Majority
Headnote
1. Municipal Corporations @=>360—Contracts—Stipulations—Power of Chief Engineer.This action was brought to recover the sum of $422,325.80, the amount claimed to be due under a contract for the construction of the Croton Falls reservoir. Plaintiff has recovered judgment in the sum of $35,388.95, and appeals from so much thereof as fails to give him the amount of certain claims, aggregating $270,-968.86, with interest. The judgment was entered by direction of the court, which dismissed the additional claims referred to, and refused to submit the issues involved in such claims to the jury. The Croton Falls reservoir, which is one of the largest in New York City’s Croton water system, was initiated under the original aqueduct commission, and after the abolition thereof was completed by the department of water supply, gas, and electricity of the city of New York, in which the powers of the former commission were vested by chapter 220, Laws of 1910. The contract was one for a unit price, as distinguished-from a lump sum. The questions in controversy arise over the action of the city’s engineer in claiming that certain units of the work should not be paid for at all, and that certain other units should be paid for at a less price per unit than that claimed by the contractor. The final estimate of the city’s engineer fixes the aggregate contract price at $4,319,-156.99. Plaintiff’s contention is that the correct amount is $4,590,-125.85. Of the amount shown by the final estimate, $31,697.29 had been withheld by the comptroller of the city of New York, and it is that amount, with interest, for which the plaintiff has recovered judgment, and from which judgment the city does not appeal. The balance, being the amount now in controversy, is made up of eight items. We shall state briefly the salient facts as to such of these claims as we think require our consideration:
[1-3] (1) Plaintiff claims that it placed class A monolithic concrete around the reinforcing rods in the main dam, above elevation 280.8, under due order from the engineer, and that it should have been allowed and paid therefor at the contract price of $7 per cubic yard (the price for class A concrete), instead of the amount finally allowed by the engineer, $2.65 per cubic yard (the contract price for cyclopean masonry). The difference in the contract price, based upon these two units, is $58,043.79.
9. The method of construction of the portion of the dam in question is as follows: Its faces are made of concrete blocks so placed in courses as to overlap or bond, and in every second course parts of the blocks extend inside the face and towards the center of the dam, being called “headers,” and forming a bond between the face and the interior mass.
In the winter of 1908-1909, Mr. Cook, the acting chief engineer, stated to the contractor that bad cracks had developed in the cross river dam, and that the engineers were considering reinforcing the dam in question to prevent a similar recurrence. To do this it was decided to place two-rows of rods inside the facing blocks above elevation 280.8, in the placing of which great care was required to be used by the engineer to lay the bars level and to insure a continuous straight line. The ends of the rods were forged into hooks, which were interlocked to form a continuous, taut, and level line along the entire length of the dam. Wedges were driven where necessary to keep this line taut, as it had to be perfect in alignment. When the rods were placed, they were surrounded with concrete. Before this reinforcing had begun the contractor claimed that it was physically impossible to place the bars in cyclopean masonry, and that the plan must be modified before the work reached the elevation in question, where the reinforcing was to begin; otherwise, the contractor would positively stop work. It claimed, as one reason for the inability to place reinforcing in cyclopean masonry, the irregularity of the large stones, projecting at different angles and at different heights, and the variation of shapes of the stones, which made the maintenance of perfect alignment through such construction impossible. The engineer, Cook,
There is a question as to whether Cook made a final classification, or only a tentative one. Plaintiff’s witnesses swear positively that the classification was a final and definite one, in reliance upon which they proceeded with their work. The engineer says that the words “limit for classification” upon the plan would indicate to the engineer that there were two classes of material to go in the dam other than the facing block, but would not indicate the kind of material that was to go in there. On cross-examination he testified that he said he “would not considér anything beyond a foot back of the headers, and that should be a classification pending future adjudication of whether they should be paid for the entire top of the dam, and whether this foot, or for none at all.” But it also appears, even from his cross-examination, that the contractor had announced its intention of stopping work unless the classification was made, and that the one foot finally indicated was a compromise between the three feet claimed by the contractor and the engineer’s disinclination to make any allowance at all. The contractor proceeded with the work, and it was properly performed; no large