Majority
Headnote
1. Damages <@=>80—Liquidated Damages—Building Contracts—Construc-This appeal involves purely a question of law. Plaintiff contracted to do some building work for defendants and to have it finished by a day certain. The contract also provided for liquidated damages at the rate of $10 a day for each day’s delay.
[2] The learned judge below was of opinion that, as defendants had permitted the plaintiff to finish the work after the date originally fixed for completion, this constituted a waiver of the right to recover the amount of damages liquidated by the terms of the contract, evenby way of counterclaim. I cannot concur in this view, and think that the decision in Deeves & Son v. Manhattan L. Ins. Co., 195 N. Y. 324 , 88 N. E. 395 , plainly indicates the contrary to be the correct rule. The acceptance of the work at the delayed day may quite properly be regarded as a waiver or abandonment of any defense to the action for the compensation provided in the contract; but, as said by the Court of Appeals, defendant is merely thereby remitted to a counterclaim for his damages, and in the case at bar these damages are fixed by the very contract upon which plaintiff seeks to recover.
Judgment modified, by reducing the amount of the recovery to the sum of $440.34, with interest from December 28, 1914-, and costs in the court below, and, as modified, affirmed, with costs of the appeal to the appellant; costs to be set off against the judgment. All concur.
Cases cited
- Mosler Safe Co. v. Maiden Lane Safe Deposit Co. 199 N. Y. 479 p. 221
- United States v. Bethlehem Steel Co. 205 U. S. 105 at 119, 27 p. 221
- Richard Deeves & Son v. Manhattan Life Insurance 195 N. Y. 324 p. 221