Majority
Headnote
1. Vendor and Purchaser (§ 344[2] ) — Contracts—Procurement of Mortgage Extension-—Duty of Parties.The defendant sold certain real property to the plaintiffs subject to certain incumbrances, including a second mortgage of $5,000, which mortgage the defendant agreed at the time of the sale to procure to be extended for a period of four years from September 15, 1906, its date of maturity. The defendant further agreed that in the event of his failure or inability to procure such extension he would pay to the plaintiff any damages or expenses they might be put to in procuring the same. On their part the plaintiffs agreed that, “if necessary,” they would execute a new mortgage in that sum for this purpose of effecting such extension.
The defendant was acting, it seems, for one Moskowitz, who was the real party in interest, but nevertheless he bound himself by the contract. The plaintiffs transferred their title and covenanted with their grantee that the agreement for the extension of the mortgage would be carried out. Some while before the mortgage became due, the plaintiffs called the defendant’s attention to the matter, and urged that he see •that the extension be procured. The defendant then informed the plaintiffs that Moskowitz was the real party, saying that the matter was-for Moskowitz to attend to, and that he himself washed his hands of the" affair, and that whatever Moskowitz did was agreeable to him. The plaintiffs then importuned Moskowitz to procure the extension, and he refused to do anything concerning it, apparently on the ground that plaintiffs had parted with their title and were therefore not entitled to ask that the agreement be performed. Plaintiffs informed him that they had guaranteed the extension to their grantee, and it was shown that such grantee was ready, if called upon, to' execute a new mortgage in case an extension of the old one could not be obtain-. ed. The holder of the mortgage refused to extend, and the plaintiffs were put to large expense in obtaining a new loan to effect the extension, and they bring this action for reimbursement.
The learned trial court dismissed the complaint upon the ground that it was incumbent upon the plaintiffs to tender to the defendant a new
Dissent
On the evidence adduced, the plaintiffs established a cause of action for the expenses to which they were put in procuring the extension of the mortgage, and the dismissal of their complaint was error.
The judgment must be reversed and a new trial granted, with costs to the appellants to abide the event.
PATTERSON, P. J., and INGRAHAM and CEARKE, JJ„ concur.
The agreement on the part of the ■defendant to procure an entension of the time of payment of the $5,-000 mortgage referred to was upon the condition that the plaintiffs held the title to the land covered by the mortgage at the time it fell due. This is evidencéd by the fact that the plaintiffs agreed that, if necessary, in ordér to procure such extension, they would “execute a new mortgage in said sum—$5,000.” When the plaintiffs, therefore, sold the land prior to the time the extension, was desired, they thereby •destroyed the agreement, because they put it out of their power to give a mortgage. Eddy v. Davis, 116 N. Y. 247 , 22 N. E. 362 . The agreement did not run with the land, nor could the plaintiffs enforce it for -the benefit of a third party.
I think the judgment should be affirmed.
Cases cited
- Eddy v. Davis 116 N. Y. 247 p. 173