stones, such as are characteristic of cyclopean masonry, being used within the one-foot limit, but the rods being placed in a trench between the cyclopean stones and the back of the facing blocks, made level, and small stones being placed under the rods where necessary to effect such a level, the hooked ends being interlocked and forming a continuous, taut, and level line, wedges being used to accomplish that where necessary. The concrete was then filled in around, under, and over the bars, completely covering them to the depth of about a foot in this fresh concrete, small stones being placed therein by hand, and then more concrete being filled in to the next level, where more rods were to be laid. No heavy stones were used in this work, and care was required to maintain the tautness of the line of rods. The use of stones in class A concrete, within the direction of the engineer, was contemplated and provided for by the specifications, so that the presence of the stones therein did not destroy its character under the contract. As the work progressed (to all appearances satisfactorily), Cook, the acting chief engineer in charge, passed and approved the monthly estimates for July, September, and October, 1909, including allowances, as certified, in the first month named for 890 cubic yards
“I told him that in putting in the steel rods the spaces bad largely been filed up with concrete, due to the fact that large stones could not be introduced in those contracted spaces.”
Sears, who was not in good health, and whom it annoyed to hear an extended argument, ended the matter by saying that he had ruled at the cross river dam that cyclopean masonry must be reinforced, and that it would be a reversal of his prior ruling to allow it in the case of this dam, and therefore he compelled the deduction from the estimates for November of an amount equal to the allowance which had been made for the difference in the classification of this work from July to October, inclusive. The October estimate had been approved by Sears himself, as well as by Cook. Before the contractor was aware of the changed position of the chief engineer, he had completed the work in controversy, and so had no intimation of the change of ground of the city until the work had been done. In a letter to the aqueduct commissioners, dated December 27, 1909, Sears quoted a letter of his to Cook, dated December 14, 1909, in which he had requested a revision of the classification as to the point in controversy, and stands upon the proposition that section 96 of the contract contemplates the extensive use of steel for reinforcing the main dam, and that, as no provision was made for the reclassification of any part of the masonry of the main dam on account of reinforcing the same with steel, in his opinion the whole mass should be classified as cyclopean masonry. Cook, in answer to- the letter to him from Sears, said that he had estimated the masonry for one foot back from the tails of the headers as reinforced concrete; it being practically impossible to place cyclopean masonry as described in the specifications nearer than this limit to the blocks.
While it is perfectly true that the contract provides (section 96) that “portions of the concrete and other masonry shall, wherever shown on the contract drawings, and in other places, if required, be reinforced by imbedding in them twisted square steel rods, or other pieces of steel or iron of the number, shapes, and sizes directed,” it sufficiently appears that the insertion of the rods in question, adjusted and tautened as required to be done, was impossible of performance through the mass of cyclopean masonry from the very nature of that form of construction, and that it would only safely be imbedded in a mass of concrete, as it was actually carried out. And the contract defines class A concrete monolithic masonry (section 71) as “all concrete reinforced with steel rods not- otherwise classified,” and, after enumerating certain portions of the work at which it is to be used, further provides that it shall be used “at such other places as the engineer may direct.” Under
“Art. 3. To prevent disputes and litigations, the engineer shall in all cases determine the amount, quality, acceptability, and fitness of the several kinds of work and materials which are to be paid for under this contract, shall determine all questions in relation to said work and the construction thereof, and shall in all cases decide every question which may arise relative to the fulfillment of this contract on the part of the contractor. His estimate and decision shall be final and conclusive upon said contractor, and in case any question shall arise between the parties hereto, touching this contract, such estimate and decision shall be a condition precedent to the right of the contractor to receive any money under this contract.
“Art. 4. The engineer shall make all necessary explanations as to the meaning and intention of the specifications, shall give all orders and directions contemplated therein or thereby, and in every case where a difficult or unforeseen condition shall arise in the performance of the work required by this contract. Any differences or conflicts which may arise between the contractor and other contractors of the commissioners in regard to their wqrk shall be adjusted and determined by the engineer.”
