlawful cancellation of the contract was as follows:
The amount o£ certificate No. 19, which had been issued by the state architect, but not paid, amounting to the sum of...........'.....$ 7,452 77
The 15 per cent, reserve amounting, at the time, to................ 11,526 24
The value of the work performed during the month of January for which no certificate was issued................................ 6,150 00
The value of the extra work occasioned- by changes and deviations in, the contract...................................;............... 1,162 00
Total.......................................................§26,291 01
Add to this the amount heretofore paid upon the contract, which equals......................................................... 73,419 52
$99,710 53
Contract price.......................................$96,454 00
Extra work......................................... 1,162 00
- 97,616 00
Excess .....................................................$ 2,094 53
This excess deducted from.........................:.............$26,291 01
2,094 53
Leaves a balance of..........................................$24,196 48
This amount the contractors had actually earned under their contract at the time of its unlawful cancellation, when they were driven from the work by the action of the state authorities.
The plaintiff and a large number of the defendants, lienors, ask for costs, and the plaintiff asks for an extra allowance. This case was in some respects difficult, and in a good many respects extraordinary. Costs are in the discretion of the court (Code Civ. Proc. §§ 3230, 3411), and it can also grant an extra- allowance in cases of this character (Code Civ. Proc. § 3253; Horgan v. McKenzie [Com. Pl.] 17 N. Y.
As to the various other applications for allowances of costs in this matter, it appears that, excepting the counsel who have been granted allowances as above stated, their labors consisted of making formal proofs of the liens represented by them, and it does not seem to be proper to award costs, except as above. Ottman v. Schenectady Realty Co., 119 App. Div. 736 , 104 N. Y. Supp. 137 ,
While the case was difficult and extraordinary, the labor was performed very largely by the plaintiff’s attorneys and by Messrs. Peck & Whitbeck, E. M. Whitney, and James A. Van Voast; and, so far as I am advised, the labors of other counsel engaged in the case were confined principally to making formal proofs of their respective claims, and for that reason, costs should not be allowed.
As to the claim between the trustee in bankruptcy arid the state, the jurisdiction of the court to pass upon that seems somewhat doubtful and it is therefore not determined here, but additional findings may be submitted, to the effect that on January 20, 1906, the state canceled the contract in question without good and sufficient cause, and that such cancellation was wrongful; also, that there became due to the contractor upon such cancellation sums which had been earned by them under the contract, and were unpaid, aggregating at least the sum of $24,196.48, with interest thereon from the date of the "cancellation of the contract. Costs to be. allowed as above indicated.
Cases cited
- Carney v. Reilly 18 Misc. Rep. 11 at 40 p. 329