Majority
Headnote
1. Evidence (§ 471[1] )—Opinions—Trenches in Street—Methods of Work.This case was before this court upon a prior ap-peal, and is reported in 124 App. Div. 824 , 109 N. Y. Supp. 519 . Upon the second trial of the action the plaintiff has recovered a verdict . against both of the defendants in the sum of $2,500, and from the judgment entered upon such verdict the present appeal is taken.
The record in the present case varies from the former one in some -important particulars, of which the following may be instanced: There was proof upon the second trial from which the jury were warranted in finding that there was no litter or rubbish present in front -of, or near, the spot where the plaintiff attempted to cross the street, mor was there anything present at that spot to call his attention to any ■unusual danger there. The testimony was fuller as to the distance
The questions of fact were submitted to the jury in accordance with the principles laid down by this court in its prior opinion and there are no valid exceptions, as far as the defendant construction company is concerned, nor can the verdict against it be set aside as against the weight of evidence. The questions involved in the trial were purely questions of fact, and, as was said in Dorwin v. Westbrook, 11 App. Div. 394 , 42 N. Y. Supp. 1123 , affirmed 158 N. Y. 742 , 53 N. E. 1124 :
“As the jury are the final arbiters of the facts, the court must, after affording them reasonable opportunities to compare their own opinions of the facts with those held by the appellate court, finally accept the judgment of the jury.”
With respect to the defendant the city of New York, however, error was committed by allowing the testimony of the witness Southard to be received against it in the face of its objection and exception. The city rested its case after offering in evidence certain documentary proof, but produced no witnesses. The witness Southard was called by plaintiff in rebuttal of testimony adduced on behalf of the defendant Degnon-McEean Company, which bore upon the question of the usual and ordinary method of doing the work which was then in progress in Eorty-Second street, and in regard to the precautions which were usually taken to guard against dangers to the public in the prosecution of such work. His testimony was properly received, for it was proof of the procedure actually followed upon such work, and was not mere speculation or hypothesis. It was not, however, admissible against any defendant except the one whose testimony was thus sought to be rebutted; and such objection was at once taken by the counsel for the city, and the request made that the jury be instructed that the rebuttal evidence was not to be taken as against the city. The denial of this request constituted error, and, exception having been duly taken, the judgment, so far as it affects the city of New York, must be reversed.
The judgment and order appealed from are affirmed, with costs to the respondent, as against the defendant Degnon-McLean Contracting Company, and reversed as to the defendant the city of New York, and a new trial ordered, with costs as to the latter defendant to abide the event.