Sales—Contract—Performance—Time. Defendant on April 28, 1903, ordered by letter from plaintiff a certain number of frames to be delivered within six weeks. This order was accepted, and on May 8th defendant ordered another lot of frames, writing on the foot of his letter of April 28th: “Note. Increase the above order to 5 M. of each.” Held, that the second order should be construed as made on the' same terms as the first, and that plaintiff was bound to de- • liver all the goods within six weeks.The action is for breach of contract. On April 28, 1903, defendant wrote to plaintiff, ordering a certain number of frames to be delivered within six weeks. On April 29th plaintiff wrote in reply, guaranteeing delivery of the frames within six weeks. These frames were so delivered, and as to them no dispute arises. On May 8th defendant went to plaintiff’s factory and ordered another lot of frames, writing on the foot of defendant’s letter of April 28th these words:
“Note. Increase the above order to 5 M. of each, and to be made paneled with pictures supplied.”
It seems to us that the second order must be construed as being made on the same terms as the first, and that the goods were to be delivered within six weeks, and that plaintiff accepted the order with this understanding.
The judgment must be reversed, and a new trial ordered, with costs to appellant to abide the event.