Majority
Headnote
1. Municipal Corporations (§ 360[1] )—Contracts—Extra Work.In July, 1893, the plaintiff’s assignor, one Ma-honey, entered into two contracts with the city of New York for “regulating and paving with macadam pavement” the roadway of Eleventh avenue from Kingsbridge road to Ft. George road and the roadway of Ft.. George avenue from Amsterdam to Eleventh avenue respectively. The contracts provided that the contractor should excavate the subsoil or other matter, whether earth, rock, or other material, to a specified depth, and that “if rock be encountered it shall be removed for at least three inches deeper.” In 1884 the city had let contracts for “regulating and grading” the streets in question, and under those contracts, according to provisions therein set forth, all rock was to be excavated to a depth of two feet below the curb line, and the excavation then refilled with soft filling to the street level. The contractors entered upon the performance of their work, and, several years before the contracts involved in this action were entered into, received payment in full upon proper certificates that the work required by the contracts had been fully performed.
There seems to be no question but that if the contracts for “regulating and grading” these streets had been actually performed as therein required, that then the performance of the contracts in question would not have necessitated the removal of any rock, except possibly for three inches along the gutters and such slight projections of rock as might be found in other places. When Mahoney commenced work under his contracts, however, he found, upon removing the soft filling on the surface of the streets, that the rock had in fact been removed to a depth of only about a foot below the curb, instead of two feet, as required by the contracts, and he immediately protested that he was not bound, under his contracts, to remove the rock which should have been removed under the contracts for the grading of the streets; but the city authorities having supervision of the work.insisted that the rock must be removed- by the plaintiff before the streets were paved. In order to fulfill his contracts, therefore, he and the plaintiff, to whom he assigned the contracts while the work was in progress, were obliged to excavate and remove about a foot of rock beneath all the pavement laid. After completing the contracts, plaintiff brought two actions to recover the cost of removing this rock. Upon the trial they w,ere consolidated, and the jury rendered a verdict in favor of the plaintiff for $37,485; the only questions submitted to them being the amount of the extra or additional work done and its value. From the judgment entered thereon and an order denying a motion for a new trial, defendant appeals.
It is not seriously disputed but what both parties to the contracts, when they were entered into, supposed that the work of grading under the prior contracts had been fully and completely performed. All of the surrounding circumstances leading up to the execution of, as well as the contracts themselves, indicate that fact. The contracts were not for "grading,” but for "regulating and paving.” That being so, I am of the opinion the case cannot be distinguished in principle from Horgan v. Mayor, 160 N. Y. 516 , 55 N.
“The question that lies at the threshold of this case is, Did the city owe the duty to the plaintiff of having the outlet pipe of this pond in working order? * * * It was, of course, impossible when the plaintiff went upon the ground to examine the proposed work to see more than the outlet gate and the size thereof. Whether the sewer lying beyond was in a condition to carry off the water was something he could not ascertain by a mere inspection of the premises. A fair construction of the contract on this point authorized the contractor to assume that the pond could be drained of water in a general sense. There would, of course, be inequalities and irregularities on the bottom, where more or less water would remain, and which the contractor was bound to pump out and keep clear during the progress of laying the concrete work. * * * It seems to us a strained and unjust construction that would require the plaintiff, under these provisions, to remove, if necessary, the entire body of water from the pond. This latter work is a subject upon which the minds of the parties could not have met and the plaintiff in his estimates did not consider that he was called upon to pump out this great body of water lying upon an area of six acres. It was proper for the plaintiff to assume that the water of the lake could be discharged into the sewer through the outlet the city had constructed for that purpose.”
The words quoted are quite applicable to the facts in the present case, except that this plaintiff, if anything, occupies a more favorable position. An examination of the streets indicated that they had been graded. The contracts for such grading were on file in the Comotroller’s office, as public records with the certificates showing that the work had been fully performed, and for which the contractors had been paid in full. The plaintiff’s assignor, before making his estimates, personally ascertained both of these facts. Under his contract he had the right to select his own method of ascertaining the actual work to be done, and he adopted this method. If the plaintiff in the Horgan Case was justified in assuming from the mere existence of the outlet pipe that the lake could be substantially drained through it, it seems to me more clear that the plaintiff’s assignor was justified in assuming that the rock had been removed for two feet below the curb line. The contracts for the grading required it to be removed to that extent, and the public records of the city showed the contracts had been fully performed. The contract in the Horgan Case required the contractor to pump out the water from the lake, but this was held to mean simply the water that might remain in the lake owing to the
Dissent
I am of the opinion that the plaintiff was entitled to recover for this additional work, and since its performance was not controverted, the only questions for the jury, as the trial court held, were the amount of such work and its value.
