Majority
Headnote
1. Appeal and Errob—Findings op Referee—Review.In 1897 the plaintiffs, as successful bidders, entered into a contract with the water board of the defendant, and thereunder began to construct public waterworks, which they did not finish. The defendant contends that they abandoned the work. However this may be, on June 3, 1899, the said board gave formal notice to the plaintiffs whereby it stated that the contract was long since terminated, but, as it noted from a communication from the plaintiffs that the plaintiffs considered the contract as still in force, it gave notice, in the exercise of its discretion and deeming that the best interests of the village so required, that it abandoned, canceled, and terminated the contract. The contract provided:
“It is further expressly agreed that the parties of the first part shall have the right to suspend or cancel this agreement at any time if in their discretion it appears to them the interests of the village of Nyack so require, and in such case the parties of the second part shall be paid in full for all the work done prior to the date of such suspension or cancellation, but shall not be entitled to any damages therefor.”
A new contract was made with another. This action is brought to recover $11,327 on five separate causes of action, with interest. The judgment entered is for $10,232.01, and the amount thereof is made up of $5,627.92 excess of judgment for principal ($14,535) over payments of $8,907.98, interest from June 30, 1899, $2,616.98, and $1,987.11 costs.
The recovery under the third cause of action should stand at $1,208.49. The only item attacked is for cartage of certain brick. If this brick was used by the plaintiffs, the cartage was not chargeable against the defendant, and it would not matter if the cartage was for brick bought by the defendant on account of the plaintiffs to replace brick furnished by the plaintiffs and rejected. But it appears that the brick was finally sold by the defendant, but not for the account of the plaintiffs. If so, then the cartage was a proper charge" against the defendant. It is true that a witness for the defendant testifies that some of this brick was used in the work. But it was for the defendant to show what part of it was used in the work, and therefore excluded from the amount sold. This it has not done. The recovery for the construction of the pure water well, excluding the removal of water, should stand at $1,319.37, for I think that upon the evidence we cannot hold counter to the referee that the crib which caused this increased expense was a detail of the work, and was within the contemplation of the original contract, or that its use was essential in the work required to be done under the contract. The referee found that the plaintiffs excavated 11,400 cubic yards of earth in the construction of the filter bed, for which the contract price was 29 cents per yard, and “performed work and furnished materials in making soundings at the request of the defendant, furnishing engine, pump, men, and coal, pumping and keeping the excavation free from water, which I find all to be of the reasonable value of $5,374.-15.” It is contended that the item is erroneous because it makes allowance for 3,400 cubic yards. I think that we cannot disturb the finding of the referee in this respect. The cost of this digging amounts to $3,306,and this amount deducted from the amount allowed by the referee would leave a balance of $2,068.15, which is made up for other work described in that finding. So far as the pumping out of the water is concerned, it is quite true that the engineering work as prescribed by the contract required such pumping as was incidental to the construction, but it is also true that during the progress of the work the defendant at the instance of its consulting en
The plaintiffs plead that they have suffered damage “by reason of moneys expended in the preparation for said work to be performed under said contract in securing right of way, building bridges, purchasing tools, machinery, employing engineer, building storage buildings, and materials damaged and destroyed, and in the expending of moneys in preparing crushed stone, and in loss and damage to material and extra material furnished for said work, all of which work performed and materials purchased and buildings erected and moneys expended were necessary under the terms and conditions of said contract, plans, and specifications, and for loss of profit in being prevented by the defendant from completing the work to be performed under said -contract, all to the damage of plaintiffs in the sum of six thousand dollars ($6,-000), of which no part has been paid.” And the learned referee under this claim awarded to them $1,946.30, made up of items stated by him as follows:
“60 yds. of sand at $1.50 per yd. 22 wheelbarrows at $16 per doz. 60 cement boxes at 80 cents apiece. 2,200 ties at 10 cents apiece. 250 yds. gravel at $2.00 per yd. Cement shed, 16x20 14-ft. post. Car load and a half of cement. Planking. Building road.”
The learned referee in his opinion says:
“I am aware that this claim does not appear in the complaint or bill of particulars. However, the evidence was allowed and received by Mr. Justice Barnard under the general issue, after objection by the defendant.”
“Securing right of way, building bridges, purchasing tools, machinery, employing engineer, building storage buildings, and materials damaged and destroyed, and in the expending of moneys in preparing crushed stone.”
And so they would not, for example, include the specific item of $340 testified to by the plaintiff as the cost of building a piece of road. I think that the defendant, under the provisions of this contract, had a right to suspend or to terminate the contract, while the prevision was that in such event the plaintiffs should recover for the work done. I think that the plaintiffs are not entitled to recover for these specific items on the theory that it is work done, for such items covered material or instruments for the doing of work. Under the terms of the contract the plaintiffs were bound to contemplate the possibility of the termination of the contract whenever the defendant’s officers deemed it for the best interests of the village; and, as they were thereby relegated to recover for work done, they cannot recover for the materials brought to hand or the instruments procured for the doing of the work. If any of the material, tools, etc., were "taken or kept by the defendant, then the plaintiffs might recover on the theory of a conversion. For these reasons, I think that these items should be excluded from the case under the present pleadings in any event, without prejudice, however, to the plaintiffs to recover by conversion or appropriate action for the material or tools, etc., which they assert they left upon the premises and which they were prevented from taking away. I think that1 interest cannot be allowed (Beckwith v. City of New York, 121 App. Div. 465 , 106 N. Y. Supp. 175 ; Excelsior Terra Cotta Co. v. Harde, 181 N. Y. 12 , 73 N. E. 494 , 106 Am. St. Rep. 493 , and Sweeny v. City of New York, 173 N. Y. 417 , 66 N. E. 101 ), for interest is only allowance in a case like this, where the amount due to the plaintiffs under their demand was merely a matter of computation.
The judgment is reversed and a new trial granted, costs to abide the event, unless the plaintiffs within 20 days shall consent to reduce the sum to $1,247, with costs and interest from the time of the entry of the judgment, in which event the judgment as modified is affirmed, without the costs of this appeal to either party. All concur.