Majority
Headnote
1. Contracts (§ 352*)—Action on Excavation Contract—Question eob Jury—Authority of Contractor.The plaintiffs were copartners engaged in the business of excavating for foundations in the city of New York, and the defendants were general contractors and had taken a contract from the owners of premises on Longwood avenue, Kelly and Beck streets, in the borough of the Bronx, for the excavation for and the con
“That the said, parties of the second part herein hereby agree to do all the excavating and blasting of all the rock and stone on the plot 200' x 110' said premises being 200 feet on the south side of Longwood avenue and being 110' on Kelly street and 110 feet on Beck street, in the borough of the Bronx, city of New York, to the depth of eight feet six inches below the curb, of the entire plot, according to the plans of the owner of the said premises, subsequently to be shown.”
The plans of the owner, to which the contract refers, provided not only for the excavation of the entire plot of the dimensions stated in the contract, and to the depth therein stated, but to a depth in the main of about six inches more, and further for excavation work connected therewith or necessary for the construction of the foundation for the building, as follows: First, for an areaway on Longwood avenue 200 feet in length by 7 feet in width to the depth of 9 feet; second, an areaway on Kelly street 7 feet in width, 37 feet in length, and 9 feet in depth; third, an areaway on Beck street of the same dimensions; fourth, two boiler pits 37 feet in length by 18 feet 5 inches in width, and of a depth from the highest point of the curb adjacent to the premises, one 18 feet and 10 inches, and the other 14 feet 10% inches; fifth, two elevator pits 6 by 7 feet, 4 feet deeper than cellar bottom; and, sixth, for certain trenches for foundation walls.
[1] The plaintiffs also excavated 2 feet beyond the rear line of the premises described in the contract, for the width of 200 feet and to the depth of 1,0 feet. This, however, was not required by the plans, and the question as to whether it was- authorized by the defendants was properly submitted to the jury, and we find no error with respect to this item.
The action is brought to recover a balance claimed to be due on the contract, and for the excavation work below the depth of 8% feet and beyond the precise description given in the contract as for extra work. The court ruled as matter of law that this was all extra work, and that the plaintiffs were entitled to recover as compensation therefor the reasonable value of doing the work,-which was not governed by the contract price. It was claimed on the part of the plaintiffs, and evidence was given tending to support that view, that they did not see the plans until about the middle of May, 1909, when they had substantially finished the work of excavating the plot of ground of the dimensions specified in the contract, to the depth thereby required, and that it was much more expensive to them to go back and excavate these areaways and to the greater depth than if they had known that it was required at the outset, when they could have done it in connection with the main excavation, and that then it was agreed on the part of the defendants that they should do the other excavating as extra
The court in submitting the case to the jury instructed them as matter of law that plaintiffs were entitled to recover for all of these items as extra work, with the exception of the item for excavating two feet in the rear of the premises, which was left to the jury as a question of fact, as already stated. Counsel for the defendants duly excepted to the charge in this regard and requested the court to instruct the jury as follows:
“I ask your honor to charge the jury that if the jury believe that the-plans called for by the contract were in fact delivered to the plaintiffs early in January, 1909, and that the work claimed by the plaintiffs as extra work was in fact shown to be called for by the plans, the plaintiffs can recover only for the work actually performed by them at the rate provided for in the contract, and the jury can award the plaintiffs only the balance due them from the defendants at that rate.”
This request was declined, and an exception was duly taken. Counsel for the defendants also duly requested the court to instruct the jury on the same point as follows:
“If the jury find that the plans called for by the contract were in fjact delivered to plaintiffs early in January, 1909, and that the work claimed by plaintiffs as extra work was in fact shown and called for by the plans, plaintiffs can only recover for the work actually performed by them at the rate of $1-50 per cubic yard, and the jury can award plaintiffs only the balance due them from the defendants at that rate.”
Which was likewise refused and an exception was duly taken.
[2] We are of opinion that the court erred in ruling as matter of law that the contract was to be taken alone, and the plans excluded,.
The only question which I regard as not free from doubt is whether the specification in the contract, with respect to the depth of the excavation, is controlling. If so, the plaintiffs could have been compelled to excavate to the depth of precisely 8% feet below the curb, at every point. Manifestly that was not intended. The plans called for an excavation on the slant of the Longwood avenue curb along Longwood avenue to the depth of 9 feet, extending over about one half of the plot, and provided that the bottom of the other half of the plot should be level and that about one half of it should be 7% feet below the curb of Beck street, and the other half 7% feet below the curb of Kelly street. I am of opinion that the depth given in the contract should be regarded as an estimate, or approximate, only, to be read with the plans, and that the depth called for by the plans is not so materially greater as to entitle the plaintiffs to recover for the additional depth, as for extra work, at least, not if the plaintiffs saw the plans before proceeding with the work, and then proceeded without objection, as the jury would have been warranted in finding.
[3] On this theory there would be no consideration for the agreement to pay for this work as extra work claimed to have been made in May; and, moreover, if the jury found that the plaintiffs had a copy of the plans at the outset, they could not have found any agreement to pay for this work as extra work, for the only theory in support of such agreement is that the plaintiffs had not seen the plans until then. This was plainly the purpose of the requests, and I think they should have been granted.
INGRAHAM, P. J., and DOWLING, J., concur. MILLER and SCOTT, JJ., dissent.