Majority
Headnote
1. Municipal Corporations—Defective Streets—Nuisances.This is an appeal by both defendants from a judgment for plaintiff upon a verdict in his favor in an action for personal injuries, and from an order denying a motion to set aside the verdict and for a new trial. The defendant construction company was engaged, and had been for some time engaged, in constructing a subway through Forty-Second street, in the city of New York, under what is known as the “Rapid Transit Act.” Chapter 4, p. 3, Laws 1891. The accident occurred on December 12, 1902, at about half past 5 o’clock in the evening, when it had grown fairly dark. The subway ran through Forty-Second street and from Fourth avenue to Broadway, and consisted of a tunnel constructed in what is known as an “open cut.” The surface of the street had been opened, an excavation made to the necessary depth, the tunnel built, the excavation filled up, and surface replaced. This work had been going on for a long while, and the street had been in a greatly disturbed condition. At the time of the accident the work immediately west of Sixth avenue had been nearly completed, and the surface of the street restored, except for a narrow trench which had necessarily been left open for the completion of the work. There was a double line of car tracks on Forty-Second street, and this trench ran between the two lines of track. The cars, as they passed, extended outside the tracks so as to partly cover the trench, so that it was impracticable to rail it off without completely stopping the running of the cars. The open trench began at a point about 30 or 35 feet west of the crosswalk over Forty-Second street on the westerly side of Sixth avenue, and ran westerly for some distance toward Broadway. The street along the curb line was littered up in places with the contractor’s tool boxes and materials, so that carts and wagons passing through Forty-Second street were obliged at these places to drive on or partly on to the tracks. Forty-Second street is a comparatively wide, and very important cross-street, and much traveled. The plaintiff, with two companions, who were fellow workmen, had come from their employer’s shop at Fifth avenue and Forty-Fifth street. They had crossed from the easterly to the westerly side of Sixth avenue,
“I could only see the track nearest me on the Forty-Second street. I started to go across the street. There was a car right In front of me, and there must have been another car or horse, and I had to take a chance to go through then because it was blocked. When I say I took a chance to get through, I mean to say there was a space there. I forget whether the car was standing still or in motion. I passed at the rear of the car; that is, at the end of it.”
The moment plaintiff had passed the end of the car, he fell into the trench, which he had not observed, and received the somewhat serious injuries for which he has recovered. The point at which he fell was not more than five or six feet from the easterly end of the open trench, and it was clearly shown that the defendant construction company had caused a red light to be placed at this end, and had stationed a watchman there to warn foot passengers and vehicles. There were other red lights exhibited at intervals along the trench towards Broadway. There was some difference in the testimony as to how far apart they were; the estimates of distance varying. It is probably not very important, so far as concerns this action, how far apart they were, because from the condition of the traffic it is doubtful whether plaintiff would have observed the lights to the westward, however near they might have been together." There was no direct evidence as to how long the trench had been in this condition, but it could perhaps be inferred that, being the last of a long continued excavation, it or a wider trench had been open for a considerable time. The defendant construction, company was engaged upon a- lawful work, and the keeping of the trench open was a necessary part of ‘its work. It was not therefore a nuisance, although it was a dangerous obstruction. Its duty was to use reasonable care to so guard the excavation as to warn persons using the highway.
From the nature of the case it could not surround the excavation with a fence, for that would have been to stop all vehicular traffic. It did adopt the precaution which experience has shown to be usually sufficient, to wit, marking the opening with red lights and stationing a watchman to warn vehicles and pedestrians. In determining what precautions it would be reasonable to adopt, the construction company was entitled to take into consideration the location of the construction, some 30 feet away from the usual and customary crossing. It is true that the plaintiff or any one else had the right
Judgment and order reversed, and new trial granted, with costs to appellant to abide the event. All concur.