Majority
Headnote
1. Contracts (§ 214[2] )—Construction—Payments.On the 9th of October, 1906, the defendant was the owner of a tract of land in Long Island City fronting on the East River and immediately adjacent to land acquired by the city of New York for the so-called Blackwell’s Island Bridge, which the plaintiff was constructing. On the date mentioned it entered into an agreement in writing, modified by two supplemental agreements, with the defendant, by which he leased to it for a term of two years a portion of the land owned by him. In consideration of the lease the
The contract provides in express terms that:
“The said Henry M. Susswein agrees on his part to pay to the Pennsylvania Steel Company in further consideration the sum of thirty-five hundred (3500) dollars in cash upon the completion of said dock.”
The defendant, therefore, was obligated to pay to the plaintiff the sum of $3,500 when the dock was completed, irrespective of plaintiff’s covenant to do the grading and filling. This was the construction placed upon the agreement by the trial court, and from the instruction to the jury to this effect no exception was taken. The dock was constructed for the plaintiff by the Edward B. Jenks Company, and, before plaintiff paid such company, it requested the defendant to look it over, and see whether or not it was satisfactory. The defendant did so, and thereafter plaintiff wrote him, saying:
“We understand that you and your representative, Mr. Hunt, looked over the dock built by Edward B. Jenks Company at Ravenswood, and that you have agreed to give formal acceptance of this work providing we wrote you, and, in order that our contract with the Jenks Company can be closed as early as possible, we would appreciate a prompt reply.”
On the 11th of March the defendant answered the letter, saying, ' among other things:
“I am in receipt of your favor of the 8th, and in reply desire to advise you that the writer, as well as Mr. Hunt, looked over the crib and we find same to be satisfactory.”
Hunt, referred to in this letter, was a dock builder employed by the defendant to see that the work was properly done. The plaintiff, after the receipt of this letter, paid the Jenks Company for constructing the dock. The defendant, having notified the plaintiff that he found the dock “to' be satisfactory”. and plaintiff having acted on that notification and paid the Jenks Company, could not thereafter be heard to say that the dock was not completed according to contract, and for the reason that, when one asserts the truth of a fact to" another and .that party .acts. upon , the statement, the party asserting the fact
Defendant’s main contention in this respect is that the dock was not completed within the meaning of the contract until the necessary fill behind the crib work had been made, so that the dock could be used. Under the contract itself, I am of the opinion that this contention is not sound; but, assuming that it is, there was sufficient evidence to sustain the finding that at the commencement of this action the fill had been substantially completed. An engineer employed by the plaintiff testified that on June 13, 1907, the land behind the dock had been filled in to an elevation of five feet five inches above low-water mark, which was about a foot above high-water mark. This was apparently enough so that the dock could be used, and it, in fact, was used continuously by the plaintiff. Hunt, who had supervision of the work for the defendant, testified that in June, 1907, “it was fairly well leveled up. * * * I did not see anything the matter so far as the fill was concerned.” Irrespective, therefore, of the question that the defendant cannot be heard to say that the dock had not been completed at the time the action was commenced, I am of the opinion that the evidence justifies the finding that it had been, and by reason of that fact the defendant was liable for the $3,500, which he had agreed to pay when the dock was completed. If this conclusion be correct, then it disposes of the defendant’s counterclaim so far as it relates to alleged defects in the dock. So far as it relates to plaintiff’s alleged failure to do the grading and filling, it seems to me that no right to recover damages had accrued to the defendant at the time the action was commenced. The contract contained .separate covenants as to the dock and the grading and filling. The dock had to be completed within three months, but no time was mentioned when the filling and grading was to be done. It therefore follows that the plaintiff might do this work any time before the termination of the lease, which .was nearly two years after the completion of the dock, and, until that time, the defendant had no cause of action against the plaintiff because it had not completed the grading and filling. To obviate this difficulty, it is urged that the plaintiff abandoned the contract. It'seems that the defendant became dissatisfied with the way in which the grading was being done, and on the 23d of May, 1907, in response to his letters on the subject, the plaintiff by its engineer wrote him:
“We have examined our contract, and find that it only requires us to grade the land leased to us, and said contract has therefore been duly carried out by us.”
If I am right about the proper construction to be put upon the con-' tract, then the defendant was correct in saying that the contract had
Other questions are raised, but it is unnecessary to consider them.
The judgment is therefore modified by striking therefrom the clause determining that.the defendant has no cause of action upon his counterclaim, and .inserting in place thereof that the counterclaim be dismissed, and the judgment as so modified and the order appealed from are affirmed, with costs to respondent. All concur.