Majority
Headnote
1. Work and Labor <8=9—Effect of Express Contract.On the 17th of June, 1911, Nathan Herrmann, the defendant’s testator, offered to build for and donate to the Jewish Protectory & Aid Society, a charitable organization, a building for use as a trade school. His offer was formally accepted on July 21, 1911. Plaintiff is an architect, who, prior to the making of the offer by Plerrmann, had, at his request, prepared preliminary sketches for the building. After the acceptance of the offer Herrmann, on the 25th of July, 1911, entered into two written agreements with the plaintiff. The first provided for the erection by the plaintiff as contractor of a frame and stucco building in conformity with the preliminary sketches at a cost of not to exceed $18,800. The second provided that Herrman would pay the plaintiff 6 per cent, of $18,800, viz., $1,128 for—
■‘all architectural services required or desirable for the planning, erection and supervision of Nathan Herrmann Agricultural and Trade School building, •s * * the services to consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings, and of the general direction and supervision of the work. * * * ”
The complaint alleges, in substance, that subsequent to the making of these contracts the plans and specifications referred to therein were modified with the knowledge and consent of Dr. Charles Schram, Herrmann’s agent, which necessitated the drafting of new plans and specifications, with the result that the cost of the building was increased from $18,800 to $48,800, and that thereby the agreed and reasonable value of plaintiff’s services as architect was increased to 6 per cent, of the latter sum, viz., $2,928, of which only $828 has been paid. Judgment was demanded for the amount remaining due. The answer denied that there was anything due the plaintiff; that the agreements between him and defendants’ testator were ever modified or superseded, and set up a counterclaim for $30,000 damages alleged to have been caused by the plaintiff’s act in increasing the cost of the building from $18,800 to $48,800. The jury rendered a verdict in favor of the plaintiff for the amount claimed by him and against the defendants on their counterclaim. The defendants appeal from a judgment entered upon the verdict (the counterclaim not being mentioned or referred to therein) and an order denying a motion for a new trial, as well as an order granting plaintiff a certificate for costs.
The fact is undisputed that plaintiff did prepare plans and specifications for a much more elaborate building than that contemplated by the preliminary sketches, by reason of which the construction of the building cost $48,800 instead of $18,800, as originally planned. The main points of difference were that the plans and specifications provided for a basement under the entire building instead of under only a part, for the rearrangement of rooms, the addition of a balcony, and for the use of brick and stucco instead of frame and stucco.
[1] The question presented upon the appeal is whether or not, by
“Ton have heard what the committee desires; draw plans in accordance with those instructions; draw the building to be of brick; draw the building with the entire basement, and provide a balcony and place the assembly room on the ground floor.”
[2, 3] Any effect, however, which might be claimed from this testimony is completely destroyed when it was conclusively established that the meeting of the directors at which these changes were alleged •to have been ordered by Dr. Schram, and the alleged statements made by him, was held on July 20, 1911, five days before the contracts between Herrmann and the plaintiff were executed. It needs no argument to demonstrate the absurdity of the claim that these written instruments, fixing the rights and obligations of the parties to them, were modified by a conversation which took place prior to their execution. The written contracts were made for the sole purpose of fixing the rights of the parties, and any oral agreement theretofore had necessarily was merged in them. A contract cannot be changed or modified before it is made. When made, if it does not set forth the .agreement, by reason of a mutual mistake, or a mistake of one of the parties and the fraud of the other, then a reformation may be had. But so long as it remains in the form in which it was executed, the rights and obligations of the parties must be determined by it.
[4] The plaintiff, doubtless recognizing the force of this rule, asserts that Dr. Schram knew of and assented to the changes which were made in the plans and specifications and the construction of the building in accordance with them, and by reason of that fact Herrmann became bound, at least by implication, to pay the reasonable value of the services rendered, which was 6 per cent, of'the cost of the build
“The preliminary drawings may be changed or altered by the architect if deemed advisable in order to have them properly work out, but for that purpose only.”
