Majority
Headnote
1. Mechanics’ Liens—Right to Lien—Damages fob Breach of Contract— Subcontractor.Action to foreclose a mechanic’s lien. After the notice of lien had been filed the owner of the real estate upon which it was sought to impress the same paid into court a sum of money sufficient to discharge the lien; there being that amount, at least, due the defendant, the general contractor. This action was subsequently brought by the assignee of the subcontractor to recover the sum of $1,029.14, with interest from a specified time, for extra work alleged to have been performed for and materials furnished to the general contractor. The plaintiff had a recovery of $562.51, with interest fromt April 1,1905, from which the general contractor appeals.
We are satisfied with the correctness of the recovery, except in sec far as it includes an allowance for the omission to build the bridge on Van Dam street. In the contract which the plaintiff’s assignor had
Nor do we think plaintiff was entitled to interest on the amount recovered. The claim made by her was unliquidated, and subject to a reduction, if our conclusion be correct, of upwards of 60 per cent. Where a party claims upwards of 60 per cent, more than he is entitled to, and the claim is unliquidated, he is not entitled tó interest upon the amount recovered. Excelsior Terra Cotta Co. v. Harde, 90 App. Div. 4 , 85 N. Y. Supp. 732 , affirmed 181 N. Y. 11 , 73 N. E. 494 , 106 Am. St. Rep. 493 .
The judgment appealed from, therefore, must be modified, by striking therefrom the difference between the amount as above found due the plaintiff and the amount which the trial court found, viz., $350, and also striking out the allowance for interest on the amount recovered, and, as thus modified, should be affirmed, with costs to appellant in this court. All concur.
Cases cited
- Excelsior Terra Cotta Co. v. Harde 181 N. Y. 11 at 73 p. 54