Headnote
Sales (§ 81[1] )—Contracts—Performance—‘‘At Once.”Plaintiff sued to recover $300, alleged to be due for services rendered in making 300 signs, which the plaintiff claimed it completed and offered to defendants, and which the latter, refused to accept. The signs were made under a contract which provided:
“150 signs to be delivered at once and balance in three months from date of order.”
The contract was dated March 3, 1911. The plaintiff offered to deliver the goods bn April 6, 1911. The defendants refused to accept them, saying:
“It’s too late now, as my man is out on the road.”
The evidence showed that these signs were to be used by the defendants’ salesman for distribution among the Eastern trade. The contract specified that the delivery should be made “at once.” The plaintiff did not establish his right to recover by showing that he offered to deliver six weeks after the contract was made. The contract, by using the words “at once,” contemplated that delivery should
Judgment reversed, and a new trial ordered, with costs to the appellants to abide the event. All concur.