It seems plain, therefore, that Cook as acting chief engineer, with full authority in the absence of Sears, had power under the clauses heretofore quoted to order the placing of class A masonry in the space up to the one-foot line, and as well to determine the nature and kind of the work thus done, so as to enable the contractor to be paid at the unit price fixed for such work. Cook concededly had been designated by the resolution of the aqueduct board as acting chief engineer during the absence of Sears, and was division engineer as well. Under the contract, the quantities of the different classes of work specified were approximate only, being given as a basis for a uniform comparison of bids, and the commissioners did not, expressly or by implication, agree that the actual amount of work would correspond therewith, but reserved the right to increase or decrease the quantity of any class or portion of the work, as might be deemed necessary by the engineer. (See contract, under heading “Statement of Quantities.”)
Upon these facts, and the others appearing in the record in detail, it would seem that questions of fact as to this first item were presented for the jury, and that plaintiff should have been allowed to go to the jury thereupon. It specifically asked to be allowed so to do upon the question of whether it had “placed monolithic concrete, class A, in any part of the main dam that was reinforced by the steel rods, namely, the part above elevation 280.8, and below the roadway, and inside the facing blocks, and outside a line one foot within the headers indicated by section 508 as limit for classification”; also as to whether the engineer had directed the contractor to put in class A concrete in the places described; also whether or not the action of the engineer in disallowing the allowance which had been made from July to October, inclusive, was arbitrary, and whether the mistake on his part in so doing was a palpable mistake. Not only were these questions for the jury, but there was an equally important question as to whether the classification made by Cook was a final one, upon the faith of which the contractor acted in proceeding with and completing the work which he was ordered to do, or whether it was simply a tentative and temporary arrangement, awaiting further adjustment.
“The question under this claim is, in my opinion, purely a legal and not an engineering one, depending upon the legal interpretation of the contract clauses above referred to, and the authority vested in Mr. Cook, as acting chief engineer, to change the classification of the masonry by the method adopted, and the validity of his ruling.”
This letter was excluded by the trial court after having been marked for identification. It would seem the offer came within the rule laid down in Uvalde Contracting Co. v. City of New York, 160 App. Div. 284 , 145 N. Y. Supp. 604 , that the final certificate and determination of the engineer are not binding upon the contractor where the engineer has attempted to interpret the contract and has erred upon an interpretation of the law applicable thereto. This letter should therefore have been received in evidence. It follows that the plaintiff’s claim under this first item, and the issues suggested regarding it, should have been submitted to the jury for determination.
[4] (2) Plaintiff claims that, having placed class B concrete around the drainage channel at the top of the main dam under due order by the engineer, it should have been allowed and paid therefor at the contract price of $5.50 per cubic yard (being the unit price for such concrete), instead of at the rate of $2.65 (the contract price of cyclopean masonry). The difference for the 988 cubic yards of construction, amounts to $2,815.80. Class B is monolithic concrete, not reinforced with steel bars. Such concrete was placed at each side of the drainage tunnel at the top of the main dam. The drainage tunnel was a modification of the original plan, not having been intended or provided for, but becoming necessary because of the determination reached during the progress of the work to run a highway across the top of the dam, thus necessitating a drainage system to prevent the pollution of the reservoir. Plans for this channel were prepared. The original contract drawings carried the cyclopean masonry in the interior of the dam as high as the concrete facing at the top surface. To carry out the new plan, forms were required to be used, and it was impossible to' lay cyclopean masonry in the narrow spaces left between the drainage tunnel and surrounding construction. Reinforcing steel was present in this section, adding to the impracticability of the use of the cyclopean masonry. No other class of construction than monolithic concrete class B could be used in this space, according to the statement of Cook, who gave orders for its use.
“I am inclined to question the authority of Acting Chief Engineer Cook to change the classification provided for in the contract, hy the method he adopted, and have some doubt as to the validity of his ruling.”
