Majority
Headnote
1. Municipal Corporations (§ 354*)—Contracts—Cancellation—Viola-tion of Labor Laiv.This action is brought pursuant to the provisions of section 3 of the Labor Law (Consol. Laws, c. 31 [Laws of 1909, c. 36], as amended by Laws of 1909, c. 292) by a citizen of the city of • Buffalo to obtain the cancellation of a contract made by the defendants Hosier & Summers with the defendant city of Buffalo for the erection by the former of the Technical High School, and as further relief that the defendant Justice, as the comptroller of the city of Buffalo, be enjoined and restrained from paying to the defendants Hosier & Summers any moneys to apply upon said contract, and that the moneys already paid to Hosier & Summers upon said contract be refunded to the city by Hosier & Summers and the officers of defendant city who are defendants in this action. The ground upon which plaintiff seeks to base his cause of action is an alleged violation of section 3 of the statute in the “manner of performance” of the contract.
[1] The complaint being, as has been said, based upon an alleged violation of section 3 of the Labor Law in the manner of performance of the contract which Hosier & Summers had with the city of Buffalo for the erection of this public building, it is important to determine whether at the time of the violations alleged there was in fact a contract between these parties. These violations all occurred between the 17th of April and the 1st day of May, 1910. The formal written contract was not in fact signed till May 22d following. Plaintiff, however, contends that the contract was in fact made as early as April 4th preceding.
There is no dispute that proper proceedings were had by the duly authorized city officials by which plans and specifications for the proposed building were duly adopted, a notice duly published calling for
[2] Doubtless the common council, after duly authorizing its superintendent of public works to enter into this written contract, could not, nor could that official of his own motion, arbitrarily refuse to compíete the business of making the contract by accepting a satisfactory bond of the contractor and signing a written contract conforming to the advertisement, the bid, and its acceptance. Sufficient authority for this proposition may, I think, be found in the cases cited and reviewed in the prevailing opinion in Molloy v. City of New Rochelle, 198 N. Y. 402 , but a contract in form to bind the city as a contract between the parties for the actual construction of the building had not then been completed. The bidder was still required to furnish a satisfactory bond, which was thereafter to be formally approved, and the written contract was to be prepared and signed, for no other contract than a written contract in such case could be a contract between the parties as the charter of defendant city provides. I think, therefore, the trial court was right in holding that at the time of the violations complained of defendants did not, in the manner of performance of a contract with the city, violate the provisions of section 3, for at the time of the violations alleged the contract had not yet come into existence. Hepburn v. City of Philadelphia, 149 Pa. 335 , 24 Atl. 279 ; Water Com’rs of Jersey City v. Brown, 32 N. J. Law, 504 ; Edge-Moor Bridge Works v. County of Bristol, 170 Mass. 528 , 49 N. E. 918 ; Dillon’s Municipal Corporation (5th Ed.) § 810.
1 The violations alleged occurred while a subcontractor named Brown H was engaged in excavating upon the site of the building. The particuI lar violations alleged were that this subcontractor permitted or re-I quired laborers engaged in the performance of that work to work H more than eight hours a day. This excavation was a part of the work H included in the specifications, and also in the written contract there
[3] Appellant claims that, even though it be held there existed no actual contract between the city and the contractor until the written contract was signed, yet when it was signed it related back to the time the commissioner of public works was authorized to enter into it for the city, and the statute having been violated in the performance of a part of the work contemplated by the contract in the interim between the authorization and the making of the contract, the contract itself at once became void because of the previous violations. It does not seem that can be held to result from these facts. It is conceded that after the written contract was in fact made no violations of the statute have been shown. The utmost that could justly be claimed as a result of the previous violations would be that the persons who “required or permitted” them could not recover for the work in doing which the violations occurred; the work having been done in anticipation of, and not under, the contract. But this is not the principal purpose of the present action. It attacks the validity of the whole contract.
No intimation is made that the execution of the written contract was unduly delayed for the purpose of permitting any part of the work contemplated to be done' without the statutory restrictions as to the manner of performance. It is doubtless true that, if there were a basis for a suggestion that thé execution of the contract was in fact delayed for the purpose, even incidentally, of avoiding the statutory prohibitions, it would be held, and properly enough, that the contractors had in fact violated the statute, and no contract, under those circumstances, should have been thereafter made with them, and, if made, it would have been void. But the good faith of defendants is not attacked.
[4] I think, also, that the trial court held properly that, even conceding that the work being done by Brown, the subcontractor, at the time of the violations alleged, was done under the contract between the city and the contractors, the evidence does not show that any of these violations were required, or permitted, by the contractors, or even that they occurred with their knowledge or consent. It would seem to be a manifest injustice to hold that violations of the statute for which the contractors were not responsible, as having themselves required or permitted them, or as having with actual knowledge, or under such circumstances as would properly charge them with constructive knowledge that violations of the statute were either required or permitted by others, who were engaged on the work, could properly be attributed to the contractors for the purpose of enforcing the drastic penalty of a forfeiture of the contract. The opinion of the trial court on this branch of the case leaves nothing of importance to be said.
The judgment should be affirmed, with costs. All concur.
Cases cited
- Molloy v. City of New Rochelle 198 N. Y. 402 p. 223