Indeed, the acts of the plaintiff himself could hardly have done otherwise than have convinced Dr. Schram that the changes would not increase either the cost of the building or plaintiff’s compensation. Thus, on September 27, 1911, he sent a letter to Dr. Schram, advising him that an application had been made to the state board of charities to approve the plans and specifications. In this letter he said:
“I inclose a copy of original application, wherein you will notice at the bottom that I mentioned, the estimated cost §30,000.00; this I did only because this amount had been published before, and has no bearing on the actual cost. “ * * The problem was difficult to get a brick building for the price of a frame building, but I desired to do something extra to aid in the good cause Mr. Herrmann had in mind.”
Not only this, but during the progress of the work, between November 17, 1911, and June 13, 1913, he issued to himself as contractor 15 certificates calling for payments under the building contract. These certificates are on printed forms, filled out by plaintiff himself. Each of the first four reads in part as follows: “Contract price $18,800. 00. Extra work none. Deduction none. Total, $18,800.” The remaining eleven are in the same form, except that instead of the word “none,” after “Extra work” and “Deduction,” appear either dashes or blank spaces. In each of these certificates the balance is computed as the difference between $18,800 and the amount of the prior payments.
But even of more significance than these certificates are the two which plaintiff issued to himself as architect, and in which he certified that he.was entitled to payments under his written agreement of employment. This agreement, as before stated, specified that plaintiff’s compensation was to be $1,128, of which $225 was payable upon the completion of the preliminary studies and $450 upon completion of the specifications and general working drawings, exclusive of details. These sums were paid to plaintiff on September 9, 1911. The agreement also provided that an additional $153 should be paid upon completion of large scale and full-size detail drawings. On May 24, 1912, plaintiff certified that this payment was due. The certificate states the contract price as $1,128; the balance to be paid as $300, and mentions no claim for extra compensation. According to plaintiff’s testimony, he knew long before the second certificate was issued to him that the building would cost largely in excess of $18,800. The conclusion, therefore, is irresistible that at that time he did not consider that his written contract of employment had been modified in any way by the changes in the plans and the increased cost of the building. His every
[5,6] Herrmann died on August 23, 1912. At that time plaintiff as contractor had called for and received payments aggregating only $2,959.19 under the building contract. Of course whatever authority Dr. Schram had as Herrmann’s agent ceased upon the latter’s death, and nothing subsequently done by him could bind Herrmann’s estate, nor could the acts of Herrmann’s executors affect plaintiff’s rights against Herrmann’s estate. Chisolm v. Toplitz, 82 App. Div. 346 , 82 N. Y. Supp. 1081 , affirmed on opinion below 178 N. Y. 599 , 70 N. E. 1096 . The powers of the executors were limited. They could only discharge obligations legally incurred by their testator. This they did, making payments to the plaintiff on his certificates up to June 13, 1913, at which time he had received on the building contract substam tially the entire contract price, $18,784.96. Thereafter they refused to malee further payments or to complete the building, and on December 12, 1913, the Protectory completed the building at a cost of $30,-000, under the direction of its own superintendent.
[7] Plaintiff did not supervise the work done under the contract made by the Protectory, or have anything to do with it; in fact, he was ordered by the Protectory to keep away from the building. As already indicated, plaintiff had been paid, prior to Herrmann’s death, $828 out of $1,128, the price fixed for his services by the contract of employment. The balance of $300 was payable “upon completion of the building,” and was apparently intended to cover the general direction and supervision of the work, which was required of plaintiff by his contract. As he concededly did not perform a substantial portion of the work of supervision, and as he stands squarely upon a plea of complete performance, he is not entitled to recover such balance in this action. Hocla Iron Works v. Hall, 115 App. Div. 126 , 100 N. Y. Supp. 696 , Stern v. McKee, 70 App. Div. 142 ,, 75 N. Y. Supp. 157 ; La Chicotte v. Richmond R. & E. Co., 15 App. Div. 380 , 44 N. Y. Supp. 75 .
Proper motions were made to dismiss the complaint at the end of ’ plaintiff’s case, and renewed at the close of the evidence. The 'motions were denied and exceptions taken.
If the foregoing views be correct, then it follows that the judgment and orders appealed from must be reversed, with costs to the appellants, and the complaint dismissed, with costs. All concur.
Cases cited
- Chisholm v. Toplitz 82 App. Div. 346 p. 500
- Hecla Iron Works v. Hall 115 App. Div. 126 p. 500
- Stern v. McKee 70 App. Div. 142 p. 500
- La Chicotte v. Richmond Railway & Electric Co. 15 App. Div. 380 p. 500