Majority
Headnote
1. Contracts (§ 147*)—Construction—Intention of Parties.On January 28, 1909, the plaintiffs and defendants entered into a written contract for the reconstruction of certain buildings, known as Nos. 113 and 113% Bowery, theretofore destroyed by fire. This contract not alone provided for the erection of the buildings and the payments to be made, but contained the following guaranties :
“Eleventh. The contractors agree to and do hereby guarantee the electric elevator and all its appurtenances and equipments and all electric light wiring and fixtures to be in perfect and easy working and running order, and to remain in such perfect and easy working and running order for the term of one year from May 1, 1909; and should the same or any part of such equipment be found to be defective after the completion of the building, they agree to replace the same with new” and perfect material or parts, and agree to
make all repairs thereto at their expense, for the said term of one year. Contractors shall also procure and furnish all required certificates.
“Twelfth. It is further expressly agreed that all materials used.' for said construction, inside or outside of said building, shall be new and first-class material.
“Thirteenth. The contractors guarantee to maintain the plumbing in the building in first-class condition for the period of one year, and also guarantee to maintain and keep the roof in repair at their own cost for the period of one year from May 1, 1909. The contractors also guarantee the steam plant and all its appurtenances to be in first-class working order and condition, and to supply the heat mentioned in the specifications for the term of one year from May 1, 1909.
“Fourteenth. All guaranties provided for in this contract shall survive the completion of the building and all payments to be made hereunder.”
On the 29th day of October, 1909, the parties hereto entered into another written contract, which recited the agreement of January 28, 1909, that certain disputes have arisen between the parties with respect to ftie reconstruction of said buildings, that the said disputes had been submitted to arbitration, that the arbitrators had awarded the defendants $2,640, and in consideration of the settlement of said disputes and the payment of said sum “the parties of the first part hereto” (the defendants) “hereby release and discharge the parties of the second part of and from said agreement of January 28, 1909, and of and from any and all agreements, claims, and demands whatsoever arising or that may arise out of the transactions had between the parties hereto on or relating to said rebuilding of the premises 113 and 113% Bowery, and of and from any and all claims and demands whatsoever in law or in equity to the date hereof,” and contains the following clauses:
“The parties of the first part do hereby transfer and assign unto the parties of the second part the following guaranties and all their right, title, and interest in and to each and every one of said guaranties, to wit: The guaranty of the Drum Elevator Company to keep the elevator and equipment in said building in repair against general wear and tear for one year from May 1, 1909. The guaranty of I. Block to keep the roof in repair for one year from May 1, 1909. The parties of the first' part agree to deliver unto parties of the second part the above guaranties, and all the other guaranties provided for in paragraphs 11, 12, 13, and 14 of said contract of January 28, 1909, and until such delivery, or in default of such delivery, the parties of the first part will remain, and hereby agree to remain, liable on said guaranties mentioned in said agreement of January 28, 1909. The parties of the first part further covenant and agree to indemnify, save, and hold the parties of the second part harmless from any liens or claims which may be made against them and against the said building 113 and 113% Bowery, by reason of the work and labor done or materials furnished thereon by the parties of the first part, in connection with said job of the rebuilding of said premises; and except as herein mentioned and reserved each of the parties hereto release the other from any further claims and demands whatsoever.”
The complaint in this action alleges the making of the agreement of January 28, 1909; recites the guaranties therein, above set forth; that plaintiffs' performed said agreement, and every part thereof, on their part to be performed; that between the 1st day of August, 1909, and the 1st day of May, 1910, the said elevator and the equipment and appurtenances were found to be and became defective and out of working order, and the roof of the buildings were found to be defective-and in a leaking condition; that plaintiffs, at divers times, noti
From an examination of the contract of January 28th, we find therein two separate agreements: One for the reconstruction of the buildings, that would be satisfied by the performance of its conditions, the construction of the buildings by the defendants, according to the plans and specifications, and the payment of the sums agreed to be paid by the plaintiffs; the other, the guaranties set forth in the eleventh and thirteenth paragraphs thereof, which would be satisfied by the maintenance in good order and repair of the parts of the buildings and their equipment therein specified for the term of one year from May 1, 1909, which the contract expressly provided (paragraph 14) “shall survive the completion of the building and all payments to be made hereunder.”
Had the buildings been completed and payments made in accordance with the terms of the contract in that behalf, no one could have claimed that the guaranties were satisfied and released, or an accord and satisfaction was had as to them, without doing violence to the expressed terms of the contract. The disputes of the parties, as appears from the contract of October 29th, related to the first agreement contained in the contract of January 28th, and the payment of amount awarded was an accord and satisfaction of that portion of the said contract. The release therein contained was a release of the plaintiffs from all claims and demands of the defendants, and not a release and discharge of the claims and demands of the plaintiffs against the defendants on account of the guaranties constituting the second agreement, unless such is found to be the intention of the parties from a consideration of the latter portion of the contract of October 29th. Upon turning to the last clause of the said contract, we read:
“And except as herein mentioned and reserved each of the parties hereto release the other from any further claims and demands whatsoever.”
This exception and reservation referred to the agreement of the defendants to assign and deliver to the plaintiffs the guaranties of Drum "Elevator Company, I. Block, and the delivery of their per
It is a_ fundamental rule for the construction of a written contract that the intent of the parties as expressed in .the words they have used must govern. It seems to us clear that it was the intent of the parties as expressed in the words of this contract' that defendants were to remain liable on the guaranties contained in the original contract until they delivered to the plaintiffs the additional guaranties called for by this contract and re-executed and delivered their own guaranties set forth in the original contract.
If it was the intention of the parties that this contract was to operate as a release, in praesenti, from the conditions of the original contract, so that no cause of action would arise under the original contract in favor of the plaintiffs, and reduce that contract to a mere evidentiary paper, from which the contract of October 29th might be made clear, as the learned justice held, why would the parties provide for a subsequent delivery of those very guaranties by defendants to plaintiffs? There remained something to be done under the contract of October 29th. The assignments were to be executed and delivered, and the guaranties delivered. The contract was therefore executory, and did not operate as a release and satisfaction until it was executed. Until that 'time the defendants were liable on the guaranties in the contract of January 28th.
The judgment should therefore be reversed, and a new trial granted, with costs to appellants to abide the event. All concur.