Majority
Headnote
Set-Off and Counterclaim (§ 41[1] )—Contracts—Action by Subcontractor Against Contractor.The plaintiff was a subcontractor, the defendant the contractor, and this action is brought to recover a balance due for goods, wares, and merchandise furnished to the defendant. The claim was for $117.24. Two defenses “counterclaimed”—(1) $350, and (2) $76.10. The learned Municipal Court allowed the plaintiff’s claim, allowed the first “counterclaim,” but disallowed the second “counterclaim,” so that the defendant recovered a judgment for $232.76.
I think that this was error. The defense in question set up that the contract between the defendant and the' owner of the premises provided that the work was to be done on November 15, 1907, and that in default thereof the contractor would pay $20 a day for liquidated damages, unless it could be clearly shown to the satisfaction of the architect that such delay was caused by a combination of the contractor’s' workmen, or by the act of God, or by a suspension of the work by written order of the architect; that plaintiff failed in the performance of his contract with the defendant; that such delay was not due to any of the said excepted causes; that by reason of the delay defendant was obliged to pay and did pay $350 as and for liquidated damages under the contract (i. e., that with the owner); and that plaintiff’s contract with the defendant was to be completed by November 15, 1907.
The defendant, to establish this defense, gave evidence that May, an officer of the plaintiff, received personal injuries from falling into an excavation in the premises; that he presented a claim therefor against the owner thereof; that the owner agreed with the defendant that
The judgment is reversed, and a new trial is ordered; costs to abide the event. All concur.