Majority
Headnote
1. Action (§ 65[1] )—Nature and Elements.The judgment and order should be reversed, and a new trial granted, with costs to appellant to abide event.
The action was brought to recover the balance unpaid upon a contract to construct on defendant’s premises á refrigerating plant and extra machinery connected therewith. The price of the plant was $8,732, to be paid one-third by three-months note when the machinery was delivered, another oneffhird in cash when the plant was completed, and the remaining one-third by a three-months note to be given at the time of such completion, which defendant might renew. The first note was given and paid, but the cash was not paid, nor the last note given. The balance unpaid was therefore about $5,822, and there was extra machinery furnished $53.10, making the total claim $5,875.10, besides interest. The verdict was directed for $6,218.65..
It was agreed plaintiff- should construct and deliver the plant in accordance with the specification annexed to the contract, ready to do work or on before March 1, 1909, and. if it did not accomplish the results guaranteed in the specifications, by reason of oversight or defect in construction, a reasonable time should be allowed plaintiff in which to accomplish said results, and when said specified results should have been accomplished, the defendant should accept the apparatus as complete and such acceptance should he final; but, if plaintiff should fail to accomplish the results specified within 90 days after the time for the* commencement of its operation, then no payments should be considered due and payable thereon, and the plaintiff should refund any amounts that may have been paid or advanced and should remove the apparatus from the premises where erected. And it was further agreed the apparatus should be and remain plaintiff’s property until fully paid for, and that in case of disagreement between the parties there should be an arbitration, the decision on which should be final. The specifications contained a guaranty by plaintiff that the apparatus should have a capacity when in full operation to make 12% tons of raw water ice per day of 24 hours in midsummer, when properly operated and run continuously, and that it should be capable of refrigerating equal to the melting of 30 tons of ice every 24 hours of continupus operation, if kept in good order and properly handled, and the temperature of the condensing water was not above 70 degrees Fahrenheit. The specifications provided that the defendant would properly insulate and furnish wood curbing for freezing tank, and foundations and tank floor, that the defendant would furnish foundations of plant and foundation for machine, pumps, or any part of the plant requiring one, constructed in the best manner, of first-class material, placed on a solid bottom, and any damage sustained by the plaintiff in setting up the work caused by imperfectly constructed foundations should be charged to defendant, and he should provide platform for brine tank and ammonia condenser.
The defendant claimed that the plaintiff failed to accomplish the results under the contract and specifications and to put the plant in condition to accomplish such results, and demanded that the $2,910 paid on the contract be returned, and he alleged damages in the sum of $10,000. On demand, a bill of particulars of such damages was fur
I think it must be said that there was evidence making it a question for the jury whether or not the plant fulfilled the terms of the guaranties. It was a question for the jury, also, whether such failure was due to the fault of the plaintiff or of the defendant. But the plaintiff claims these questions were of no consequence, because the defendant, with full knowledge of all defects, accepted and used the plant and did not offer to return the same. The action was "one at law; therefore the rights of the parties were to be determined as of the time the action was commenced. The machinery was installed June 21, 1909.' It did not operate satisfactorily. The defendant had 90 days under the contract to remedy defects, which would expire September 21, 1909. Eight days after that the action was begun. During that 90-day period a test was made for 21 days. This test was not satisfactory. The hardening room could not be used and the bunker room leaked. The 21-day test closed in July. Further efforts beyond that time were made to remedy the defects in the plant and building by both parties. The plant had to be run during the 90-day period to see if the defects were cured. It was run, it seems, for the 8 days thereafter before the action was begun. I do not find in the evidence that the plant was ever made so as to comply with the guaranties, or that there was any talk about an acceptance of the plant as it was, or about its being removed from the premises by the plaintiff. The court could not hold as matter of law that there was an express acceptance by the defendant of the plant. It must have found a constructive acceptance, and that alone from the use of the plant for the 8 days just prior to the commencement of the action.
This was error. It was at most a question for the jury, and should have been left to them, especially as the defendant by this finding was deprived of his defense that the guaranties were not complied with, and therefore he not only could not be compelled to pay the balance of the contract price, but was entitled to have the plaintiff remove the plant from his premises and pay back the money already advanced. There was no evidence that the defendant ever conceded the plant was constructed in compliance with the contract and the guaranties. He was always claiming it was not, and refused to pay the balance of the contract price. The complaint does not seem to allege acceptance in express words, but merely that there was a sale and delivery. The ordinary rules, in cases of the sale of personal property, as to return or acceptance of the property, are not applicable here. This plant was to be put in defendant’s building, was to remain plaintiff’s property till paid for, and plaintiff was to have an opportunity to correct defects for 90 days after the operation thereof was commenced. If then it
The parties, so far as the evidence discloses, did not talk or correspond about it for the few days intervening, and then this action was begun, and reliance is placed, not upon a compliance with the contract by the furnishing of a satisfactory plant, one in accordance with the contract and guaranties, but upon the technical claim that defendant, by using the part of the plant he did .for the few days,' accepted the whole plant, and such acceptance was final. The question might have been submitted to the jury, and, if a finding had been made favorable to the plaintiff, it very likely would have stood; but I cannot assent to the proposition that the limited use of the plant for a few days after the 90-day period had expired was as matter of law an acceptance of the plant. The use under the circumstances of this case for the 8 days should not be held to operate as acceptance, so as to cut off all defenses based upon failure to furnish the plant agreed upon, that would insure the results guaranteed. All concur. -