Majority
Headnote
1. Judgment @=>678—Res Judicata—Action to Foreclose Mechanic’s Lien.This action was brought to recover a balance alto provisions of a contract in writing, made by the parties to this action on the 1st day of March, 1904, by which the plaintiff, therein designated as the contractor, agreed to furnish and provide all materials and perform all the' work necessary for the erection of an office building on premises owned by defendant, likewise designated owner, in the city of Binghamton, N. Y., according to plans, drawings, and specifications to be furnished by the architects of the owner; the building to be completed on or about the 1st day of March, 1905, or within such additional time after that date as would equal the period that the contractor might be delayed by the owner in commencing the excavation after the 1st of April, 1904. The contract was construed by the parties as constituting the plaintiff superintendent of construction for defendant, notwithstanding certain general provisions designed to insure completion within the time specified, and such it was in effect at least as between the parties, for the owner agreed to reimburse the contractor for “the total necessary actual cost of all labor and material” and to pay it, evidently as compensation for its services, 5 per cent, in addition thereto', it being provided that the contractor should not receive a percentage on the cost price of any material which the owner might have and which might be used in the building, but only upon the expense in laying and using the same, and that in no event should the 5 per cent, exceed the sum of $25,000; and it was provided that the materials should be purchased pursuant to competitive bidding and from vendors and at prices approved by the owner, and that, unless otherwise agreed by the owner, all labor and services should also be employed pursuant to competitive bidding approved by the owner. The contract contained other provisions to the effect that the owner should pay the contractor monthly for the actual cost of labor and materials and the 5 per cent, in addition thereto, upon statements and vouchers to be submitted to the owner by the contractor; that the owner should have the right to retain out of any payments due an amount sufficient to indemnify it against any lien or claim chargeable to- the contractor, for which, if established, the owner might become liable; and that if, after final payment, the owner should be obliged to discharge any such lien, the contractor should reimburse it therefor; and that the owner should be at liberty to terminate the employment" of the contractor and to take possession of the work if the contractor should at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or materials of proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance, of any of its agreements, and such refusal, neglect, or failure should be certified by the architects, as therein provided. And it was provided that the contractor should pay, as liquidated damages, the sum of $100 per day for each and every
There is no controversy with respect to the cost of the work, or the amount of plaintiff’s percentage thereon, or the balance unpaid on either item. The only questions arise with respect to a claim made by the defendant to an offset against the amount claimed by the plaintiff, on account of two items of expenditure which it claims it was obliged to make, owing to acts of the plaintiff in violation of its duty under the contract.
On the 15th day of October, 1904, the plantiff, pursuant to the provisions of the contract, let the work “mentioned in the specifications and shown on the drawings” for the “Plain and Ornamental Plastering” to McNulty Bros., who agreed to complete it by the 28th day of November, 1904. By the provisions of the contract with McNulty Bros., the plaintiff was at liberty to terminate it for, among other things, their failure to prosecute the work with due diligence. On the 1st day of November, 1904, the architects employed by the owner wrote the plaintiff complaining of the manner in which the plastering work was being done; and on the 23d day of the same month the architects made a certificate in writing to the effect that McNulty Bros, had “failed to prosecute the work, provided for under and by the terms of their contract, with sufficient promptness and diligence to enable them to complete said work within the time and according to the terms of their contract, to wit, November 28, 1904, and that they have failed in the performance of the agreements contained in their said contract,” and that with the force of men employed by them it would be impossible to finish their work in less than six weeks, and that such failure “to furnish the necessary number of men and quantity of materials to finish said job within the time agreed upon is sufficient ground to terminate the employment of the said subcontractors on said job,” and on that day the defendant notified the plaintiff that it had, on the certificate of the architects, elected to terminate McNulty Bros.’ contract, and directed the plaintiff to terminate it by a formal notice inclosed, and to finish the work in accordance with the provisions of article 5 of the contract with McNulty Bros., which, in such case, authorized the plaintiff to take over the work and finish it for the account of McNulty Bros., accounting to them for any difference between the cost of completion and the balance unpaid on the contract and holding them liable for any excess of such costs. On the 25th day of that month, the plaintiff delivered a notice to McNulty Bros., under date of the 23d, to the effect that it would on the 29th, which was the day after the day on which McNulty Bros., were required to complete their work, take possession and finish the plastering pursuant to article 5 of the contract, and also delivered therewith the architects’ certificate and the defendant’s notice of its election to terminate the contract. The plaintiff took possession of the work covered by the McNulty Bros, contract on or about the 29th day of November, 1904, and completed the same by day labor. The actual and necessary cost of completion was duly certified
[1] On the 27th day of February, 1905, McNulty Bros, filed a mechanic’s lien against the premises for $11,000.93 on the agreed price and value of the labor and materials performed and furnished by them. They brought an action in the Supreme Court in Broome county to foreclose the lien, and made the plaintiff and defendant herein parties defendant, and in their complaint alleged that they were induced to abandon their contract under an agreement by the plaintiff herein to pay them the cost and expenses of the labor and materials performed and furnished and 10 per cent, in addition thereto, and alleged that the work was performed and the materials furnished with the knowledge, consent, and approval of the owner. Both defendants denied the making of the agreement and pleaded the facts herein stated in justification for the termination of the contract. On the trial of the issues in that action the court found that an oral agreement was made as alleged between the plaintiff and McNulty Bros, on the 26th day of November, 1904, and that any rights the defendants or either of them had or