Majority
Headnote
United States (§ 70*)—Contracts—Construction. A provision of a contract for dredging necessary in the construction of a government storage dock, that the constructing quartermaster should pass on the “quality of work done,” did not authorize him to decide, as between the contractor and subcontractor, whether the material which the subcontractor failed to excavate was “hardpan,” which the subcontract, by its terms, did not cover.Plaintiff contracted with the United States to furnish all the labor and material required for the construction of a storage
“Third. Should any dispute arise respecting the true construction or meaning of the drawings or specifications or quality of work done, the same shall be decided by the constructing quartermaster, Ft. Wood, N. Y. H., and his decision shall be final and conclusive.”
“Fifth. It is agreed that if the party of the second part should encounter ledge rock or hardpan in the execution of this contract, that this material is not to be removed under the terms of this contract." ¿
The defendant concededly did not complete the contract, but, after working at it for some time, discontinued work. This action is for damages suffered by plaintiff by reason of defendant’s fault. Defendant attempts to justify its discontinuance by the assertion that it encountered “hardpan,” which it was not required to remove, and that it did in fact remove everything but hardpan. The issue as to whether hardpan was encountered went to the jury, which found in defendant’s favor. On motion, the court set aside the verdict and ordered a new trial “on the grounds that the said verdict is against the weight of evidence and as a matter of judicial discretion.”
The verdict was clearly against the evidence. Certainly the defendant did not sustain the burden of justifying its default. For this reason, if for no other, the orders should be affirmed. It is not necessary to pass upon the many exceptions taken during the trial, except to express the opinion that the provision in clause 3 of the contract, providing that the constructing quartermaster should pass on the “quality of work done,” did not impose upon him the duty or authority to decide, as between -plaintiff and defendant, whether the material which defendant failed to excavate was or was not “hardpan.” That was not a question as to the “quality of work done.”
■Orders affirmed, with costs to respondent. All concur.