Majority
Headnote
Landlord and Tenant (§ 298[1] )—Removal of Tenant—Summary Proceeding—Claims of Tenant.The plaintiff landlord herein appeals from an order, based upon the verdict of a jury, dismissing its petition to .remove the defendant tenant for nonpayment of rent. The nonpayment of rent and other necessary proof required of the landlord were admitted; but the
The seventh and eighth counterclaims are for damages caused by the negligent manner of performing work pursuant to an order issued by the Public Service Commission in connection with the construction of the subway. The evidence shows clearly that this work was done by the Degnon Construction Company, an independent contractor, over which company the plaintiff had no control, and for the acts of which it could not be held legally liable. The submission of these counterclaims to the jury was error, highly prejudicial to plaintiff, and must have largely influenced the jury in rendering a verdict in favor of defendant, which, in effect, was a finding that defendant had suffered damage under the various counterclaims submitted to them, in excess of the amount of rent due, $2,916.70.
As to the other counterclaims, they consisted principally of demands for damages caused by the negligent manner of doing work required by the municipal authorities, or repair work, which, under the provisions of the lease, the tenant was obligated to do, and which plaintiff undertook to do at the request of the defendant. As to these items, the proof as to negligence in the manner of doing the work, and as to the extent of the damage thereby suffered by defendant, is vague and, inconclusive, and not sufficient to support the jury’s verdict.
For these reasons the judgment and final order should be reversed, and a new trial granted, with costs to appellant to abide the event.
PAGE, J., concurs. WHITAKER, J., dissents.