Majority
Headnote
1. Master and Servant (§ 265[1] )—Obligations of Master—Performance-Presumptions.The defendant is a boat builder, having a plant near the Harlem river in the city of New York. In the building of a boat 125 feet long, it became necessary to construct a temporary building over the hull, to protect the workmen and the boat from the elements. The boat had been completed, or nearly so, and the plaintiff, who was an experienced ship carpenter, who had worked upon the premises for about seven years, was directed to assist in tearing down the temporary structure. The building was cheaply constructed, the roof being made with rafters reaching from the eaves to the ridge pole through the center, these being in turn coupled together with small timbers, to which boards 16 feet in length were nailed, extending from the ridge pole to the eaves on either side. For the purpose of shutting out the rain and snow, these boards were covered with strips of tarred paper about 18 inches wide, the same being held in place by strips of board overlapping the joints and nailed at intervals, and it was while the plaintiff was engaged in removing one of these slats that the strip of tarred paper on which he was sitting came loose and slid down the incline, carrying the plaintiff to the ground, some 20 feet below. He has been awarded a substantial verdict in a common-law action for negligence; the question submitted to the jury being whether the defendant had furnished the plaintiff with reasonably safe tools and appliances for the performance of the labor.
[1, 2] The presumption is, of course, that the master has performed this duty (20 Am. & Eng. Ency. of Law, 87), and there is absolutely no evidence in this case that any of the tools and appliances which were furnished by the defendant were defective or inadequate, or that there was any failure on the part of the defendant to supply all of the necessary tools and appliances now suggested as proper. It is true that the plaintiff testifies that there was no rope or ladder upon the building; but we know of no authority which holds that it is the duty of the master, in the performance of the details of the employé’s work, to follow him around with appliances. The duty is performed if the master has furnished such appliances as are reasonably necessary for the performance of the work, and the plaintiff has not overcome the presumption in favor of the master by merely showing that the defendant had not equipped the building with safety appliances to guard him in the performance of the work. He must go further, and show that the defendant, a boat-building concern, with a plant, had not supplied the necessary materials for the performance of the work. If there were ropes, ladders, etc., in and about the plant, which the plaintiff was at liberty to make use of, the defendant owed no further duty to the plaintiff, and there is no evidence to overcome the presumption that the master had supplied all of these things. There was evidence in the case sufficient to have warranted a jury in finding that the very building on which the plaintiff was injured
[3] Beyond this, the situation was entirely open and obvious to the plaintiff, a man of experience in the particular line. There were no hidden defects which the master was bound to know and to guard against, and the plaintiff by undertaking to do the work must be deemed to have accepted the open and obvious risks of the employment.
The judgment and order appealed from should be reversed, and a new trial granted.
Judgment and order reversed, and new trial granted; costs to abide the event. All concur.