Majority
Headnote
Municipal Corporations (§ 374[1] ) — Action on Contract — Public Work— Sufficiency of Evidence — Amount of Work.In September, 1911, respondents entered into a written contract with the city of Troy to improve Oalcwood avenue in said city. The contract called for widening the street and lowering and raising the grade at various places, including the construction of gutters, culverts, and catch-basins, as set out in the specifications in detail. Respondents thereafter began work about October 5th, and continued until January 9, 1912, when work was discontinued for the winter. Work was resumed on April 5th and continued until June 1st, at which time respondents notified the city in writing that the work under contract was completed. On May 14th respondent Doyle wrote to the city engineer, claiming that he had just learned that the grade stakes recently set for the work were not in accordance with the original plans and grades, but were at a lower elevation, thus increasing the cut on the work and decreasing the fill. He also claimed that this change of grade constituted a violation of the contract by the appellant. After respondents stopped work in June, a dispute arose between the parties as to whether the work contracted for had been in fact performed, and finally the city in the fall of 1912 completed the work claimed by it to have been left undone by respondents. Thereafter an action was brought by the contractors to recover for the work done by them on a quantum meruit. The case was tried before George Lawyer, Esq., as referee, and from the judgment entered upon his report this appeal is taken by defendant.
Respondents’ total claim is made up of many items valued at the'contract prices. Upon the trial all of these items and amounts, except two, were agreed upon by the parties. These two contested items were claimed by respondents to have been caused by the unauthorized change of grade during the progress of the work, as mentioned in the letter of May 14th. One was for 1,410 yards of hard macadam excavated, of the reasonable value of $1.50 per yard, or $2,115, and the other item was for 481 yards of earth re-excavated, of the reasonable value of 48 cents per yard, or $238.88. Upon the trial the respondents’ pleadings were amended to increase this first item in accordance with the proof to 1,711 yards, or $2,566.50, and the referee has allowed in full this item as thus amended. The other item he cut down to 450 yards, or $216, and as such has allowed it. Although the evidence ■on this latter item is not altogether convincing, we think his finding thereon is not against the weight of evidence. With regard to the first item mentioned, however, a more serious doubt arises.
At the time this contract was entered into the contractors received from the city engineer a certain map or profile, and grade or slope stakes were set upon the street for their use. The work covered a distance of 1,500 feet along the street, and along the middle of the street ran a single track, with a switch, of the United Traction Company. It seems to have been contemplated by the original plans for
Turning, now, from the engineers’ calculations, it may be helpful to consider any outside facts that may have a bearing on this point. It seems admitted that the intended change of grade was 5 inches only, and that the grade at the most was actually changed for 8 inches, if allowance is made for the error due to a bench mark being 3 inches too low. Respondent Doyle testified that the cut he made, due to the change of grade, extended only 1,050 feet. If, now, he had made a cut of 8 inches over the entire width of this 66-foot road, sidewalks', track, and all, for a distance of 1,050 feet, the amount of excavation would have been just 1,711 yards. A 5-inch cut would amount to 1,069 yards. But there is evidence by an engineer, who inspected this work after it was completed, that the only cut he found was for about 300 feet, and the track foreman of the Traction Company also testified that the track was not lowered for more than 300 feet of this en-
Another circumstance to be noted is the fact that, as the grade stakes were not set until about a month before the work was ended, the 450 yards of earth excavation and 1,711 yards of hard macadam excavation claimed would appear to be excessive amounts of work for the pay roll shown during this period. Some of the men on the job were used at other work than excavating during this time, so it seems improbable that as much macadam excavation as claimed could have been done in this time in addition to the re-excavation already allowed for. An examination of the entire record leads, in our judgment, to the conclusion that this item of 1,711 yards is contrary to the weight of evidence, and that an allowance of 1,000 yards of macadam excavated would give to plaintiffs full compensation. The judgment should therefore be modified, by reducing the amount of recovery for hard macadam excavated due to change of grade to 1,000 yards, at $1,50 per yard, or $1,500.
Judgment affirmed, as modified, without costs of this appeal to-either party. The'finding of fact of which the court disapproves is that 1,711 yards of hard madacam were excavated by respondents, due to a change of grade, and we hereby find that 1,000 yards only were excavated, of the reasonable worth and value of $1,500. •
Judgment modified, as per opinion, and, as modified, unanimously affirmed, without costs to either party. The finding of fact of which the court disapproves is that 1,711 yards of hard macadam were excavated by respondents, due to change of grade; and this court finds that 1,000 yards only were excavated, of the reasonable value of $1,500.