Objection is made to the form of the complaints but they allege facts sufficient to sustain the recovery. It is not necessary to determine the exact form of the action, because it does not appear that the question was properly raised upon the trial, or that the defendant was misled or prejudiced in any way on that account. Neither were there any errors committed calling for reversal.
The judgment and order appealed from must, therefore, be affirmed, with costs.
MILLER, and DOWLING, JJ., concur.”
(dissenting). The cause of action, as stated by the respondent is • “an action in quantum meruit for the reasonable value of rock excavation as damages fbr the breach of the paving contracts arising from the wrongful direction of the defendant, its officers and agents, requiring the plaintiff’s assignor and the plaintiff to excavate rock which was not included in the terms of the paving contracts.” To sustain this cause of action the plaintiff must first prove a breach of the contract by the defendant, and that the damage arising from that breach was the cost to the plaintiff of making the rock excavation, for which he has recovered. It is difficult to see how there could possibly be a breach by the defendant of its contract which would entail upon it a liability for the costs of excavating the rock, unless somewhere in the contract there was an obligation imposed upon the defendant to excavate this rock which the plaintiff did excavate.
The plaintiff seems to eliminate any cause of action based upon an additional contract, either as extra work under the contract executed, or upon the theory that the directions of the defendant’s officers to ■excavate this additional rock was a new and independent' contract; but it is quite evident that upon neither of these theories would the plaintiff be entitled to recover.
It is a principle universally established that “in cases of public agents the public corporation is not bound unless it manifestly ap
Now, the charter of the city of New York expressly limits the power of the corporate officers to make any contract, except one based upon proposals which have been duly advertised, and then the contract must be made to the lowest bidder. Section 419, c. 466, Laws 1901. It is not claimed that there was any contract made for excavating this rock, based upon such bids as the charter requires, unless it was included within the contract actually made between the plaintiff’s assignor and the defendant, and under which the work in question was performed. The city of New York was not, therefore, liable to the plaintiff for any work done under the contract, except for the amount expressly agreed to be paid to the plaintiff’s assignor by its terms; nor can there be any liability for extra work under this contract, as that would be a violation of the charter provisions and in violation of the express provisions of the contract.
It would seem, therefore, that the plaintiff was quite correct in basing his sole right to recover upon an alleged breach by the defendant of some provision of the contract, and to recover damages for a breach of the contract, it would seem to be essential that such a breach should be established by the evidence.
Now, the city of New York, wishing to pave Eleventh avenue from ICingsbridge road to Et. George road with macadam pavement, and in pursuance of an ordinance of the city of New York it issued to contractors proposals for bids “Eor regulating and paving with macadam pavement the roadway of Eleventh avenue from ICingsbridge road to north curb line of Ft. George road.” It will be noticed that these proposals started out with the statement that the work to be done was “regulating and paving.” The proposal then recited the ordinance of the common council, and provided that the “estimates of the above work indorsed with the above title, also with the name of person or persons making the same, and the date of presentation, will be received at the office of the department of public works, until 12 o’clock m., of Tuesday, June 13, 1893, at which place and hour the
“As the above-mentioned quantities, though stated with as much accuracy as is possible in advance, are approximate only, bidders are required to submit their estimates upon the following express conditions, which shall apply to and become part of every estimate received.
“(1) Bidders must satisfy themselves by personal examination of the location of the proposed work, and by such other means as they may prefer, as to the accuracy of the foregoing estimate, and shall not, at any time after the submission of an estimate, dispute or complain of such statement or estimate of the engineer, nor assert that there was any misunderstanding in regard to the depth of the excavation to be made, or the nature or amount of the work to be done. * * * No extra compensation beyond the amount payable for the several classes of work before enumerated which shall be actually performed, at the prices therefor to be specified by the lowest bidder, shall be due or payable for the entire work. * * * Work or materials not specified and for which -a price is not named in the contract, will not be allowed for.”
