Majority
Headnote
1. Sales (§ 418[2] )—Breach by Seller—Damages .The action is for breach of contract. On the 1st day of August, 1909, the plaintiff entered into a written contract with the defendant for the purchase of “about 100,000” Roman brick, to be delivered when ordered. The defendant knew that the brick was intended for the courts, areas, and front of an apartment house, which the plaintiff was constructing on West 106th street, between Amsterdam avenue and Broadway, borough of Manhattan. The plaintiff ordered the entire quantity to be delivered forthwith, and when the contract was made the defendant was informed that loss would result to the plaintiff from delays in delivery. Wherefore a clause in the printed form of order prepared by the defendant, to the effect that it was “contingent upon strikes, accidents, or other delays beyond the control of the seller,” was stricken out. The evidence tended to show that the plaintiff made repeated demands for the delivery of the brick, but that the deliveries were of small lots of a few thousand each from September 9, 1909, to December 11, 1909. The evidence also tended to show that, if the brick had been delivered when ordered, the building would
[1] The learned trial judge dismissed the complaint, for the reason that there was no proof of the difference between the contract price and the market price' of similar brick at the time and place of delivery. But it is plain that the general rule of damage has no application to this case, and the question involved is whether there was any evidence of special damages which required the submission of the case to the jury. The general rule not being applicable, the plaintiff was entitled to recover such damages as were within the contemplation of the parties; i. e., those flowing directly and naturally from the breach.
[2] The impossibility of proving with mathematical exactness the amount of the damage sustained would not prevent a recovery, provided such damages were certain in their nature and in respect of the cause from which they proceed. Delafield v. Armsby, 131 App. Div. 572 , 116 N. Y. Supp. 71 , affirmed on opinion below 199 N. Y. 518 , 92 N. E. 1083 .
[3] The plaintiff claimed four items of damage, viz.: (1) $1,700, paid the building contractor as damages for delay; (2) $2,600, interest on the average value of the property during the 2% months of delay claimed; (3) $486, the proportionate amount of taxes assessed on the property for that time; (4) $7,758, rentals lost by reason of the delay. The plaintiff did not have to pay taxes or interest because of the delay.
With respect to the first item, the evidence showed that thé plaintiff agreed to pay the said contractor $1,700 as damages for the delay caused by the defendant’s breach and gave its note therefor; but that item included $1,400 as estimated damages sustained by the contractor by being prevented from doing work on other contracts. Obviously that item was too remote to be included.
[4] There was evidence, however, tending to show that the contractor was put to an extra expense of $300, paid to the workmen when idle and waiting for more brick to be delivered. The defendant’s breach of contract was the proximate cause of that damage, and it must be presumed to have been within the contemplation of the parties when the contract was made. It was, therefore, error to dismiss the complaint.
[5] As to the last item of damage, the defendant must have known that a delay in the completion of the building would deprive the plaintiff of the use of the property during such delay. Such damage, if shown, was the direct and natural result of the defendant’s breach.' There is one difficulty, however, in the proof on that head, resulting-from the fact that the building was not completed and ready for occupancy until October 1, 1910, and it would not have been completed
The judgment should be reversed, and a new trial granted, with costs to appellant to abide the event. All concur.