Majority
Headnote
1. Contracts (§ 303[2] )—Implied Obligations.The defendant was the general contractor for the erection of a house in the city of New York for Andrew Carnegie, for which he was to receive a stated fixed price. He made a subcontract with plaintiff to quarry, cut, and furnish granite. The architects ánd agents for Carnegie were a certain firm of architects. They were to furnish the plans for the work to be done under both the general contract between the defendant and Carnegie, and the subcontract between plaintiff and defendant, and all work under either contract was to be subject to their inspection, approval and acceptance. The plaintiff has recovered judgment for a sum admitted to be due him. He- appeals, however, because the trial court refused to submit to the jury or permit a recovery for a claim for damages resulting from the delay of the architects in furnishing detailed plans necessary to be had before the required granite could be quarried. His claim in this regard is that, although he constantly requested .that plans be furnished him, they were unreasonably delayed, and that in consequence he was put to much additional expense in keeping his quarry open, in loss of interest, in increase in the rate of wages, and the like. For the purposes of this appeal we -must "assume that the' plans were unreasonably delayed, and that the plaintiff suffered some damage thereby.
The question is whether the defendant is liable for such damages. To determine this question, it is necessary to consider the contract between the parties read in the light of the surrounding circumstances.
“The architects shall furnish to the party of the first part such further drawings or explanations as may be necessary to detail and illustrate the work to be done, and the party of the first part shall conform to the same as part of this contract so far as they may be consistent with the original drawings and plans referred to and identified as provided in art. 1.”
It was the apparent intention of the contract that reasonably complete drawings should accompany the contract, leaving only additional or explanatory drawings to be furnished under the second clause. It appeared in evidence, however, that, while some drawings did accompany the contract, they were not sufficient either as to detail or in scale to constitute working drawings from which the granite could be quarried.
The delay complained of was in furnishing such detailed drawings on the proper scale. The appellant has called our attention to a number of cases in which there has been applied to building contracts the familiar rule that there is in every contract an implied obligation on each contracting party to do all that he reasonably can do to enable the other party to perform his contract, and that for a failure so to do either directly or by the default of his servants or agents the party so failing may be held to respond in damages. If the architects whose default is said to have caused the damages were defendant’s agents, or if the defendant assumed responsibility for their acts, he might be held liable under the rule stated. As we read the contract, however, the architects were not created defendant’s agents, and he did not assume responsibility for them. They are expressly described as “acting for the purposes of this contract as agents for the owner,” and, as has been said, plaintiff knew perfectly well that the owner was Carnegie, and that defendant was merely a contractor with the owner. Plaintiff, therefore, distinctly and specifically agreed to perform his work under the direction and to the satisfaction of Carnegie’s agents. The designation of the architects as “agents of the owner” was expressly declared to be “for the purposes of this contract,” which means for all of its purposes. When, therefore, the second clause provided that the architects should furnish further drawings or explanations, it was equivalent to saying that the owner’s agent would furnish them. Plain
The judgment must be affirmed, with costs to the respondent. All concur.