Majority
Headnote
1. Shipping @=177—Demubbage—Liability of Purchaser of Cabgo.[1, 2] Although this brick cargo was purchased without any bill of lading or assignment of the contract of carriage, by the act of purchase defendant undertook to unload without unreasonable delay, as well as to pay for any additional towage and wharfage caused by ordering the discharging berth to be shifted. Houge v. Woodruff (D. C.) 19 Fed. 136 . As vendor of the cargo, plaintiff was entitled to hold the vendee for any loss occasioned by his delay in taking delivery of the goods. Personal Property Law (Laws of 1911, c. 571) § 132. Having a temporary possession of the brick barge, plaintiff could recover any damages for detaining the barge beyond a reasonable period for her discharge, since presumably he could otherwise employ the barge, or, if he chose, turn the barge back to its owner.
[3, 4] On November 17, 1913, defendant purchased this cargo. Up to January 1, 1914, weather conditions were favorable for discharging. But it was not till March 12th that the cargo was out. The question of the brick’s quality, including its alleged rejection and defendant’s repurchase of it in January, were left to the jury, with the controverted testimony as to the daily rate to unload such a cargo, as well as the effect of a trade custom for other dealers in brick to take and pay for portions of such cargoes, by delivery from the barge’s rail.
Defendant urges that the court should have charged defendant’s request that:
“It was incumbent upon the plaintiff to protect the brick from the weather while it was on the barge.”
After remarking that there was no evidence on the subject, the learned court said:
“I suppose it was the plaintiff’s business to exercise reasonable care for the protection of the brick until it was actually taken in charge of by the defendant. * * * I will leave it to the jury to say in this case, from all the facts and circumstances, who, if either of these parties, was responsible for any damage done to the brick while on the barge.”
The answer had pleaded that after this alleged repurchase—that is, while the. barge was at 133d street, Manhattanville—there was severe cold and freezing weather, when the brick, being uncovered, froze to the deck. This was set up to excuse delay in' taking the brick at that time, and not as a counterclaim. But if defendant had not attempted to rescind the contract of purchase, and the discharge had gone on with ordinary dispatch, the cargo should have been all unladen before January 1st. After that, the vessel could be considered as on demur-
[5] The plaintiff proved payment of the hire of the barge at $5 a day, and $38 for extra towage in shifting the barge to three different unloading berths. The summons and complaint were served on March 31st, but this payment appears to have been receipted for on April 4th, five days after suit brought. The action, however, was not premature. Proof of detention, with a market value for use of such a craft, made out plaintiff’s right of action. This receipted bill was evidence to protect defendant against a possible double liability to the barge owner. While the cause of action must arise before beginning suit, the evidence to sustain it need not then be complete. Gillies v. Manhattan Beach Improvement Co., 147 N. Y. 420 , 42 N. E. 196 . We cannot say that the weight of evidence is against the verdict, or that the damages found were excessive.
The judgment and order are therefore affirmed, with costs. All concur.
Cases cited
- Baldwin v. Sullivan Timber Co. 142 N. Y. 279 at 285, 36 p. 836
- Gillies v. Manhattan Beach Improvement Co. 147 N. Y. 420 p. 836