Majority
Headnote
Contracts (§ 198*)—Construction.The defendant, undertaking to build a vault in a cemetery, contracted with the plaintiff to drive piles for the foundation. The contract indicates that it was estimated that 181 piles, each 20 feet in length, would be required, for which a gross payment of $5,460 was stipulated. But it was also considered that there might be required, (1) some additional piles; (2) additional lengths of piling ; (3) shorter piles, should they be “found sufficientand it was stipulated that additional piles or additional lengths of piling should be paid for at $1.30 per lineal foot, and that for piles shorter than 20 feet deduction from that length should be made at the rate of 60 cents per lineal foot. But how would it be determined whether the 181 piles, each of 20 feet length, or longer or shorter piling, would be required ?
“The pile core shall in each case be driven until not more than ten blows ■ of a No. 2 vulcan steam hammer are required to "secure 1 inch penetration. Should boulders or other obstructions be encountered which prevent securing further penetration, driving shall cease and the pile be considered a completed pile, unless such obstructions are removed by you to permit of further driving. Length of pile to be paid for shall be the length of shell actually driven in the ground, unless the shell is filled to a point above the surface of the ground, in which case the length of pile to be paid for shall be the length from the point of the shell to the top of the concrete in said shell.”
The defendant’s argument is that less than ten blows of the hammer in fact were required to secure one inch penetration, and that, although the pile has been driven beneath the surface, pile should have been driven on pile until ten blows or less did not secure one inch penetration. According to that view, the pile wholly driven ceases to be the limit, but indefinite piles must be superimposed one upon another until the hammer in ten blows has exhausted its power to drive the vertical series another inch. The plaintiff insists that the pile, whatever its length, is the unit, and that, when it has been driven and the necessary resistance not met, another of greater length in the defendant’s discretion may be driven, but not upon top of it, and that, if the pile is wholly inserted, it becomes a completed pile if, before its full length has been driven, ten blows of the hammer will not drive it another inch, or “boulders or other obstructions be encountered which prevent securing further penetration.” But the defendant urges that, although the pile be fully in the ground, it shall be driven down as long as the ten blows of the hammer can make it penetrate a further
“It was understood that you drive on Thursday with your 40 ft. core, it being assumed from the borings that the required resistance can be secured with this core, if not, why then other steps will have to be taken.”
It is inferable from the letter that the length of the pile required was determinable from knowledge already at hand and not from inserting a pile, and, if it did not meet requisite resistance, piecing it out with other piles, end on end, until sufficient lengths were in the one line. In the absence of knowledge of practical operation advising otherwise, I think that such process of extension is not the intention of the contract.
Therefore the judgment and order should be reversed, and a new trial granted; costs to abide the event. All concur.