Majority
Headnote
1. Damages (§ 68[1] )—Interest—Action on' Building Contract—Interest on Progress Certificates Retained.The action was brought to recover the sum of $53,-120.48 damages for delay and increased cost alleged to have been occasioned by the wrongful acts and interference of the defendant in the prosecution of the work of constructing a bridge and its approaches between Pelham Bay Park and City Island, in the Twenty-Fourth ward of the city of New York, under a contract between the plaintiff and defendant.
The complaint contained three causes of action, the first of which was taken from the consideration of the jury. The jury returned a verdict on the second cause of action for $13,764.11, and for $8,209.48 on the third cause of action. The third cause of action was to recover damages for increased cost of performing the work caused by the action of the city in ordering a cessation-of the work on the City Island approach for a number of months, and then directing its continuance after changes in the condition had made the prosecution thereof more difficult and expensive. As a distinct item of damage under this cause of action was a claim for $2,205.14 interest. The contract provided
These progress certificates were mere estimates of the amount of work done, were in no sense final or conclusive, and were made for the benefit of the contractor. These retained percentages were not in any event due until the completion of the work, and we are unable to see any basis upon which interest can be charged upon sums not due. Furthermore, the principal upon.which this interest is claimed, to wit, these retained 30 percentages, has been paid in full, and the plaintiff has executed a release therefor. Interest cannot thereafter be claimed upon a principal sum paid in full and a release therefor given. The item under consideration is not interest on the amount sued for in this case, but is interest on an amount which has been paid.
The learned court charged the jury as follows:
“He claims interest of $2,205.14 on payments due him under the contract, but withheld during the period of that delay. If he is responsible for that delay, you will refuse to give him that interest; if he is not, you will award it to him.”
As the jury found that he was not responsible for that delay, they must, under that instruction, have included this amount in the verdict which they returned upon the third cause of action.
The judgment and order should therefore be reversed and a new trial ordered, with costs to the appellant to abide the event, unless the plaintiff will stipulate to reduce the verdict by the sum of $3,305.14, in which event the judgment as so modified, and the order appealed from, will be affirmed, without costs in this court to either party. All concur.