Majority
Headnote
Contracts—Partial Performance.This case and the case of Levin v. Same Defendants, 107 N. Y. Supp. 618 , were tried on the same day, and the facts are somewhat similar. In this case the plaintiff substantially completed two garments in lot No. 1,867; the value of his labor being shown to be $3.50 for the complete maldng of each garment, or $7 in all. He did some work on three garments of lot No. 1,776, which, if the work had been fully done, would have been worth $10.50, and on four garments of lot No. 1,761, which, if completed, would have been worth $16, making as the total value of his labor, if each garment had been fully finished, the sum of $33.50. It was conceded, however, that defendants paid $3.85 for the uncompleted labor on the garments, and had also paid the plaintiff $6 on account, ^making $9.85 in all, which sum should have been deducted from $33.50, and judgment for the plaintiff for $23.65, instead of $37.65, as given, should have been entered.
Judgment modified, by reducing amount to $23.65, and, as modified, affirmed, without costs.