Majority
Headnote
1. Contracts (§ 288*)—Construction—Progress Payments.The plaintiff made a contract with the O’Connor-Mc-Intire Company for certain work to be done by the latter in paving streets and constructing sidewalks and gutters. The work was to be fully performed for a lump sum of $11,000, and was to be completely finished by the 1st day of November, 1909. The contract contained the following clause:
“(4) Payments will be made monthly upon proper certificate of the superintendent of the amount of work done to the extent of eighty per cent, of the amount of said certificate, and the said party of the second part hereby agrees that the certificate of the said superintendent that the work has been faithfully performed in accordance with the requirements of the contract and these specifications herein contained shall be a condition precedent to the right of the said party of the second part to payment for the entire work or any part thereof due it under this agreement, and the said party of the second part further agrees that twenty per cent, of the amount due under any certificate under this agreement shall be retained by the party of the first part from the amount due to the said party of the second part at the time of making such payment.”
It was provided that, if the contractor should abandon the work or in any way violate any of the conditions of the contract, the' plaintiff might notify said contractor to discontinue all work or any part thereof, and that thereupon the plaintiff might complete the work itself at the expense of the contractor who bound itself and its bondsmen to
The contractor found' some difficulty in obtaining sufficient money or credit to carry on the work according to the terms of the contract, and on September 18, 1909, a supplementary or amendatory contract was entered into whereby plaintiff agreed to pay for labor and materials to be employed and furnished by the contractor, the amounts so paid to be pro tanto in lieu of the monthly payments provided to be paid to the contractor under the original contract. It was further provided that these payments for labor and materials should be so limited that the total amount thereof per month, together with the payments to be made monthly upon the proper certificate of the superintendent, as provided for by the original contract should not exceed 80 per cent, of the said certificate as therein provided, “the intention being [so reads the contract] that the amount of the monthly payments may be reduced by the amount paid by the party of the first part for necessary labor and materials as herein provided.” This supplementary and amendatory contract was formally consented to by the defendant on October 29, 1909. The plaintiff continued to pay for labor and materials under this last agreement until December 7, 1909, when it found it could pay no more without paying in excess of 80 per cent; of the value of the work done, whereupon it notified the contractor - to this effect, and further notified him that he must place more men upon-the job and push the work rapidly, and that failure to do so would- be considered an abandonment of the contract. No response was made by the contractor, and no further effort made by him to proceed with the work. The answer admits that defendant was duly notified of the contractor’s default, but defendant made no attempt to avail itself of the provision of the undertaking authorizing it to proceed with the completion of the work.
The plaintiff did proceed with and completed the work, expending, including the amounts paid under the original and supplementary contracts, a sum exceeding by over $4,000, the agreed contract price. It has recovered a judgment against defendant for the sum of $3,000, with interest, the amount of the undertaking; The answer, as amended at the trial, consists of formal denials on information and belief of parts of the complaint, and of a separate defense that the plaintiff and the O’Connor-McIntire Company made substantial changes in the original contract and the work done and to be done thereafter without the knowledge or consent of the defendant. No evidence was offered to support this separate defense.
[1] The defendant’s principal contention is that plaintiff overpaid the contractor,' and hence relieved the surety from the obligation of its un
[2] The contract made the superintendent the umpire to decide on the amount of work done, and both the contractor and the defendant are bound by his decision in the absence of fraud or palpable mistake, neither of which are charged.
[3] According to the unchallenged testimony of the superintendent, the amount paid to the contractor prior to the making of the supplemental contract represented 80 per cent, of the work done up to that time, and the sums paid for work and materials after that time
[4] The defendant makes a somewhat half-hearted objection to the act of plaintiff in paying for a lot of tarvia which the contractor had ordered, and left upon the ground when he abandoned the work. The objection is without substance. It is not claimed that too high a price was paid; and, if plaintiff had not taken over this tarvia and used it in completing the work, it would have been obliged to buy an equal amount elsewhere.
[5] That the superintendent made no certificate of the amount of' work done after the making of the supplementary contract is unimportant. The only purpose of such certificate was to fix the amount to be paid the contractor, and as the whole 80 per cent, payable was expended for labor and materials there was nothing to be paid the contractor, and no occasion for making certificates. Smith v. Mollesen, 148 N. Y. 248 , 42 N. E. 669 ; St. John’s College v. Ætna Indemnity Co., 201 N, Y. 341 , 94 N. E. 994 .
The judgment arid order must be affirmed, with costs. All concur.,