Majority
Headnote
1. Principal and Surety—Nature of Undertaking—Construction.This is a motion to set aside the verdict of the jury for $500 on the ground that it was against the weight of evidence, contrary to law, and contrary to the evidence. The action is to recover -$1,000 for breach of a written contract, dated June 5, 1905, between -the plaintiff and the defendant Rosoff, whereby the plaintiff granted and conveyed to said defendant certain buildings in the borough of Manhattan, city of New York, down to the level of the cellar bottoms
“That if the said principal shall faithfully perform said contract on his part in so far as such contract provides for the demolishing and removing of said buildings, then this obligation shall be void; otherwise, to remain in full force and effect.”
At the trial plaintiff’s evidence was to the effect (testimony of James R. Hay) that the defendant Rosoff failed to remove the débris or any part thereof; that the buildings in question consisted of five adjoining houses, of 20 feet frontage each, upon lands extending about 100 feet into the block; that the cellars, which were of uniform depth of 10 feet each, were filled very nearly to the street level, and in some places above the street level, with the débris resulting from the taking down of the houses; that the amount of old mortar and cement in this mass was very small; that the estimated cost of freeing the premises from this débris, exclusive of old mortar and cement, would be about $1,200. Another witness of the plaintiff testified that 25 per cent, of this mass of débris was other than old mortar and cement; this being his estimate only, based upon a superficial examination. No effort was made by him to accurately determine the exact proportion. In addition to this a large quantity of tin, such as comes from roofs, was on the premises. The frontage of the houses was 100 feet and the depth of the houses into the block was 60 feet. This gave a surface area of 6,000 square feet, and with a depth of 10 feet the cubic contents of the mass was 60,000 cubic feet, or 2,222 cubic yards, plus a small fraction of a cubic yard. The evidence of the character of the débris and the fact that a quantity of tin was left upon the premises was corroborated. The testimony of the defendant Rosoff was that the reasonable cost of removal of the débris such as came from these buildings was $2 a load of 2% cubic yards, making the total cost, based upon the figures given, of $1,776. If 25 per cent, of this was inquired to be removed, the pro rata cost would be $444.
The defendants raise the question that the sum sued for was in the nature of liquidated damages, and therefore the jury, finding for the plaintiff upon the issues presented, should have' found a verdict for said 'sum, and that a verdict for a smaller amount cannot be sustained. In considering this question it should be observed that the agreement is by reference made part of the bond, and, therefore, in seeking the extent to which the defendants obligated themselves to the plaintiff and in determining the scope of their liability, the two documents should be read together. Though the liability of a surety is in strictissimi juris, his undertaking must be given a fair and reasonable con
“Whether a sum agreed to be paid as damages for the violation of an agreement shall be considered as liquidated damages or only a penalty depends upon the meaning and intent of the parties as gathered from a full view of the provisions of the contract, the terms used to express such intent, and the peculiar circumstances of the subject-matter of the agreement Dakin v. Williams, 17 Wend. 447 ; Williams v. Dakin, 22 Wend. 201 . The contract in such cases, as in every other, is to govern, and the true inquiry is, what was the undertaking? Whether it was folly or wisdom for the contracting parties thus to bind themselves is of no consequence, if the intention is clear.”
Mundy v. Culver, 18 Barb. 336 , 338, is authority for the statement that there are various legal rules for ascertaining whether a sum named in a contract to be paid by a defaulting party was intended as liquidated damages or a penalty merely. Among these rules is one, well established by numerous decisions, that when a contract is such that the damages, in case of a violation of it, will be uncertain in their nature and amount, and the parties have stipulated that in the event of a breach a certain sum shall be paid by the party in default as liquidated damages, they will be regarded as having so intended, and that sum will be treated as the measure of damages. Sedgwick on Damages, 421; Holmes v. Holmes, 12 Barb. 137 ; Dakin v. Williams, supra.
Considering the subject-matter of the agreement in the case at bar, the nature of the transaction that the bond was intended to facilitate, and giving a natural construction to the provisions of the contract and bond in seeking therefrom the intention' of the parties, it seems quite clear to me that the defendant Rosoff bound himself to remove certain specified débris within a certain time limitation, and that upon a breach of his obligation both defendants obligated themselves to respond in damages to the plaintiff in such sum, not exceeding $1,000, as he may have been damnified, governed by the proper measure of damages in such cases.
The defendants urge that the plaintiff failed to prove that he suffered any actual damage whatever, as the evidence showed that the premises in question, with the débris thereon, were sold and conveyed to a third person. When the breach of said contract occurred the rights and liabilities of the parties became fixed and determinable. The breach occurred, as found by the jury, 30 days after the date of the contract, when the defendant Rosoff had failed to remove the débris pursuant to contract, and the plaintiff was entitled then to recover damages, to
“The fact that since the lease was made other methods for making brick have been devised which rendered this condition of the surface unnecessary does not change the construction to be put upon the covenant, nor the defendant’s liability under it.”
To the same effect is Appleton v. Marx, 191 N. Y. 81 , 83 N. E. 563 .
The question raised by the defendant as to the sufficiency of the evidence as to the quantity of debris other than old mortar and cement left upon the premises is answered by the fact' that the evidence on this element of the case was submitted to the jury, who found by their verdict what proportion of the unremoved débris was other than old mortar and cement. Assuming, for the sake of argument, that the evidence on this proposition was meager, the jury passed upon the credibility of the witness on this point and the probability of his evidence, and found the facts substantially to be as testified to. There is sufficient, in my opinion, to support the verdict, and I am loath to disturb it.
Motion to set aside the verdict and for a new trial denied. The defendants may have 10 dqys’ stay of execution after notice of entry of judgment, and 30 days to make and serve a case.
Cases cited
- Smith v. Molleson 148 N. Y. 241 at 246, 42 p. 617
- Colwell v. Lawrence 38 N. Y. 71 p. 617
- Kemp v. Knickerbocker Ice Co. 69 N. Y. 45 p. 617
- Hosmer v. True 19 Barb. 106 at 109 p. 617
- Williams v. Dakin & Bacon 22 Wend. 201 p. 617
- Mundy v. Culver 18 Barb. 336 at 338 p. 617
- Holmes v. Holmes 12 Barb. 137 p. 617
- Scott v. Haverstraw Clay & Brick Co. 135 N. Y. 141 p. 618
- Appleton v. Marx 191 N. Y. 81 at 83 p. 618