• 1. Appeal—Review—Questions of Fact—Findings of Referee.This is an action in equity for the reformation and performance of a written contract of August 20, 1897, referred to in the opinion in action No. 2, between the plaintiff and the defendant Charles H. Turner, and herewith decided. 110 N. Y. Supp. 594 . Reference to such opinion is made for a more complete statement of the facts. The order of the Appellate Division made in the case, as reported in 67 App. Div. 625 , 73 N. Y. Supp. 783 , is made a part of the record in both cases, so that the two cases, although distinct and separate, are identical so far as their history is concerned up to the time when said order was made.
The referee found as a fact in this case that there was a deficiency in the quantity of spruce and pine lumber guaranteed by the plaintiff under the contract of August 20, 1897, of 1,120,087 feet less than the 6,000,000 feet so guaranteed. It is urged that the evidence does not justify the conclusion of the referee that there was such deficiency. It appears that plaintiff had another contract with the defendant Charles H. Turner for sawing lumber, and the work under the two contracts was proceeding simultaneously. The evidence is convincing that the lumber sawed under both contracts was mingled at the mill of plaintiff. In view of such intermingling, defendants were permitted to make estimates of the lumber from the tract in question based on the quantity •cut by the choppers, and the application of some rule prevalent among lumbermen for estimating the number of feet of lumber which a certain quantity of logs will produce. Assuming that there had been an intermingling of lumber at the mill, I do not see how there was any better way, or, indeed, any other way to arrive at the exact quantity of lumber under the contract in question. The referee was not bound to •accept the plaintiff’s uncorroborated statement as to the amount of the lumber, but was at liberty to take into consideration the best evidence which under the circumstances the defendants were able to submit. It is said that defendant Charles H. Turner was responsible for the intermingling of the lumber at the mill because his superintendent, Praire, was in charge under a provision in the contract that the work should be done under and by direction of the said defendant. Praire was called as a witness by plaintiff, and the latter is therefore hardly in a position to question his credibility. And Praire testified, not only to the fact of such intermingling, but also that he repeatedly instructed the plaintiff and also the plaintiff’s foreman that the lumber should be •kept separate; and, although Praire may have been vested with au
According to the contract of August 20, 1897, plaintiff was at liberty to make up the deficiency in the spruce and pine lumber at the rate of $2.50 per 1,000 feet, which for 1,120,087 feet would amount to $2,-,800.22, and, on paying this amount, plaintiff would be entitled to a deed of the “sawmill site” by the defendants, and the referee should have so held. It appears from the report of the referee, however, that he combined this amount with the amount due to the plaintiff in action No. 2, and that he struck a general balance of all transactions between the parties, and directed that plaintiff might have a specific performance, not on the payment of said sum of $2,800.22, but on the payment of $2,186.16, the amount of such general balance. By adopting this practice, the referee disregarded the order of this court that the two actions should be tried separately, and the effect of such practice has been to substantially reconsolidate the two actions and nullify said order.At a cursory glance it might seem that this irregularity benefited plaintiff and could not be corrected on his appeal. On reflection, however,it is apparent that plaintiff may have been prejudiced by such irregular practice. The order of this court granted at the instance of defendants required the litigation to be severed and to proceed in two separate and distinct actions, and it is now the right of the plaintiff, as well as of the defendants, by virtue of said order, to have the litigation thus proceed. It is apparent that the practice of the referee in awarding to the plaintiff herein that which he" was only at liberty to award him in action No. 2 might have had the effect of embarrassing and prejudicing the plaintiff in that action, and possibly of .defeating such action. A recovery herein for what was properly involved in action No. 2 might have operated as a defense to that action, and hence plaintiff had a grievance herein notwithstanding that the amount he was adjudged to pay in order to procure a specific performance was less than it should have been, which grievance on his appeal should be redressed. As stated in action No. 2, and for the same reasons, the proper judgment may now be directed by this court on the facts as found by the referee without the necessity of a new trial. It may not be amiss to say for the guidance of the parties that in the taxation of costs which will follow as the result of our determination in both cases such disbursements as were common to the two actions in the trial before the referee should be apportioned equally to such actions.
We do not award the defendant Charles H. Turner an affirmative judgment for the deficiency under the contract amounting to $2,800.22, because, as stated in action No. 2, he is not entitled to the same until a
The judgment should be reversed, and judgment is hereby directed to be entered on the referee’s report that the defendants recover of the plaintiff costs to be taxed exclusive of costs of this appeal, and that on payment by the plaintiff of such costs and the further sum of $2,800.-22, with interest as fixed by the referee within 30 days after service of a copy of such judgment, the defendants deliver to the plaintiff a proper deed of the premises in question. No costs of this appeal are awarded. All concur.