Majority
Headnote
1. Appeal and Error—Objection Not Made Below—Variance.The complaint contains two causes of action; the first based upon a contract all of the terms and conditions of which it is. alleged were duly performed by plaintiffs, and the second upon quantum meruit for the value of the. same materials and services. There was no evidence given upon the trial of the value of the materials furnished or services rendered, and the trial court properly limited the plaintiffs’ right to recover to the first cause of action, resting upon the full performance by plaintiffs of the alleged contract. By the terms of this instrument the plaintiffs were to deliver the materials not later than May 7, 1907, and complete the labor on or before May 9th. The contract is contained in a written proposal made by plaintiffs and defendant’s letter of acceptance, which contained the following clause:
“Time is the essence of this contract, as I am under forfeit of $50 a day for completion.”
Upon the trial the evidence of the plaintiffs established the fact that their labor was not completed within the time limited by the contract, and the appellant now contends that the judgment must be reversed '
No error was committed by the trial court in the charge relating to the alleged counterclaim. There was no evidence of any loss of bonus or payment of forfeiture caused by plaintiffs’ failure to finish their work within the time stated in the contract, and no evidence of damage of any kind sustained by defendant which could be charged to such failure. In the absence of such evidence, the defendant was not entitled to any relief based upon the counterclaim.
The judgment of the Municipal Court must be affirmed, with costs. All concur.