Majority
Headnote
Troves and Conversion (§ 2[1] )—Property Subject of Conversion—Defective Contract.The defendant was the owner of certain real estate in the city of New York, including a building thereon. It desired to tear down the building for the purpose of erecting a new one, and to that end entered into the contract with the plaintiffs referred'
I am unable to concur in this view. When the contract was made the building was real property, and its character as such could not be changed except by an actual severance from the land upon which it stood. The difference between the real and personal property exists, not by virtue of an agreement, but by nature of the subject. Real estate cannot be changed into personalty merely by calling it such. The walls of a building, no matter of what composed, so long as they remain an integral part of the building, are real estate, and it is beyond the power of parties interested, by agreement, to change them into personal property. Ford v. Cobb, 20 N. Y. 344 .
This was pointed out in Davis v. Bliss, 187 N. Y. 77 , 79 N. E. 851 , 10 L. R. A. (N. S.) 458 ; the court saying:
“It doubtless is the rule that personal property may be so firmly attached to or thoroughly and substantially made a part of the realty that its character as personalty will not be preserved even by special agreement intended to accomplish that result.”
In People ex rel. I. R. T. v. O’Donnel, 202 N. Y. 313 , 95 N. E. 762 , the question presented was whether certain machinery and power houses were real property within the meaning of the Rapid Transit Act (Daws 1891, c. 4). The court held that the machinery was not, but that the power houses were, saying:
“On the other hand, these power houses were most substantial structures, composed in large measure of brick and stone and steel and iron. They were so constructed on the land that apparently they could only be removed by utter demolition. They were primarily and essentially real property, and never had existence in any other character. They were so fundamentally real property that probably interested parties dealing with them could not, by express agreement, have given them any other character than that of real property.”
In Western Union Telegraph Co. v. B. & S. Ry. Co. (C. C.) 11 Fed. 1 , it was said that bricks which were built into the walls of a building, or shingles that form the roof, or stones that go into the foundation of a house, cannot, even by agreement of the parties/ be made to retain their character as personal property, for the obvious reason that they become so inseparably affixed to the realty as to be a part of it, independent of any question as to the intent of the parties.
In Warren v. Leland, supra, the court based its decision on the ground that growing trees became personalty merely by virtue of the contract of sale. But that decision was, to a certain extent, disapproved in Goodyear v. Vosburgh, 57 Barb. 243 , on the ground that the doctrine of constructive severance had nothing to do with the question decided. Green v. Armstrong, 1 Denio, 550 , and Vorebeck v. Roe, 50 Barb. 302 , merely mention the doctrine of constructive severance of growing trees or grass, without expressing any approval.
In Lacustrine Fertilizer Co. v. Lake G. & F. Co., supra, it was held that soil removed from the land of one person and placed on the land of another, with his consent, and without an intention on the part of the former to reclaim it, or an agreement authorizing him to remove it, becomes a part of the land of the latter.
Authorities, which hold that things of a personal nature, such as fixtures, etc., annexed to the freehold of a person other than the owner, may, by agreement between him and the owner, retain their character as chattels, are not applicable, and this for the reason that the chattels •in the cases to which the doctrine is applied were such originally • and never became a part of the land at least to such an extent as to lose their identity.
Here, we have a building standing upon land concededly real estate, and I am unable to see upon what principle an agreement to tear it down and remove the materials of which it is composed can change it * from real estate into personal property. If it does not, then the determination of the Appellate Term and the judgment of the City Court should be. reversed and a new trial ordered, with costs to appellant to •abide event.
INGRAHAM, P. J., and SCOTT, J., concur.
This is an action for the conversion of1125 loads of brick, 2 boilers, 10 tons of old iron, 50 windows, and 100 window sills. The defendant owned the premises, known as Nos. 71-77 East Eighty-Second street in the borough of Manhattan, New York, a five-story and basement brick apartment house, which had been erected thereon. On the 3d day of June, 1911, defendant entered into a contract in° writing and under seal with plaintiff by which it sold to him all the material of which the apartment house was composed with the exception of “a Fitzgibbons Boiler,” which the plaintiffs agreed to protect from injury during the demolition of the building; and plain
“Should the contractor complete all the work comprehended under this agreement on or before July 25, 1911, the owner will pay the contractor the sum of five hundred dollars ($500.00), as a bonus. In the event- of the" contractor failing to complete all the work comprehended under this agreement on or before August 3, 1911, the contractor shall pay the owner forthwith the sum of five hundred dollars ($500.00), as a penalty.”
