The cause of action, is alleged in subdivisions 3, 4 and 5 of the complaint, in conjunction with other subdivisions alleging the plaintiffs’ ownership, presentation of claim, etc. The said three subdivisions are as follows:
“(3) That heretofore and on or about the 6th day of July, 1899, the said defendant constructed and enlarged its sewer and has since wrongfully maintained a sewer emptying and discharging upon the said lands of these plaintiffs large quantities of water upon said lands, and that said defendant has utterly failed to construct beneath the surface of a strip of land on the easterly side of the land of the plaintiffs hereinbefore described as the defendant has promised and agreed by its duly authorized agents in writing, bearing date the 24th day of July, 1902, so as to carry off the surface water, drainage and sewerage, but he has continually since the 6th day of July, 1899, wrongfully and unlawfully emptied and discharged the same upon the lands of the plaintiffs as hereinbefore described, in large quantities, thereby converting the lands of said plaintiffs into a bog, swamp or quagmire to the great damage of said plaintiffs.
“(4) Plaintiffs further allege that a judgment of the Supreme Court of Queens county was duly made and entered in an action in the Supreme Court of Queens county, wherein the above named plaintiffs were plaintiffs and the city of New York was defendant, fixing the amount of damages sustained by the plaintiffs up to July 24, 1902, by reason of wrongful and unlawful acts, committed by defendant as aforesaid.
“(5) Plaintiffs further allege that ever since the 24th day of July, 1902, and up to the present time the said defendant through its agents, servants and employés has emptied and discharged the surface water and sewerage upon the lands of said plaintiffs in large quantities, thereby converting their said lands,, as aforesaid, into a bog, swamp or quagmire to the great damage of the plaintiffs.”
And the prayer for judgment is as follows:
“Wherefore these plaintiffs demand judgment, and that said nuisance be abated and discontinued, and that the defendant be restrained by injunction, thereby discharging by its sewers and sewer pipes, drainage or surface water or any other sewerage upon the lands of the plaintiffs, and for two thousand five hundred ($2,500.00) dollars, damages, and for the costs and disbursements, of this action.”
Argued before WOODWARD, JENKS, HOOKER, GAYNOR,. and RICH, JJ.James M. Seaman, for appellants.
Theodore Connoly (Alex. E. Strouse, on the brief), for respondent.
The order appealed from requires the plaintiffs “to-file an amended complaint wherein the complaint herein shall be made more definite and certain in respect to the cause or causes of action therein sought to be set out”; and further, that such amended complaint “shall set forth separately and number the same their causes of action.” This is all of this singular order which the learned counsel for the corporation of the city of New York procured and' caused to be entered. It does not state in what respect the complaint, is indefinite or uncertain, or what the plaintiffs shall allege in the new pleading to cure it, or what the two causes of action which it requires to be separately stated and numbered are, or where they are.
Section 546 of the Code of Civil Procedure provides that:
“Where one or more denials or allegations, contained in a pleading, are so-indefinite or uncertain that the precise meaning or application thereof is not apparent, the court may require the pleading to be made definite and certain,, by amendment.”