Headnote
Appeal from Trial Term, Madison County.Judgment and order affirmed, with costs. All concur, except SMITH, P. J., dissenting in part in memorandum.
(dissenting in part). The contract signed- is unambiguous. Plaintiff has recovered for extra work in doing work which was within the terms of the contract, on the ground that before the signing of the contract he was assured by the city authorities that a strict performance thereof would not be required. This holding seems to be unjustified, either upon principle or authority. Whatever right the plaintiff might have for reformation of the contract, until the contract is reformed he has no claim for additional compensation for work specifically required thereby. The judgment, therefore, so far as it awards additional compensation for work upon the reservoir site in taking the roots out from the land, is in my judgment unauthorized, and should be reversed.