This proposal for bids was signed by the Commissioner of Public Works; and annexed to this proposal was a form of contract with blanks to be filled in with the name of the bidder to whom the contract was awarded and the price to be paid for the work.
In reply to this proposal the plaintiff’s assignor submitted a bid which was accepted and the contract duly executed. By this contract dated the 29th day of July, 1893, the plaintiff’s assignor agreed, for the consideration thereinafter mentioned, to furnish and provide, at his or their own proper costs and expense, all the necessary materials and the labor and in a good, firm, and substantial manner, and strictly in accordance with the following specifications, regulate and pave with macadam pavement the roadway of Eleventh avenue, from Kings-bridge road to North curb line of Ft. George road; and also lay and relay crosswalks; “all the said work to be done in the manner and under the conditions hereinafter specified.” The contract further provided that the contractor will not at any time “dispute or complain of such statement, nor assert that there was any misunderstanding in regard to the depth of the excavation to be made or quantity of filling that may be required to place the pavement upon the required grade, or the nature or amount of the materials to be furnished or work to be done; and he covenants and agrees that he will complete the entire work to the satisfaction of the commissioners' of public works and in substantial accordance with said specifications, and that he will not ask, demand, sue for, or recover for the entire work, any extra compensation beyond the amount payable for the several classes of
“In case there shall be, at the time stipulated for the commencement of the work, any earth, rubbish, or other incumbrance on the line of the work, the same is to be removed at the expense of the contractor.”
And, further:
“Preparation of Road, etc.—All paving and other stones necessary to be removed shall be taken up and immediately removed from the line of the work; the subsoil or other matter (be it earth, rock or other material) shall then be excavated and removed by the contractor to such depth that when properly shaped and rolled it shall be sixteen inches below the surface of the broken stone when completed, irrespective of the finishing material, and sixteen inches below the surface of the stone pavement or new lines of bridge stones. If rock be encountered it shall be removed for at least three inches deep- * * *
“The roadbed shall be truly shaped and trimmed to the required grade and with such crown as shall be directed, by the water purveyor, and rolled to ultimate resistance with a roller weighing not less than ten tons where practicable, until the surface is firm and compact, and if the material will not admit of satisfactory rolling, such material must be removed by and at the expense of the contractor, and proper material substituted. **♦*#**#***♦*♦
“Depth of Pavement.
“The pavement, when completed, shall be, when practicable, at each point of such construction, at least of such a depth as required by the specifications and of such crown and such form of gutter as shall be directed, and in any case the thickness of the pavement is to be determined on a line at right angles to the grade and crown.”
The plaintiff’s assignor further agreed that he would obey and conform to all ordinances of the corporation of the city of New York then in force, or that might be in force, during the progress of such work in relation to blasting rocks in the streets and avenues of said city; and further agreed:
“To receive the following prices as full compensation for furnishing all the materials and performing all the labor which may be required in the prosecution of the whole of the work to be done' under this agreement, and in all respects performing and completing the same, to wit, for the new pavement per square yard the sum of ($1.95) one dollar and ninety-five cents; for furnishing and laying new bridge stones, per square foot, the sum of (650) sixty-five cents. It being expressly understood that the measurements shall be taken after the laying or settling of the pavement and bridge stones, and that the aforesaid prices cover the furnishing of all the different materials and all the labor, and the performance of all the work mentioned in this specification and agreement."