might have had to terminate the written contract “were waived, surrendered, and superseded by the oral agreement” between McNulty Bros, and the Andrew J. Robinson Company, and that the cost of the work and materials, with 10 per cent, added, was $10,522.63, which was also the reasonable value thereof, and a foreclosure was accordingly decreed. Both defendants appealed, but the judgment foreclosing the lien was affirmed without opinion. See 130 App. Div. 892 , 114 N. Y. Supp. 1135 . The judgment roll in that action was introduced in evidence on the trial of the issues herein by the plaintiff, and it is conceded that the findings, so far as material to the issues, are binding upon both parties. The defendant herein on March 3, 1909, paid that judgment, which with costs, disbursements, and interest aggregated the sum of $14,346.02; and that is the basis, of the other offset claimed by it. The court on the trial of the mechanic’s lien action also found that, at the time the oral agreement was made, certain work necessary to be performed by the plaintiff herein before McNulty Bros, could complete their contract had not been performed, and that-the condition and the amount and quantity of said work were such that the plaintiff herein was and would be unable to perform it on or before the date McNulty Bros, were required to complete their work, and that the nonperformance thereof did and would prevent McNulty Bros, from performing the contract on their part within the time specified therefor; that, by reason of the action of certain labor unions prior to the time of the making of the oral contract, the plaintiff herein was and would be unable to com
[2-6] No testimony was offered on the trial of this action. The evidence is wholly documentary and consists of the decision and judgment roll in the mechanic’s lien action, the certificates of the architects, notices from defendant to plaintiff and from plaintiff to McNulty Bros., and of admissions contained in the pleadings and made on the trial. With respect, therefore, to the matters concerning which findings were made in the other action, neither party offered any further evidence. Counsel for plaintiff, however, concedes that plaintiff had no “direction” from defendant to make the oral contract with Mc-Nulty Bros., by which it was found in the other action they were induced to surrender the work to plaintiff in an uncompleted condition. In view of that admission and of documentary evidence clearly showing that defendant, in authorizing plaintiff to terminate the contract with McNulty Bros., contemplated that such termination should be had, and that the work should be completed under and in accordance with the terms of the contract, it must be assumed that such oral contract was not authorized by the defendant. On the 28th of November, 1904, the defendant by letter gave plaintiff specific instructions with respect to completing the work in a manner to hold Mc-Nulty Bros, for any deficiency, and, so far as appears, plaintiff assumed to acquiesce without informing defendant with respect to the oral contract made two days before. If the court in the other action considered that the defendant authorized the oral contract, then it would have held defendant liable for any deficiency judgment, but plaintiff only was so held liable. Doubtless defendant was interested in having the work speedily finished, and in taking over the work for that purpose, but it was asserting that as a matter of right under the contract. Its attitude conferred no implied authority on plaintiff to make the oral contract, and there is nothing to indicate that plaintiff ever claimed to have received authority to make the oral contract or
[7] It is claimed that the ornamental plastering was not embraced in the contract with McNulty Bros., but that it is included in the amount claimed by defendant as the cost of completing that contract. The sole basis for that claim is an assertion made on the trial by counsel for plaintiff to the effect that the ornamental plastering, although expressly specified in the contract, was not included in the specifications, to which counsel for the defendant assented by saying that he would accept the statement of counsel for the plaintiff with respect thereto. We are unable to say from an examination of the specifications, which it is recited in the contract are for plain and ornamental plastering, whether they cover both or only the plain plaster. That is not material, however, for it was alleged in the answer and expressly admitted by the reply that the defendant “was obliged to and did furnish and complete said plastering work contracted to be done by said McNulty Bros, as aforesaid, for which it was obliged to and did pay, under the direction and with the approval of the plaintiff, the sum of $17,232.17.” The architects also duly certified under the contract, with a view to charging McNulty Bros, therefor, that this was the amount “actually and necessarily paid” by the owners for finishing the work covered by the contract; and it was found in the other action that this was the amount of expenses incurred by the owner in finishing the work. It is therefore too late for respondent to contend that the cost of completion, as shown, included other work.
[8] It appears that, owing to labor conditions, the defendant directed plaintiff, after the termination of the contract with McNulty Bros., to complete the contract by day labor, employing only union men, and that it was so completed. The claim is made by counsel for respondent that the cost of completion in such circumstances would not have been the measure of damages against McNulty Bros., and cannot be as against plaintiff. It appears, however, that the defendant expressly required that plaintiff pay no righer rate of wages than McNulty Bros, paid, and it must be assumed that plaintiff observed this requirement. On terminating the work for cause under the contract with McNulty Bros., plaintiff was not required to relet it by contract, but was unrestricted with respect to the manner in which the work should be finished. Unless, therefore, we are able to say by judicial notice that union labor is more expensive at the same rate than nonunion labor, which manifestly we cannot do, there is no basis for this contention.
We are therefore of opinion that the defendant should have been allowed the two offsets claimed by it, viz., $14,346.02, the amount of the McNulty Bros, judgment, which was paid on the 3d day of March, 1909, together with interest thereon to the date of the judgment, together aggregating $18,757.42, and the additional cost of completion over and above McNulty Bros.’ contract price, and 5 per cent, thereon, and 5 per cent, on said amount of $10,522.63, erroneously allowed to plaintiff by the judgment, and interest on these three items
It follows, therefore, that the judgment should be modified accordingly^ and, as modified, affirmed, without costs, and all findings of fact inconsistent with the views herein expressed are reversed and findings in accordance with these views will be made, and, on the settlement of the order, any question with respect to the computation of interest may be determined. Settle order on notice.
INGRAHAM, P. J., and McLAUGHLIN and CLARKE, JJ., concur. SCOTT, J., dissents.