Majority
Headnote
Contracts (§ 332[2] )—Actions—Pleading.Plaintiffs brought' this action to recover architects’ fees for the preparation of plans and specifications for a storehouse building to be used in connection with the Kensington Avenue Hospital. The complaint alleges a contract in writing between the parties, and full compliance therewith and performance thereof by plaintiffs “in so far as performance on their part was not waived or prevented by the defendant,” and that the plans .and specifications made by them were delivered to and approved by the proper authorities and $500 paid them on account. At the commencement of the trial the plaintiffs introduced the contract in evidence, and counsel for the defendant thereupon moved to dismiss the complaint, upon the ground that it failed to state facts' sufficient to constitute a cause of action.
The fifth paragraph of the complaint is as follows:
“That the estimated cost of the construction and erection of said building-was fifty thousand dollars ($50,000).”
The third paragraph of the contract reads:
“The architects shall on or before the 1st .day of July, 1905, furnish to the city preliminary studies and specifications, together with an estimate of the cost of the said building or structure. If the said preliminary drawings, specifications and estimate are not satisfactory to, and approved by, the president, then the architects shall and will revise and correct the same so as to conform to the suggestions, criticisms and requirements of the president, and so that the estimated cost, including architects’ fees and the cost of surveys and inspection, shall be well within the sum of fifty thousand dollars ($50,000), the appropriation or funds available for the said building or structure.”
I do not construe this paragraph of the contract as necessarily requiring the estimate accompanying the preliminary studies and specifications to be, “including architects’ fees and the cost of surveys and inspection,” “well within the sum of fifty thousand dollars.” The last provision quoted is not made applicable to the preliminary plans, but is in terms limited to the revised and corrected plans. The complaint alleges the approval of the preliminary plans, followed by the preparation and delivery of completed plans and specifications, and a payment of $500 on account thereof. The pleadings do not show that the plaintiffs were ever asked to revise or in any manner
« The judgment must be reversed and a new trial granted, costs to abide the event. All concur.