Eminent Domain (§ 236[1] )—Assessment oe Compensation—Report oe Commissioners—New Hearing.This is a proceeding begun by the city of New York to acquire land for the extension of its water supply system, pursuant to the provisions of chapter 734 of the Laws of 1905, as amended. The property in question on this appeal is situate in the town of Cortlandt, near the village of Peekskill, in Westchester county. Commissioners of Appraisal were duly appointed and the proofs of the petitioners and the owners were taken as to damages. On these proofs, a report was made awarding damages to the owners in the sum of $4,088. A motion was made at a Special Term of this court in Westchester county to confirm the report. Pending the decision of this motion, the owners of the land moved to set aside the report on the ground of newly. discovered evidence. The learned court at Special Term decided both motions by granting an order setting aside the report of the commissioners and appointing new commissioners of' appraisal to take proofs and report as to the damages to be awarded to the owners of the land. From that order this appeal was taken.
The Court at Special Term filed an opinion from which it appears that it had concluded that the present commissioners had arrived at their report upon an erroneous principle, in that they had failed to consider the proofs of the owners as to the damages caused to that part of their property which was not taken, and which, together with the part taken, was used by them in the harvesting and storing of ice for the purposes of sale in the village of Peekskill. The whole tract owned by the claimants consisted of about 7% acres, and comprised a small pond, with lands forming its shore or border, and some swamp land adjoining, which was connected with the pond by a small stream or ditch. This land on one of its sides fronted oh a public highway known as Locust avenue. The portion of the tract taken by the city of New York comprised a part of the swamp land and some of the shore of the pond. In taking this land the city cut off access from the remainder except over two specified rights of way shown in the maps filed in pursuance of the statute. In their original claim of damages, the owners asked an award of damages in the sum of $34,800. This amount they increased by an amended claim to $35,600, in support of which they gave proofs. The city gave evidence tending to show that the damages were about $3,000 or $3,100. From, this great difference between the amount claimed and the amount awarded the owners argue that the commissioners arrived at their estimate by failing to take into consideration the value of the land for the purposes of harvesting ice, and in which purpose its sole practical value consisted. This argument seems to have impressed the learned court at Special Term, and contributed very materially to the decision n,ow under review. The whole tract of the owners comprised originally 7.318 acres, of which 4.998 acres were land and 3.33 acres in the pond. Of this entire tract, the city took 3.665 acres, leaving the owners 3.653 acres, of which 3.369 acres were in the pond and but 1.384 acres were land. The result of this taking was, according to the owners’ contention, to destroy entirely the suitability of the remainder of their property for ice harvesting purposes, and it was upon the basis of this contention that its estimate of its damages was framed. The damage to the land and pond not taken was calculated by the owners as follows:
As to the grade of the rights of way as shown on the city’s map, another question arises. These grades were concededly so steep as to-constitute a serious element of damage to the owner, and the commissioners so thought, as appears by the record. It is claimed by the owners that through a misunderstanding the commissioners omitted this item from their total estimate of damages. It is urged by the appellant that the commissioners made an allowance for it by awarding some $2,000 more damages than those estimated by the city’s expert witnesses. It appears from the owners’ proof that the rights of way granted by the city could be made of the former grade by the use of about 2,000 cubic yards of earth fill on the owner’s land, and of an easier grade by the use of 2,500 cubic yards. It is urged by the appellant that the commissioners in making the award at a sum in excess of the estimate of the city’s witnesses made provision for the cost of the earth fill. No evidence was given as to the cost of the fill, and, assuming that the award of the commissioners was intended to cover this item, there is nothing before the "court to show whether the provision, if made, was adequate or inadequate. This objection, however, is not grave enough to require the setting aside of the report and the appointment of new commiss.oners, as tire question can be met sufficiently by remitting the matter o the present commissioners for further proof and consideration. A more serious question arises on the ground of newly discovered evidence. Since the commissioners made and filed their report, the city has begun its work of construe-:
The order appealed from should be só modified as to refer the matter back to the same commissioners fór a new hearing, and, as so -modified, affirmed, without costs. All concur.