The contract having been executed and the plaintiff’s assignor having assigned this contract to the plaintiff, the plaintiff proceeded with the work. After commencing the work it was found that the proper performance of the contract required the excavation of certain rock underneath the surface of the street as.it had been before regulated and graded. The plaintiff protested against being compelled to ex
The plaintiff does not specify what particular clause of this contract the defendant failed to perform, and I can see in the contract no duty assumed by the defendant which it has not fully performed. There was no representation made in the contract as to whether or not excavation of rock would be necessary, and by the contract the plaintiff’s assignor in express terms undertook to remove such rock as should be found necessary to lay the pavement' as required by the contract. There were no representations by the city or by its responsible officers that no rock would be found, or that required the city to do any work which was necessary to prepare for the proper paving of the avenue. The plaintiff says that he was intrusted by his assignor to make the preliminary examination necessary for putting in a bid; that he visited the locality, examined the surface of the existing avenue, and that he then found that a number of years before that there had been a contract made for regulating and grading this avenue. He examined the contract for such regulating and grading,- and found that it required the excavation of rock upon the line of the avenue to such a depth that if that contract had been properly performed no rock excavation would have been necessary. He then examined the certificate of the then commissioner of public works, and found that he had certified that the contract had been performed and thereby assumed that all rock had been excavated; and it was based upon this examination of that contract and the certificate of the responsible city officers that the contract had been performed that he assumed that no rock excavation would be necessary, and, therefore, submitted the bid in question.
In the proposals for this work which included by express terms regulating and paving of this avenue, there was no mention made of the former contract; nor was this contract in any. way based upon any assumption by the city or its officials that that other contract had been performed in accordance with its terms; and we may assume that the city had been defrauded by the official who had certified that the former contract had been performed, when it had not, and had there paid to the contractor a sum of money to which he was not entitled; but I cannot see how that can possibly affect the right of the city to require of the plaintiff or his assignor to perform this contract. There was no representation made by the city to this plaintiff nor his assignor that that contract had been completed according to its terms. There was no presumption that the former officials who had charge of the work under that contract had properly performed their duty, so as to affect the obligation of the plaintiff or his assignor in the performance of this contract. When this proposal was received there was a distinct statement in it which, by its terms, became a part of the contract, that the bidder must satisfy himself, by personal exam
Thus, the parties had in contemplation, when the contract was made, the contingency of rock excavation being necessary to enable the pavement to be laid as provided for by the contract, and it was expressly agreed that should such rock excavation be necessary, it should be made by the contractor at its own expense. Where, in this contract, is there one provision which either expressly or by implication, provides that the defendant should be under any obligation to remove any rock that should be found, or any representation or statement that any rock had been removed so that the pavement could be laid without excavation? There was no provision by which the city expressly agreed to do anything in regard to this avenue to prepare it for the laying of this pavement. There can be, as I see, no implied obligation to perform such work, but it seems to me that this rock was, by the express agreement of the parties, to be removed by the plaintiff as a part of the work that he had to perform, and that there was absolutely no breach of contract by the defendant which could possibly give the plaintiff a cause of action. The plaintiff, however, says that whatever the technical features of the action may be, he submits that the allegations of the complaint and the facts proved upon the trial support the judgment appealed from under a line of
The plaintiff also cites the case of Gearty v. Mayor, 171 N. Y: 61, 63 N.
I think there is no theory upon which this action can be sustained; no act of any of the city authorities for which the city can be held liable; no contract or agreement by which the plaintiff is entitled to receive any sum of money, except that already paid him, and no possible theory, that I can see, upon which the plaintiff can recover.
There is presented the rather unusual case of a person having made a contract with the city which, because of a misapprehension on his part as to the extent of the work to be done, has involved him in a loss; but the judgmerft must be satisfied with money raised by taxation. It cannot be affirmed, in my opinion, without breaking down the rules which are firmly established to protect municipal corporations from unjust claims made against them, rules which are perfectly familiar to every one making a contract with a municipal corporation, and which are necessary for the protection of the public; and the courts have, I think, no right to give to a contractor who has made a mistake in making a contract, an additional payment for the work that he has agreed to do when that money is to come out of the public treasury and ultimately must be supplied by taxation. The plaintiff knew perfectly well the obligations that he assumed. He entered into this contract upon an assumption, not based upon anything that the city or any of its officers said or did, but upon his examination of the work that he had to do, and because that assumption
I think, therefore, that no cause of action was alleged or proved, and that the judgment should be reversed and a new trial ordered.
LAUGHLIN, J., concurs.
Cases cited
- Horgan v. Mayor of New York 160 N. Y. 516 p. 61, p. 70