Municipal Cobpobations—Public Impbovements—Bids— Non acceptance — Action fob Damages.The facts in this case are substantially as follows: The-defendant’s charter (Laws 1899, p. 163, c. 128, § 33) provides:
“Whenever any expenditures to be made or incurred by the common council or city board or any city officer in behalf of the city for work to be done, or materials or supplies to be furnished, except ordinary repairing and macadamizing of.streets, shall exceed two hundred dollars, the city clerk shall advertise for and receive proposals therefor, in such manner as the common council, or as the board or officer charged with making such contract shall prescribe, and the contract therefor shall be let to the lowest responsible bidder,, who shall execute a bond to said city with one or more sureties, being freeholders, for the faithful performance of the contract,” etc.
The defendant’s common council caused a notice to be published for-sealed proposals for regulating and grading certain of its streets, stating in the advertisement:
“The common council reserves the right to reject any and all bids.”
The plaintiff duly filed proposals for á portion of the work. Six-bids were received, including plaintiff’s, which were referred to the-street and sidewalk committee of the common council and the city engineer to be tabulated, the result of which established the plaintiff" to be the lowest, with a bid of $61,626.30; Ensinger Bros, were next lowest, with a bid of $64,204.40; and the other bids ran from $69,150-to $84,395. The committee and engineer reported this result to the common council, with their recommendation that the contract for the-improvement for which the plaintiff bid be awarded to Ensinger Bros. On the filing of this report the council rejected plaintiff’s bid and’ awarded the contract to Ensinger Bros, at the amount of their bid,. $64,204.40, against plaintiff’s written protest that he was the lowest responsible bidder and entitled under the charter provisions to the-contract. He thereupon brought this action, in which he seeks to recover damages alleged to have been sustained through loss of profits-by the refusal of the common council to award the contract to him. The learned trial justice, at the close of plaintiff’s evidence, upon defendant’s motion, dismissed the complaint, holding as matter of law that the action could not be maintained, and the correctness of this, decision presents the only question for our consideration.
The plaintiff was the lowest bidder, and at the time of filing his-proposal he was solvent, and by experience was qualified to do the-work. There was a failure on his part to comply with the requirement to verify his proposal, no signature being attached to the affidavit,, although the notary attached his signature and office thereto, which the-plaintiff contends, under the decision of McCord v. Lauterbach, 91 App. Div. 315 , 86 N. Y. Supp. 503 , made the bid irregular, and justified its rejection by the council; and, while the case is an authority for this contention, we do not care to determine the question here presented upon that ground. The plaintiff relies upon People ex rel. Coughlin v. Gleason, 121 N. Y. 631 , 25 N. E. 4 , as authority for his-contention that under the provisions of defendant’s charter it was obligatory upon the common council, if it awarded the contract to either
No contractual relation existed between the parties in the case at bar, and I am unable to find any authority in support of the existence of a right to recover damages in such an action. The authorities cited by plaintiff are all based upon an acceptance of the bid, which established a contractual relation from which flowed the right of recovery. As has been repeatedly held, a provision for the award of a contract to the lowest responsible bidder, by a municipal corporation, is intended to benefit the taxpayers, and not the bidder. The duty is a public one, and not for the benefit of individuals or the promotion of private interests. , Its violation does not inure to the benefit -of the lowest bidder, and the statute creates no liability in terms for •such violation. Had the plaintiff commenced the proper proceeding against the defendant’s common council to prevent its entering into a .contract with Ensinger Bros., and to .compel the award of the -contract to him, he might have found relief, and the very results contemplated by the statute would have been effected; but there is no rule of law permitting the recovery of damages by the lowest responsible bidder in .an action brought against the municipality upon the facts presented by this record.
The exceptions taken at the trial must be overruled, the decision •of the trial court in dismissing the complaint sustained, and judgment entered upon the dismissal, with costs.
Exceptions overruled, and judgment affirmed, with costs. All concur.