Majority
Headnote
1. Street Railroads @=34—Reconstruction and Relocation of Elevated Structure—Noncompliance with Orders of Public Service Commission'—Restraint bt Injunction.Plaintiff seeks to restrain the defendants from relocating or reconstructing the columns supporting the elevated struc
“Upon the Bowery between Chatham sanare and a point two hundred and ten.(210) feet southerly of the southerly line of Canal street, the additional tracks shall be located near the middle of the street and shall be constructed upon'longitudinal girders supported by cross girders resting upon the existing columns, strengthened as may be necessary or on new columns located on the sidewalk, so that the distance from their faces to the curb lines shall be the same as with existing columns, and no additional columns shall be there placed within the roadway of the Bowery between the existing curb lines. From said point two hundred and ten (210) feet southerly of the south? erly line of Canal street northward upon the Bowery to Sixth street the existing elevated structure may be relocated and reconstructed, provided the supporting columns as relocated and reconstructed shall be so placed that the center line of all columns placed between the curb lines shall be at a distance of not less than fourteen (14) feet from the curb line .and not less than seven (7) feet from the centers of any surface street railway tracks."
The railway company then proceeded to obtain the necessary consents from the property owners along the line, and, not having obtained a sufficient number, applied to the Appellate Division in this department for the appointment of three commissioners as prescribed by the Rapid Transit Act (Laws 1909, c. 498). The commissioners were appointed, and on the 10th day of February, 1914, filed their report that the said railway should be constructed and operated as determined by the certificate of the Public Service Commission of March 19, 1913. On the 27th day of February, 1914, the report of the commissioners was confirmed by the Appellate Division. Certain plans
[1, 2] The contention of the defendants that the plaintiff has been guilty of laches is untenable. A reading of the affidavits submitted discloses that whatever negotiations or conferences may have been had between the parties were for the purpose of avoiding litigation. The lapse of time between the starting of the work and the present is not so great as would warrant this court in depriving the plaintiff of any remedy it may have. While it has been repeatedly held in this state that the courts will not interfere in public improvements on any slight consideration, yet it has also been held that, when a corporation seeks to act under certain power granted to it, it must comply with the authority thus given to it. See Railroad Co. v. Davis, 43 N. Y. 137 ; Gray v. York State Telephone Co., 92 App. Div. 89 , 86 N. Y. Supp. 771 ; Eels v. American Telephone Co., 143 N. Y. 133 , 38 N. E. 202 , 25 L. R. A. 640 ; In re City of Buffalo, 78 N. Y. 362 ; Matter of Marsh, 71 N. Y. 315 ; Village of Canandaigua v. Benedict, 8 App. Div. 475 , 40 N. Y. Supp. 707 ; Knox v. Met. El. R'y, 58 Hun, 517 , 12 N. Y. Supp. 848 . As was said by Mr. Justice Bronson in Sharpe v. Speir, 4 Hill, 83 , a corporation must show a grant either in terms or by necessary implication for all the powers which it attempts to exercise. See, also, Dyckman v. Mayor, 5 N. Y. 439 .
The contention on the part of the defendants that it is impossible to comply with the requirements of the certificate issued by the Public Service Commission, by reason of the fact that the space between the curb and the railroad track .would not leave seven feet as required by the certificate, is a matter that might appeal to the said Public Service Commission, and they undoubtedly would have power to modify their certificate, but such objection is not available in this proceeding. The court is concerned not with the question whether the defendant railway corporation can comply with the certificate, but is as to what is the power of such corporation under the certificate issued to it. It is apparent, therefore, to me that the act of the defendant Manhattan Railway Company in reconstructing the columns on the sidewalk in front of the premises of the plaintiff is in clear violation of the authority granted to the railway corporation, and the motion to continue the injunction pendente lite must be granted.
Settle order on notice.
Cases cited
- Rensselaer & Saratoga Railroad v. Davis 43 N. Y. 137 p. 969
- Eels v. American Telephone & Telegraph Co. 143 N. Y. 133 p. 969
- In re City of Buffalo 78 N. Y. 362 p. 969
- In re Marsh 71 N. Y. 315 p. 969
- Village of Canandaigua v. Benedict 8 App. Div. 475 p. 969