The plaintiffs commenced work on the 5th day of June; and on the 25th of July, the date specified for the completion of the work, the building had been removed to the street level. There were three boilers in the basement of the building, only two of which, as has been seen, were purchased by the plaintiffs. The work remaining to be done at that time was the removal of these two boilers and the foundation walls, so far as they were required to be removed by the plaintiffs, and removing the débris. On July 25th and until July 28th or 29th, according to the testimony introduced in their behalf, the plaintiffs continued the work, including the removal of the foundation walls, with a gang of about 35 men, and then their men were driven from the premises by another contractor who was employed by the defendant to finish the work; but, according to testimony introduced by the defendant, the plaintiffs continued on the work during that time with only about seven or eight or ten men, and they were engaged in removing loose material, but did nothing further with respect to demolishing the foundation walls, which were of stone and brick. The plaintiffs were not permit
, The plaintiffs seek to recover the value of the material embraced in their contract remaining on the premises when they were excluded therefrom, and appropriated by the defendant or its contractor. The action is brought upon the theory that this material which had been part of the real property was constructively severed from the realty and at once became personal property by virtue of the contract. The uncontroverted evidence shows that some of the material claimed to have been converted had been severed from the building and remained upon the premises or adjacent thereto; and evidence by the plaintiffs tends to show that the two boilers had been severed and were loose and detached, but that is controverted. With the exception of the boilers, there is a conflict in the evidence with respect to the quantity of the various items of material for which the plaintiffs seek to recover; but they adduced evidence tending to "show the quantities and values as alleged. If therefore the plaintiffs were entitled to recover for all of the material, the amount of damages became a fair question of fact on the evidence, which was sufficient to sustain the verdict. If, however, as contended by the learned counsel for the defendant, the plaintiffs were only entitled to recover for that -part of the material which had been actually severed from the building, then the verdict cannot be sustained, either on the evidence, or on the theory on which the case was tried, for the evidence shows that a large part of the material had not been severed from the realty, and the case was submitted to the jury on the theory that the plaintiffs were entitled to recover for all of it.
It is contended in behalf of the defendant that the trial court erred in not submitting to the jury the question «as to whether its claim that the plaintiffs did not prosecute the work with due diligence, which if sustained would have entitled it to take possession and complete the work, was not well founded. The charge indicates that the learned trial court was of opinion that title to all the material passed to the - plaintiffs, by virtue of- the contract, unaffected by the question as to whether or not the defendant exercised its right, in the event that the facts justified it, to'take possession of the work and complete it; and that inasmuch as no counterclaim was pleaded for the expense of completing the work, as contemplated by the contract in such event, the court did riot deem that question important. It is not necessary to express an opinion on that point on this appeal, for it is not fairly presented. Counsel for the defendant requested the court to rule, as ■ matter of law, that his client was entitled to-exclude the plaintiffs from the preinises and.to finish the work. The court properly declined to instruct the jury, as so’ requested, for that depended upon conflicting evidence. No request was made to submit the question of fact to the jury as to whether the circumstances were-such-as to- justify the de
“You come down, therefore, to the question of damages, and there must he some damage in this case, in view of the construction which the court has placed upon that instrument”—meaning the contract.
An exception was taken by defendant to this instruction. It is now claimed that the court thereby, in effect, took from the jury the question of fact with respect to whether or not the defendant was justified • in excluding the plaintiffs from the work, and ruled as matter of law that it was not. It is manifest that this part of the charge "did not relate to that question, and it was the duty of counsel, if he thought it did, to draw the attention of the court thereto specifically.
Counsel for the defendant contends, inasmuch as time was of the essence of the contract and the work was required to be completed on or before the 25th day of July, that the plaintiffs were in default, and that they forfeited any right they might otherwise have had to the material. I am of opinion that in view of the provisions of article 8 of the contract, herein quoted, the plaintiffs had until and including the 3d day of August to complete the work. If the plaintiffs completed the work on or before the 25th day of July, the defendant agreed to give them a bonus of $500; and, in the event of their failure to complete the work on or before the 3d day of August, they became liable to the defendant in a like sum, as a penalty. That provision necessarily gave the plaintiffs the right to continue the work until the 3d day of August, if by due diligence it could not be completed sooner. See Vandegrift v. Cowles Eng. Co., 161 N. Y. 435 , 55 N. E. 941 , 48 L. R. A. 685 .