Section 71 of the contract provides that class B monolithic concrete shall be used at certain specified places and “at any other places that the engineer may direct.” This question is interwoven with the question presented in the first item, and therefore further discussion of it seems unnecessary; the conclusion reached being the same—that questions of fact were presented for the jury, indicated "by plaintiff’s attorney in his motion to go thereto, as follows: Whether the plaintiff placed monolithic concrete, class B, in that part of the main dam, between the drainage tunnel and an imaginary line one foot within the headers, as indicated upon the plan, by the direction of the engineer; whether the action of the engineer in disallowing the allowance that had been made in the estimates for July to November was arbitrary; and whether the mistake upon his part in so doing was a palpable mistake. The letter heretofore referred to from the chief engineer was, of course, relevant as well upon this point as showing that he had disallowed the claim solely as a matter of legal construction by him of the contract.
[5] (3) The contract provides that dimension stones shall be measured for- payment as of the “sizes of the smallest rectangular blocks from which the separate stones can be cut.” Section 89. The city’s chief engineer, Wegmann, in authority at the time when the stones in question (laid on the top of the waste weirs) were furnished, decided upon an allowance of three inches on all sides of the stone as reasonable. This allowance was reversed by De Varona, as chief engineer of the department of water supply, gas, and electricity, who made the basis of his computation the volume of a rectangular stone of the neat dimensions of the block to be used. The amount in controversy is
“The stones shall be cut to exact dimensions, and all angles and arrises shall be true, well-defined, and sharp.”
It sufficiently appears that in practice it is necessary to take a block substantially larger than the dimension stone in its final form and cut it down to the exact dimensions. It was apparent, as soon as work was about to commence on these dimension stones, that an allowance would have to be made for cutting, as it was physically impossible to cut the dimension stone from a rectangular block without some allowance f,or cutting away. Therefore, acting under the provisions of article 3 of the contract, the plaintiff submitted the question of such allowance for waste or loss to the chief engineer; plaintiff contending that it was entitled to six inches on all sides of the stone. After consideration, the chief engineer, on May 14, 1910, wrote the plaintiff as follows:
“Referring to my conversation of yesterday with your Mr. J. IP. C'ogan, I would say that I have instructed division engineer Cook, in making up his monthly estimates, to make an allowance of three inches around the net dimensions of dimension stone.”
In conformity with the practice thus indicated, the volume of the dimension stones was measured, and the allowance of three inches around each direction was included in the monthly estimates of March,’ April, and May, 1910. No question was raised as to the propriety of this allowance until Mr. De Varona succeeded to the control of the work. Thereafter, under his instructions, the allowance theretofore made was reduced so as to meet his views, with the consequent claim upon plaintiff’s part. An expert quarryman and stonecutter was called, whose company had furnished the dimension stones in qúestion, and whose testimony (by stipulation) was to the effect that:
The “sizes of the smallest rectangular blocks from which the separate dimension stone could in practice be cut are at least three inches on all sides larger than the. rectangular blocks which were taken by the engineers as the standard of measurement; that is, six inches longer, six inches higher and six inches wider. The measurements taken by the engineers was 7.485 feet in width, 2.818 feet in height, by the net length of the stone.”
The defendant called a witness, also an expert, who testified that:
“The smallest rectangular block from which any given stone can be cut is the size of the block which would be contained by the dimensions—the finished dimensions—of the given stone.”
Thus, an issue of fact was presented as to what was the smallest rectangular block from which these dimension stones could be cut. This was quite apart from the question of the effect to be given to the allowance by the then chief engineer of the three-inch limit as a reasonable one. Plaintiff specifically asked tó be allowed to go to the
The other items of the plaintiff’s claim which were dismissed, we think, were properly disposed of by the court, and do not require further discussion.
The judgment appealed from, in so far as it dismisses the three items of the plaintiff’s claim heretofore enumerated, will therefore be reversed, and a new trial ordered as to the same, with costs to the appellant to abide the event. Settle order on notice. All concur.