← Cases

Logan v. Berkshire Apartment Ass'n

20 N.Y.S. 369 Court N.Y. City Ct. Decision date 1892-10-24 English

Delivered by Van Wyck, J.

Contents

Majority

p. 369
Logan et al. v. Berkshire Apartment Ass’n.
(City Court of New York General Term.
October 24, 1892.)

Headnote

Contract—Performance—“Satisfaction” of Party.
Plaintiffs made and delivered to defendant a hot-water pressure tank under a contract that it should be to defendant’s “entire satisfaction. ” A mistake in placing the manhole at the top instead of at the side was remedied after delivery by lowering the foundation so as to permit the passage of a man between the tank and the ceiling. Defendant then used the tank for nearly two years. Held, in an action for the price, that defendant could not complain of a charge declaring his liability in case merely of substantial performance of the contract.
Appeal from trial term.
p. 370
Action by William J. Logan and others against the Berkshire Apartment Association to recover for the price of a hot-water pressure tank furnished defendant. Judgment for plaintiffs. Defendant appeals. Affirmed.
For decision on former appeal, reversing a judgment of nonsuit, see 18 NY. Supp. 164 .
Argued before Van Wyck and McCarthy, JJ„
Stickney, Spencer & Ordway, for appellant. Lyon & Smith, for respondents.

The complaint alleges that plaintiffs agreed to make a hot-water pressure tank of certain dimensions for, and deliver the same to, defendant on foundation in cellar; that the same was so made and delivered; that an alteration was required by defendant; which plaintiffs made; and that defendant retained and still has possession and use of the same, but refuse» to pay therefor, although payment has been demanded of him. The answer contained only a general denial. The plaintiffs at the trial proved the contract fuller in detail than they had alleged it in the complaint, and this they had the right to do. The contract provided that the work was to be done “to-defendant’s entire satisfaction. ” Several of appellant’s objections are founded upon what he contends was error for the court to charge the jury “that plaintiffs were bound to furnish this work in such a manner that it complied substantially with the contract, and, if you find that the contract was substantially performed, the defendant is bound to pay.” This was not error against the defendant. Boiler Co. v. Garden, 101 N. Y. 387 , 4 N. E. Rep. 749 . The contract was simply to make for and deliver to defendant a chattel, and which was done September, 1890, and defendant had ever since retained and was still using it, for the purpose for which it was made, in May, 1892, the time of trial. Mr. Moran, the defendant’s superintendent, who made the contract, and concededly had full authority to act for defendant, testifies, at folio 120, as follows: “This tank is in our house now, and we are still using it. This tank was put upon the foundation in this way, and, with the exception that we lowered the foundation a little, it is now pretty near as it was'delivered to us in the first place, with the manhole still up.” The contract provided that this manhole should be on the side, whereas it was made on the top, of the tank, but plaintiffs testified that this mistake was easily remedied with defendant’s consent, and without altering the tank, by lowering the foundation, which would lower the tank so as to leave sufficient space between the ceiling of the cellar and the top of the tank to permit of a man entering it through this manhole, and Moran says that the foundation was so lowered. It is true that it was testified that defendant had been necessarily compelled to have some new flanges attached, by another machinist, to the tank, and it is equally true that plaintiffs testified that the flanges which were attached by them were perfect and complete; and hence that what defendant had caused to be done in this regard was entirely unnecessary. Remembering that defendant had not counterclaimed for the cost of these extra flanges, would it not seem that plaintiffs were entitled to a direction in their favor upon Mr. Moran’s evidence? However, the court refused to so charge as requested by plaintiffs at folio 163, and, notwithstanding the acceptance, retention, and use of the chattel by defendant for nearly two years, the court was indulgent to defendant, and charged that, before the jury could find for plaintiffs, they must decide, from all of the evidence, that plaintiffs had substantially performed their contract. The defendant’s complaint, in reference to this charge, is of no avail, and the verdict of a jury, which decrees payment for a tank which was retained and used for nearly two years after its delivery, must be sustained, unless some error of law was committed. The defendant’s exceptions do not seem substantial, in the view which has been taken of the pleadings and proof, and the judgment is affirmed, with costs.

Cases cited