The remaining question is as to whether this contract constituted a severance of the building material from the realty, so that, as between the parties, title thereto at once passed to the plaintiffs as personal property. I am of opinion that it did and that the defendant is liable therefor in conversion. Stackpole v. Eastern Rd., 62 N. H. 493 ; 2 Cooley on Torts (3d Ed.) 838; Tyson v. Post, 108 N. Y. 217 , 15 N. E. 316 , 2 Am. St. Rep. 409 . The building was, of course, realty, and the statute of frauds requires that a contract for the sale thereof to be valid should be in writing (McGregor v. Brown, 10 N. Y. 114 ; Green v. Armstrong, 1 Denio, 550 ; see, also, Bank of Lansingburgh v. Crary, 1 Barb. 542 ; Warren v. Leland, 2 Barb. 613 ; Vorebeck v. Roe, 50 Barb. 302 ), and the contract in question fully answers that requirement. The law is well settled in this jurisdiction that growing timber becomes as between the owner and vendee constructively severed from the realty under a valid contract of sale thereof. Bank of Lansingburgh v. Crary, supra; Warren v. Leland, supra. See, also, Lacustrine Co. v. Lake Guano, etc., Co., 19 Hun, 47 ; Id., 82 N. Y. 476 ; Goodyear v. Vosburgh, 57 Barb. 243 ; Smith v. Jenks, 1 Denio, 580 ; Kingsley v. Holbrook, 45 N. H. 313 , 86 Am. Dec. 173 ; Hoit v. Stratton Hills, 54 N.
In the case at bar, the only parties in interest, or who could in any manner be affected by the contract, which contemplated the actual severance of the building with expedition, were the owner and the plaintiffs. In the cases in which a different rule has been authoritatively laid down, recording acts or the rights of third parties, or public interests, were involved. See Ford v. Cobb, 20 N. Y. 344 ; Fryatt v. Sullivan Co., 5 Hill, 116 ; Tifft v. Horton, 53 N. Y. 377 ; 13 Am. Rep. 537 ; Duffus v. Howard Furnace Co., 8 App. Div. 567 , 40 N. Y. Supp. 925 ; Voorhees v. McGinnis, 48 N. Y. 278 ; Sisson v. Hibbard, 75 N. Y. 542 ; Lacustrine Co. v. Lake Guano, etc., Co., supra; Vorebeck v. Roe, supra; Davis v. Bliss, 187 N. Y. 77 , 79 N. E. 851 , 10 L. R. A. (N. S.) 458 ; People ex rel. I. R. T. v. O’Donnel, 202 N. Y. 313 , 95 N. E. 762 ; 13 Am. & Eng. Enc. of Law (2d Ed.) p. 622.
I am of opinion, therefore, that the plaintiffs were entitled to recover for the material not actually severed, as well as for the material which had been actually severed from the realty. These views lead to an affirmance of the determination of the Appellate Term, with costs.
CLARKE, J., concurs.
Cases cited
- Ford v. Cobb 20 N. Y. 344 p. 853, p. 858
- Davis v. Bliss 187 N. Y. 77 at 79 p. 853, p. 858
- People ex rel. Interborough Rapid Transit Co. v. O'Donnel 202 N. Y. 313 p. 853, p. 858
- Warren v. Leland 2 Barb. 613 p. 854, p. 857
- Bank of Lansingburgh v. Crary 1 Barb. 542 p. 854, p. 857
- Goodyear v. Vosburgh 57 Barb. 243 p. 854, p. 857
- Vorebeck v. Roe 50 Barb. 302 p. 854, p. 857
- Vandegrift v. Cowles Engineering Co. 161 N. Y. 435 p. 857
- Tyson v. Post 108 N. Y. 217 p. 857
- McGregor v. Brown 10 N. Y. 114 p. 857
- Lacustrine Fertilizer Co. v. Lake Guano & Fertilizer Co. 82 N. Y. 476 p. 857
- McFadden v. Allen 134 N. Y. 489 p. 858
- Mott v. Palmer 1 N. Y. 564 p. 858
- Leonard v. Clough 133 N. Y. 292 p. 858
- Tifft v. Horton 53 N. Y. 377 p. 858
- Duffus v. Howard Furnace Co. 8 App. Div. 567 p. 858
- Voorhees v. McGinnis 48 N. Y. 278 p. 858
- Sisson v. Hibbard 75 N. Y. 542 p. 858