Majority
Headnote
1. Contracts—Performance—Excuse for Defects.The defendant Condict contracted to install a refrigerating plant for the defendant the Mt. Sinai Hospital, and guaranteed that, when installed, it would produce three tons Of ice every 24 hours, and maintain a 20-ton refrigerating capacity on live steam at 80 pounds pressure, or exhaust steam at 1-pound back pressure. This contract was claimed to have been assumed by the subsequently formed corporation, the defendant Steele & Condict. The plant was installed under the supervision of the hospital architect. Steam for the running of the plant and connections from the boilers were to be furnished by the hospital. The plaintiff’s assignor supplied a certain portion of the plant under a subcontract, and was given an order upon the hospital for the amount due, which it refused to pay. A mechanic’s lien was thereupon filed, and this action was brought for its foreclosure.
The contention of the defendant hospital on the trial was that the plant, when installed, did not fulfill the guaranty as to capacity, and hence no final payment became due on the contract which could be applied to the satisfaction of plaintiff’s lien. Quite irrespective of their answers, however, but without any proper objection thereto, defendant sought to show that this failure resulted from improper installation insisted upon by the hospital agents. From the record it would seem the trial court did not give due weight to the facts proved showing the plant failed to do the work guaranteed because it was improperly installed under the direction of the architect and engineer of the hospital. Defendant Nathan W. Condict, the original contractor, was a man of many years’ experience in installing
If the machine was installed in the manner dictated and insisted
The court was right in determining that the order upon the hospital taken by the plaintiff’s assignor was not received in absolute payment, whether the amount was collected from the hospital or not. It was also right in giving a personal judgment against the contract,ors for the amount due the subcontractors. A lien in proper form had been filed for material furnished in the improvement of real property as the installation of the ice plant was. The rights under that lien having been assigned to plaintiff, and he having brought his action and made the contractors parties defendant, and a valid lien in form thus existing, it was proper for the court to render a personal judgment against the contractors indebted.for the material furnished. Hawkins v. Mapes-Reeves Construction Co., 82 App. Div. 72 , 81 N. Y. Supp. 794 , affirmed 178 N. Y. 236 , 70 N. E. 783 ; Clapper v. Strong, 41 Misc. Rep. 184 , 83 N. Y. Supp. 935 , affirmed 90 App. Div. 536 , 85 N. Y. Supp. 748 .
The court was also justified in finding that the defendant the Steele & Condict corporation assumed to carry out the contract with the hospital, and that the plaintiff’s assignor, therefore, had a claim against it for materials furnished, as well as Condict individually. The defendant Condict by his answer admitted that plaintiff’s assignor furnished the refrigerators mentioned in the complaint, and that they were installed in the Mt. Sinai Hospital, and that the amount claimed by plaintiff had not been paid; and, in addition, asked the court to render a personal judgment against him for the difference between the amount due and the amount of the order which he claimed was given in absolute payment. The plaintiff’s money judgment against the two defendants must therefore be affirmed.
It is suggested that the contractors have no right of appeal as against the defendant hospital. The record does not disclose that they served their answers upon the attorney for the hospital their codefendant; but it was asserted-upon the argument that such was the fact, and we think we would be justified in so assuming. Their answers, however, did not ask that plaintiff’s alleged lien be enforced, but demanded that his complaint be dismissed because the alleged order given to his assignor had been taken in absolute payment. The contractors filed no lien, and hence they could not recover a money judgment against the hospital because it was entitled to a jury trial on that issue. It is only where a party has filed a mechanic’s lien that upon failure for any reason to establish the lien a money judg
As so modified, the judgment should be affirmed, with costs to each respondent. All concur.
In this case the only question, as I view it, that is presented on this appeal is as to the validity of the judgment in favor of the plaintiff against the appellants. There is no question presented as between the defendant and the Mt. Sinai Hospital. The Mt. Sinai Hospital made a contract with its codefendant, Nathan Woodhull Condict, for the installation of a refrigerator plant in its hospital building then in course of construction. Condict made a subcontract with the plaintiff which was completed by the plaintiff, but upon which Condict failed to pay. Whereupon the plaintiff filed a lien against the hospital property, and commenced this action to foreclose that lien, alleging that there was an amount due by the hospital to Condict in excess of the plaintiff’s claim. Both Condict and the hospital interposed answers, but the record does not show that the Condict answer was served upon the hospital, and the only judgment demanded by the Con-dict answer against the hospital is to- recover a small sum of money which it was alleged in the answer was due to Condict over and above the amount of the plaintiff’s claim; but, as it does not appear by the record, and counsel on the argument-did not state as a fact that the Con-dict answer was served upon the hospital, the court could grant to Con-dict no relief against the hospital. Section 521 of the Code of Civil Procedure. When the case came on for trial, the plaintiff sought to prove that there was due by the hospital to the defendant Condict a sum of money in excess of that claimed, and the defendant Condict joined with the plaintiff in attempting to prove that fact. That fact the hospital denied, and the learned judge found as a fact that, the defendant Condict having failed to construct the machine in accordance with the provisions of his contract with the hospital and the damages sustained by the hospital in consequence of Condict’s failure to comply with his contract being in excess of the amount due to Condict under the contract, neither the defendant Condict nor the plaintiff as assignee of the whole or any part of the claim of the defendant Condict is entitled to any recovery against the hospital; but further held that the plaintiff was entitled to a money judgment against the defendant Condict for the amount due to the plaintiff under his contract with Condict, and upon this decision a money judgment was entered in favor of the plaintiff against the defendant Condict, the complaint being dismissed as to the hospital. The plaintiff, being satisfied with his judgment, did not appeal, but the defendant Condict appealed, and the case is before us on his appeal. The right of the plaintiff-to a money judgment against Con-
It seems to me quite clear that the defendant Condict cannot appeal because the court has not awarded to the plaintiff all the relief asked for. That was a matter as between the plaintiff and the hospital. If the plaintiff was satisfied with his conceded right for a money judgment against Condict, Condict was not aggrieved, and he could not ask the court to reverse the judgment so as to give to the plaintiff a lien upon the property of the hospital. Condict has not paid the judgment, and therefore cannot claim to be subrogated to any right of the plaintiff to prosecute this appeal, or to enforce this lien against the property of the hospital; and there is no theory, so far as I can see, upon which the defendant Condict can object because the plaintiff was not .afforded all the relief he demanded. The failure of Condict to serve his answer upon the defendant hospital precluded the court from determining any question in controversy between Condict and the hospital; and, as the court below had no power to give to the defendant Con-dict any relief as against the hospital, we certainly are not justified in reversing the judgment because the court has refused to give Condict such relief.
Without considering, therefore, the merits of the case, it seems to me that we can do nothing else but affirm this judgment. As it is claiméd, however, that the question as between the hospital and Con-dict was never determined because of the inability of the court to grant Condict any relief in this action, I think the judgment appealed from should be modified by providing that the determination of this question should not be a bar to a further action brought by Condict against: the hospital to recover the amount due to him under the contract; and,, as thus modified, the judgment should be affirmed, with costs in favor of the plaintiff against the defendant Condict.
Cases cited
- Hawkins v. Mapes-Reeves Const. Co. 82 App. Div. 72 at 81 p. 529
- Hawkins v. Mapes-Reeve Construction Co. 178 N. Y. 236 p. 529
- Clapper v. Strong 41 Misc. Rep. 184 p. 529